99-002581
Clarence Rowe vs.
Oleander Power Project, L.P., And Department Of Environmental Protection
Status: Closed
Recommended Order on Monday, September 27, 1999.
Recommended Order on Monday, September 27, 1999.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8CLARENCE ROWE, )
11)
12Petitioner, )
14)
15vs. ) Case No. 99-2581
20)
21OLEANDER POWER PROJECT, L.P., and )
27DEPARTMENT OF ENVIRONMENTAL )
31PROTECTION, )
33)
34Respondents. )
36)
37RECOMMENDED ORDER
39An administrative hearing was conducted on August 30, 1999,
48in Viera, Florida, by Daniel Manry, Administrative Law Judge,
57Division of Administrative Hearings.
61APPEARANCES
62For Petitioner: Clarence Rowe, pro se
68418 Pennsylvania Avenue
71Rockledge, Florida 32955
74For Respondent, David S. Dee, Esquire
80Oleander Power Landers & Parsons
85Project, L.P.: 310 West College Ave nue
92Tallahassee, Florida 32301
95For Respondent, Scott A. Goorland, Esquire
101Department of W. Douglas Beason, Esquire
107Environmental Assistant General Counsel
111Protection: Department of Environmental Protection
116The Douglas Building
1193900 Commonwealth Boulevard
122Mail Station 35
125Tallahassee, Florida 32399-3000
128STATEMENT OF THE ISSUE
132The issue in this case is whether the Department of
142Environmental Protection ("DEP") should issue an air construction
152permit authorizing Oleander Power Project, L.P. ("Oleander"), to
162build and operate an electrical power plant in Brevard County,
172Florida, that includes five combustion turbines and two fuel oil
182storage tanks (the "Project").
187PRELIMINARY STATEMENT
189On November 24, 1998, Oleander filed an application with DEP
199for a permit authorizing the construction of certain stationary
208sources of airborne emissions (an "air construction permit"). On
218March 26, 1999, DEP issued a "Public Notice of Intent to Issue an
231Air Construction Permit" ("Public Notice"). The Public Notice
241included attachments comprised of DEPs draft "Air Construction
249Permit" (Permit No. PSD-FL-258; DEP File No. 0090180-001-AC)(the
"257Draft Permit"), "Technical Evaluation and Preliminary
264Determination," and "Best Available Control Technology
270Determination."
271By letter dated April 12, 1999, Petitioner requested an
280administrative hearing. On June 9, 1999, DEP referred the matter
290to the Division of Administrative Hearings ("DOAH") to conduct an
302administrative hearing.
304On June 23, 1999, Oleander filed a motion to dismiss for
315failure to comply with requirements prescribed in the Public
324Notice for a petition for administrative hearing. After hearing
333argument from both parties by telephone conference, the motion to
343dismiss was granted with leave to file an amended petition no
354later than July 19, 1999.
359On July 19, 1999, Petitioner timely filed a Petition for
369Administrative Hearing (the "Petition"). On July 27, 1999, an
379administrative hearing was scheduled for August 25, 1999, and
388subsequently rescheduled for August 30, 1999.
394At the administrative hearing, Oleander presented the
401testimony of four witnesses, each of whom was accepted as an
412expert. Mr. Richard Zwolak was accepted as an expert in land-use
423planning, land-use compatibility analyses, and socioeconomic and
430environmental impact assessments. Mr. Ken Kosky was accepted as
439an expert regarding air pollution control and best available
448control technology. Mr. Bob McCann was accepted as an expert in
459meteorology, air quality dispersion modeling, and air pollution
467impact assessments. Mr. Al Linero was accepted as an expert in
478air pollution control issues, DEP regulations that govern new
487sources of air pollution, and air permitting. Oleander submitted
496Exhibits 1-3, 5-17, 19-32, and 34-46 for admission in evidence.
506DEP did not call any witnesses or submit any exhibits for
517admission in evidence. Petitioner presented the testimony of one
526witness who was not tendered as an expert. Petitioner submitted
536Exhibits 1-12 for admission in evidence.
542Petitioner's request for public comment was granted. Five
550individuals entered un-sworn public comment on the record. The
559individuals were not placed under oath or cross-examined because
568the agency stated that it did not propose to "consider such
579material" within the meaning of Section 120.57(1)(b), Florida
587Statutes (1997). (All chapter and section references are to
596Florida Statutes (1997) unless otherwise stated.)
602The Petition included allegations of "environmental
608injustice" and harm to Petitioner's extended family and their
617progeny. Those allegations had been previously stricken from the
626Petition in response to Oleander's motion. At the administrative
635hearing, Oleander attempted to introduce evidence concerning
"642environmental justice" issues. DEP objected to the introduction
650of such evidence on the ground that DEP does not have
661jurisdiction to consider issues of environmental justice. DEPs
669objection was sustained, but Oleander was allowed to proffer its
679evidence concerning environmental justice.
683The identity of the witnesses and exhibits, and any
692attendant rulings, are set forth in the Transcript of the hearing
703filed on September 7, 1999. Petitioner did not file a proposed
714recommended order ("PRO"). Respondent timely filed its PRO on
725September 17, 1999.
728FINDINGS OF FACT
7311. Oleander seeks an air construction permit to build and
741operate an electrical power plant in Brevard County, Florida.
750Oleander provided reasonable assurances that the Project will
758comply with all of the conditions and emissions limitations
767prescribed by DEP in the Draft Permit.
7742. The Project received adequate review from the state
783agency responsible for regulating the Project. DEP reviewed
791Oleanders application, requested and received additional
797information concerning the Project, and independently verified
804the impacts assessments contained in the application.
8113. The Project received adequate review from Brevard
819County. Oleander executed a Stipulated Settlement Agreement with
827Brevard County (the " Brevard County Agreement") in which Oleander
837agreed to comply with restrictions concerning the Projects hours
846of operation, minimum buffers, noise, odor, vibrations, traffic,
854and other issues. The Brevard County Agreement provides
862additional assurances that the Project will not adversely impact
871the public.
8734. Members of the public received adequate notice of the
883Project and had sufficient opportunity to make public comments.
892On March 3, 1999, DEP held a public meeting in Brevard County to
905receive public comments regarding Oleanders application. On
912March 26, 1999, DEP issued its Public Notice of DEPs intent to
924grant the Draft Permit to Oleander. On April 8, 1999, DEPs
935Public Notice was published in Florida Today . On May 13, 1999,
947DEP held a second public meeting in Brevard County to receive
958public comments concerning Oleanders application. Members of
965the public had an opportunity during the administrative hearing
974to enter their comments on the record.
9815. The Project includes the construction and operation of
990five 190 megawatt ("MW") combustion turbines that will be used to
1003generate electricity. The Project also includes the construction
1011and use of two fuel oil storage tanks, two water storage tanks,
1023an administrative building, a stormwater management system, and
1031other associated and ancillary facilities.
10366. The Project is a "peaking" power plant. It will operate
1047only during times of peak demand caused by hot or cold weather or
1060storm events.
10627. The Draft Permit authorizes Oleander to operate the
1071Projects combustion turbines for a maximum of 3,390 hours per
1082year, or approximately 39 percent of the available hours in a
1093year. During the remainder of the year, the combustion turbines
1103will not operate and will not have any airborne emissions. Based
1114on the historical experience of other peaking power plants in
1124Florida, the combustion turbines are expected to operate less
1133than 800 hours per year.
11388. Oleanders combustio n turbines will be the most
1147advanced turbines used in Florida for peaking service.
1155Oleanders turbines will be more efficient, in terms of emissions
1165and producing power, than the turbines currently used at other
1175peaking plants in Florida.
11799. The Projec t will use General Electric ("GE") Frame 7FA
1192combustion turbines. These turbines are capable of complying
1200with the emission limits and requirements in the Draft Permit.
1210Oleander will hire staff or train their own staff to operate the
1222Project in compliance with the Draft Permit. Oleanders parent
1231company already has a training program for its plant operators.
1241Oleander has operated similar projects successfully.
124710. The primary fuel for the power plant will be natural
1258gas. Natural gas is the cleanest burning of all fossil fuels.
126911. In the event that natural gas becomes unavailable, the
1279Draft Permit authorizes use of low sulfur distillate fuel oil
1289("fuel oil") for the equivalent of 1,000 hours of full-load
1302operations per year. Fuel oil contains a maximum of 0.05 percent
1313sulfur, is 35 to 50 percent more expensive than natural gas, and
1325imposes economic incentives for Oleander to minimize the use of
1335fuel oil.
133712. Water needed for the Project will be provided by
1347the City of Cocoa. Oleander will not install any on-site wells
1358to supply water to the Project. All of the wastewater from the
1370Project will be sent by pipeline to the City of Cocoas
1381wastewater treatment plant. The Project will not discharge any
1390industrial wastewater on-site.
139313. The Projec t will be built on a site that is
1405located northeast of the intersection of Interstate 95 ("I-95")
1416and State Road ("SR") 520 in unincorporated Brevard County (the
"1428Site"). The Site contains approximately 38 acres of land.
143814. The Site is appropriate for use as an electrical power
1449plant. The Site already is zoned for industrial purposes. The
1459surrounding areas are primarily zoned for industrial uses. An
1468existing electrical substation is located on the north side of
1478the Site. An existing electrical transmission line corridor is
1487located on the west side of the Site. Townsend Road is located
1499on the south side of the Site. An existing natural gas pipeline
1511is located nearby, on the west side of I-95, and can provide gas
1524for the Project.
152715. Residential, commercial, and industrial development
1533within a three kilometer radius of the Site is minimal. The
1544Project will be compatible with those industrial and commercial
1553land uses that are located in the area near the Site.
156416. The closest residential areas are more than 1,400 feet
1575from the Site. The Site is compatible with the closest
1585residential neighborhoods. The Site and adjacent off-Site areas
1593provide a significant buffer to the closest residential areas.
1602The Site can be developed without causing adverse impacts on
1612residential areas.
161417. Combustion turbines currently operate at many
1621locations in diverse population centers in Florida. For example,
1630combustion turbines are operated within 800 feet of the Shands
1640Hospital at the University of Florida, within 1,200 feet of
1651Cinderellas Castle at Disney Worlds Magic Kingdom, and near the
1661Lake Worth High School. Combustion turbines also are located
1670near several residential neighborhoods in the state.
167718. DEP and Oleander evaluated the Project in accordance
1686with requirements prescribed in DEPs Prevention of Significant
1694Deterioration (" PSD") program. As part of the PSD review, a
1706determination was made of the Best Available Control Technology
1715(" BACT").
171819. A BACT determination involves a case-by-case analysis
1726of those air pollution control technologies that are feasible and
1736can achieve the maximum emission reductions. A BACT
1744determination also requires an analysis of the costs,
1752environmental impacts, and energy impacts associated with the use
1761of each one of the proposed control technologies.
176920. A BACT determination results in the establishment of an
1779emission limit for each pollutant of concern. In this case, DEP
1790determined the appropriate BACT limits for the Projects
1798emissions of carbon monoxide ("CO"), oxides of nitrogen (" NOx"),
1811sulfur dioxide (" SO 2 "), sulfuric acid mist ("SAM"), volatile
1824organic compounds (" VOCs"), particulate matter ("PM"), and
1835particulate matter less than ten microns in diameter (" PM 10 ").
1847(PM and PM 10 are referred to herein as "PM/ PM 10 . ") BACT emission
1863limits applicable to the Project are set forth in the Draft
1874Permit, and are incorporated by reference in this Recommended
1883Order.
188421. DEP determined that when the Project operates on
1893natural gas, BACT for NOx is an emission limit of 9 parts per
1906million (" ppm"), corrected to 15 percent oxygen. This emission
1917limit is based on the use of dry low NOx (" DLN") combustion
1931technology utilized in the combustion turbines included in the
1940Project. The proposed NOx emission limit of 9 ppm is the lowest
1952emission limit in Florida for simple cycle peaking power plants
1962and sets the standard for similar facilities throughout the
1971United States.
197322. DEP determined that when the Project operates on fuel
1983oil, BACT for NOx is an emission limit of 42 ppm, corrected to 15
1997percent oxygen. This emission limit is based on the use of DLN
2009and wet injection technology. Wet injection technology involves
2017the injection of either water or steam directly into the
2027combustor to lower the flame temperature and thereby reduce the
2037formation of NOx.
204023. The U.S. Fish and Wildlife Service (" USFWS") provided
2051comments to DEP concerning the Project. In their comments, the
2061USFWS suggested that the NOx emission limit should be 25 ppm when
2073the Project is operating with fuel oil. However, the USFWS
2083suggestion was based on the USFWS misreading of the provisions
2093of other PSD permits. When read correctly, those permits
2102establish the same NOx emission limit when firing fuel oil that
2113DEP established in this case, i.e., 42 ppm.
212124. In its BACT determination, DEP considered whether a
2130selective catalytic reduction (" SCR") system should be used to
2141reduce the Projects NOx emissions. SCR is an add-on NOx control
2152system in which ammonia is injected into the exhaust gases of a
2164combustion turbine. The exhaust gases are then exposed to a
2174catalyst where the ammonia and the NOx react to form nitrogen and
2186water.
218725. SCR does not represent BACT in this case and should not
2199be required for the Project. The use of SCR would impose
2210excessive costs on the Project, adversely impact the Projects
2219energy efficiency, and cause increased emissions of particulate
2227matter and ammonia.
223026. BACT for CO and VOCs is based on the Projects use of
2243an advanced combustor design, i.e., DLN technology, and good
2252combustion practices. The use of an oxidation catalyst for CO
2262removal is not required because an oxidation catalyst is not cost
2273effective for the Project. BACT for PM/ PM 10 , SO 2 , and SAM is
2287based on good combustion practices and the use of clean low
2298sulfur fuels.
230027. The PSD program establishes separate ambient air
2308quality standards for Class I and Class II areas defined in
2319Florida Administrative Code Rule 62-204.360(4). (Unless
2325otherwise stated, all references to rules are to rules
2334promulgated in the Florida Administrative Code in effect on the
2344date of this Recommended Order.) The Project is located in a
2355Class II area. The Projects impacts on ambient air
2364concentrations will be below all applicable PSD standards
2372("increments") prescribed in Rule 62-204.260(2) for Class II
2382areas.
238328. The nearest PSD Class I area is the Chassahowitzka
2393Wildlife Refuge (the "Refuge"). The Refuge is approximately 180
2403kilometers from the Site. An analysis of the Projects impacts
2413on the Refuge is not required because the Refuge is more than 150
2426kilometers from the Site. The impacts from the Project on the
2437closest Class I area are expected to be insignificant within the
2448meaning of Rule 62-204.200(29).
245229. DEP does not require Oleander to evaluate the
2461cumulative impacts caused by the Project and other major sources
2471of air pollution in the relevant Class II area. However,
2481Oleander evaluated the Projects impacts together with the
2489impacts of the Florida Power & Light Cape Canaveral Plant, the
2500Orlando Utilities Commissions Indian River Plant, and the
2508Orlando Utilities Commissions Stanton Energy Center. The
2515Project itself will not have any measurable effect on the ambient
2526conditions resulting from the operation of all of these sources.
253630. DEP has adopted prima ry and secondary Ambient Air
2546Quality Standards (" AAQS") in accordance with requirements
2555adopted by the U.S. Environmental Protection Agency ("EPA").
2565Primary standards are designed to create an adequate margin of
2575safety for the protection of the public health, including the
2585health of the young, the old, and those with respiratory diseases
2596such as asthma. Secondary standards are designed to protect the
2606public welfare from any known or anticipated adverse effects of
2616air pollution. AAQS are reviewed every five years by scientists
2626and physicians in light of the most recent scientific studies and
2637data.
263831. In Brevard County, existing air quality is better than
2648levels allowed under AAQS. Brevard County is classified as an
2658attainment area.
266032. Oleander anal yzed the Projects potential impacts on
2669ambient air quality in Brevard County in compliance with the
2679applicable DEP requirements for such an analysis. Oleanders
2687analysis was based on conservative assumptions intended to over-
2696estimate impacts from the Project. For example, the analysis
2705assumed that the Project would operate continuously throughout
2713the entire year, even though the Projects annual operations will
2723be limited to a maximum of 3,390 hours. In addition, Oleander
2735assumed that the Project would use fuel oil for the entire year,
2747even though the Project will be limited to firing fuel oil for a
2760maximum of 1,000 hours per year.
276733. The Projects maximum impacts on ambient air quality
2776will be 0.6 percent or less of the applicable AAQS for each
2788criteria pollutant. Oleander's analysis demonstrates a wide
2795margin of safety for public health and welfare.
280334. The Projects maximum potential impacts are less than
2812the EPA "significant impact" levels. Consequently, the Projects
2820impacts are deemed insignificant from a regulatory perspective,
2828and more detailed analyses of the Projects impacts on ambient
2838air quality are not required under applicable PSD requirements.
284735. The Project is not expected to cause any meaningful
2857impacts on air quality in any neighborhood in Brevard County. In
2868all neighborhoods, the Projects impacts on air quality will be
2878insignificant. Similarly, the Projects impacts on soils,
2885vegetation, wildlife, and visibility will be insignificant. The
2893Project also will not cause any significant growth-related air
2902quality impacts.
290436. The cumulative impacts from the Project and other
2913sources of air pollution in the area will be insignificant. When
2924all of these sources are considered together, the maximum impact
2934from their combined emissions will be 50 percent or less of the
2946applicable AAQS.
294837. The PSD program does not require Oleander to perform
2958any ambient air quality monitoring for any pollutant prior to the
2969time that construction of the Project commences because the
2978Projects air quality impacts will be less than the applicable
2988DEP de minimis levels. Pre-construction monitoring for ozone is
2997not required unless a facility will have VOC emissions equal to
3008or greater than 100 tons per year. The Projects maximum
3018potential VOC emissions will be 64 tons per year. Therefore, the
3029Draft Permit does not require Oleander to install any ozone
3039monitors.
304038. DEP maintains two ambient air quality monitors in
3049Brevard County to measure ozone concentrations. DEP also has
3058ambient air quality monitors for ozone in Volusia, Seminole,
3067Orange, Osceola, and St. Lucie Counties.
307339. The ambient air quality data from DEP monitors
3082demonstrate that the ozone concentrations in Brevard County are
3091below the applicable AAQS. Further, the data demonstrate that
3100ozone is a regional issue because the ozone levels in the region
3112tend to rise and fall at the same time and to the same degree.
312640. A requirement for Oleander to install an additional
3135monitor in Brevard County would be unnecessary and unjustified.
3144The impacts from the Project on ozone and other ambient air
3155quality parameters are so small that the impacts could not be
3166measured with an additional monitor. An additional monitor in
3175Brevard County would provide no meaningful benefits when
3183assessing whether Brevard County is meeting the AAQS for ozone
3193and would cost between $75,000 and $100,000 a year to install and
3207operate.
320841. Emissions from the Project will not cause any
3217significant impact on the water quality of water bodies in
3227Brevard County. There will be minimal, if any, "fallout" of
3237particles into nearby waters, including the St. Johns and Indian
3247Rivers.
324842. The maximum amount of nitrogen that could be deposited
3258annually as a result of airborne NOx emissions from the Project
3269is 0.0007 grams per square meter ("g/m 2" ). By comparison, the
3282current nitrogen deposition rate from other sources in the area
3292is 0.4 g/m 2 . Thus, the Projects impact on nitrogen deposition
3304in the area will be only a fraction of the deposition that is
3317occurring already.
331943. Airborne emissions from the Project will not cause or
3329significantly contribute to a violation of any ambient air
3338quality standard or PSD increment. The Project complies with all
3348applicable DEP air quality requirements, including the applicable
3356policies, rules, and statutes.
3360CONCLUSIONS OF LAW
336344. The Division of Administrative Hearings has
3370jurisdiction over the subject matter and the parties. The
3379parties were duly noticed for the hearing.
338645. Oleander has the ultimate burden of proof in t his
3397proceeding. Florida Department of Transportation v. J.W.C. Co.,
3405Inc. , 396 So. 2d 778, 787 (Fla. 1st DCA 1981). Oleander also has
3418the initial burden of presenting prima facie evidence that
3427Oleander has complied with all of the applicable DEP standards
3437and rules. J.W.C. 396 So. 2d at 788.
344546. If Oleander presents the requisite prima facie
3453evidence, Petitioner must present "contrary evidence of
3460equivalent quality" proving the truth of the allegations in the
3470Petition. J.W.C. 396 So. 2d at 789. Petitioner cannot satisfy
3480his evidentiary burden with speculative concerns about potential
3488or possible adverse environmental effects. See Chipola Basin
3496Protective Group, Inc. v. Florida Chapter Sierra Club , 11
3505F.A.L.R. 467, 481 (DER Final Order, May 29, 1988); J.T. McCormick
3516v. City of Jacksonville , 12 F.A.L.R. 960, 971 (DER Final Order,
3527January 22, 1990); Altman v. Kavanaugh , 15 F.A.L.R. 1588, 1576
3537(DOAH Recommended Order, adopted in pertinent part by DER Final
3547Order, November 1, 1991).
355147. Oleander presented c ompetent substantial evidence that:
3559(a) DEP properly determined BACT for the Project; (b) airborne
3569emissions from the Project will not cause or significantly
3578contribute to a violation of any ambient air quality standard or
3589PSD increment; (c) airborne emissions from the Project will have
3599no significant adverse impacts on water quality in any surface
3609waters; (d) airborne emissions from the Project will not cause
3619any significant adverse impacts on human health or the public
3629welfare; (e) the Project satisfies applicable DEP rules and
3638criteria; and (f) DEP should issue the air construction permit
3648for the Project.
365148. Petitioner failed to present "contrary evidence of
3659equivalent quality" proving the truth of the allegations in the
3669Petition. Petitioner speculated about potential impacts from the
3677Project but presented no competent substantial evidence to
3685support the allegations in the Petition.
369149. During the administrative hearing, members of the
3699public were allowed to enter comments on the record in accordance
3710with Section 120.57(1)(b). In relevant part, Section
3717120.57(1)(b) provides:
3719When appropriate, the general public may be
3726given an opportunity to present oral or
3733written communications. If the agency
3738proposes to consider such material, then all
3745parties shall be given an opportunity to
3752cross-examine or challenge or rebut the
3758material. (emphasis supplied)
376150. DOAH is not the "agency" for purposes of Section
3771120.57(1)(b). DOAH is defined separately in Section 120.52(5) as
3780the "Division." DEP is the "agency" for purposes of Section
3790120.57(1)(b). Compare , Section 120.52(1)(defining an "agency")
3797with Section 120.52(5)(defining the "Division").
380351. At the administrative hearing, five individuals were
3811allowed to comment on the Project so that DEP would have the
3823opportunity to hear additional comments from the public before
3832DEP presented its recommendation at the final hearing regarding
3841the Project. The five members of the public were not sworn or
3853placed under oath because DEP stated that it did not propose to
3865consider such material.
386852. Unsworn testimony is not competent substantial evidence
3876and cannot be used as the basis for a finding of fact. See
3889Department of Environmental Regulation v. Chemairspray, Inc. , 520
3897So. 2d 96, 97 (Fla. 4th DCA 1988); Leon Shaffer Golnick
3908Advertising, Inc. v. Cedar , 423 So. 2d 1015, 1017 (Fla. 4th DCA
39201982)("[t] rial judges cannot rely upon . . . unsworn statements
3932as the basis for making factual determinations; and [an
3941appellate] court cannot so consider them on review of the
3951record"). Accordingly, the un-sworn comments made by the public
3961at the administrative hearing cannot form the basis for a finding
3972of fact in this case.
397753. Even if the public comments at the hearing had been
3988sworn testimony, the comments were not probative of the issues in
3999this case. The five individuals who made public comments were
4009not competent to express the opinions included in the public
4019comments. Most of the individuals readily acknowledged that they
4028are not experts regarding the subjects for which they offered
4038opinions. See Warriner v. Doug Tower, Inc. , 180 So. 2d 384 (Fla.
40503rd DCA 1965)(testimony of expert on one subject was properly
4060stricken where expert acknowledged he was not qualified to
4069express an opinion regarding the issue in dispute). None of the
4080individuals who offered comments at the administrative hearing
4088established the required special knowledge, skill, experience, or
4096training to be competent to offer opinion testimony on the
4106technical issues involved in the evaluation of the Project. See
4116also Sections 90.701 and 90.702. That portion of the public
4126comments not comprised of opinion consisted of speculative
4134concerns about either possible adverse environmental impacts or
4142possible economic consequences for private property.
414854. The Petition alleges that DEP should consider
"4156environmental justice" issues when DEP evaluates the Project.
4164Petitioner alleges that the proposed agency action is
4172inconsistent with the provisions of President Clintons Executive
4180Order 12898, entitled "Federal Actions to Address Environmental
4188Justice in Minority Populations and Low-Income Populations."
4195Executive Order 12898 is designed to focus the attention of
4205federal agencies on "environmental justice."
421055. Executive Order 12898 requires federal agencies to
4218identify and address those situations where federal programs,
4226policies, and activities have disproportionate adverse impacts on
4234minority or low-income populations in the United States.
4242Environmental justice complaints are also evaluated by EPAs
4250Office of Civil Rights for compliance with Title VI of the Civil
4262Rights Act of 1964, when such complaints are based on allegations
4273of discrimination against minorities resulting from the issuance
4281of certain pollution control permits.
428656. The provisions of Executi ve Order 12898 are beyond the
4297scope of this proceeding and beyond the jurisdiction of DEP and
4308DOAH. Courts have consistently held that neither DEP nor DOAH
4318has jurisdiction to consider the provisions of Executive Order
432712898. See , e.g. , Council of the Lower Keys v. Charley Toppino
4338& Sons, Inc. , 429 So. 2d 67, 68 (Fla. 3rd DCA 1983)(issuance of
4351an air pollution permit by the Florida Department of
4360Environmental Regulation "must be based solely on compliance with
4369applicable pollution control standards and rules"; DER "is not
4378required or authorized" to deny such permit because of alleged
4388non-compliance with local zoning ordinances or land use
4396restrictions); Taylor v. Cedar Key Special Water and Sewerage
4405District , 590 So. 2d 481, 482 (Fla. 1st DCA 1991)(court adopted
4416holding in Council of the Lower Keys , above, with regard to a
4428water pollution permit, and then noted that "[r] emedies apart
4438from the permitting scheme are available" to address the
4447petitioners claims); see also Miller v. Department of
4455Environmental Regulation , 504 So. 2d 1325, 1327 (Fla. 1st DCA
44651987)(when considering whether a project would adversely affect
4473the "property of others," pursuant to DERs statutory authority
4482in dredge and fill cases under Section 403.918(2), DER did not
4493err by concluding that DER should not extend its review to
4504include consideration of non-environmental impacts).
450957. The issue in this proceeding is whether the Project
4519complies with state requirements for the issuance of an air
4529construction permit. Applicable requirements are set forth in
4537Chapter 403 and Rules 62-4, 62-204, 62-210, 62-212, 62-214, 62-
4547296, and 62-297. Nothing in the relevant statutes or rules
4557allows either DEP or DOAH to enforce the requirements of
4567Executive Order 12898.
457058. The undersigned sustained DEP's objection to the
4578submission of evidence by Oleander relevant to environmental
4586justice issues. Consideration of such evidence would have lacked
4595jurisdiction and would have been contrary to the law of the case
4607established in previous rulings in this proceeding. Oleander
4615proffered evidence that addressed environmental justice issues
4622generally, as well as the Projects direct compliance with
4631Executive Order 12898.
463459. Apart from any issue of environmental justice, Oleander
4643introduced competent substantial evidence to demonstrate that the
4651airborne emissions from the Project will not have any meaningful
4661adverse impacts on any neighborhood in Brevard County. In all
4671neighborhoods, the impacts from the Projects emissions will be
4680insignificant. The evidence also shows that the Project will be
4690compatible with, and will not adversely affect, any residential
4699neighborhood. Residential neighborhoods are distant and well-
4706buffered from the Site.
4710RECOMMENDATION
4711Based upon the findings of fact and conclusions of l aw, it
4723is
4724RECOMMENDED that:
4726DEP enter a final order granting Oleanders application for
4735an air construction permit for the Project, subject to the
4745conditions and limitations contained in the Draft Permit.
4753DONE AND ENTERED this 27th day of September , 1999, in
4763Tallahassee, Leon County, Florida.
4767___________________________________
4768DANIEL MANRY
4770Administrative Law Judge
4773Division of Administrative Hearings
4777The DeSoto Building
47801230 Apalachee Parkway
4783Tallahassee, Florida 32399-3060
4786(850) 488-9675 SUNCOM 278-9675
4790Fax Filing (850) 921-6847
4794www.doah.state.fl.us
4795Filed with the Clerk of the
4801Division of Administrative Hearings
4805this 27t h day of September, 1999.
4812COPIES FURNISHED:
4814F. Perry Odom, General Counsel
4819Department of Environmental Protection
4823The Douglas Building
48263900 Commonwealth Boulevard, Mail Station 35
4832Tallahassee, Florida 32399-3000
4835Kathy Carter, Agency Clerk
4839Office of General Counsel
4843Department of Environmental Protection
4847The Douglas Building
48503900 Commonwealth Boulevard, Mail Station 35
4856Tallahassee, Florida 32399-3000
4859Clarence Rowe
4861418 Pennsylvania Avenue
4864Rockledge, Florida 32955
4867David S. Dee, Esquire
4871Landers & Parsons
4874310 West College Avenue
4878Tallahassee, Florida 32301
4881W. Douglas Beason, Assistant General Counsel
4887Scott A. Goorland, Assistant General Counsel
4893Department of Environmental Protection
4897The Douglas Building
49003900 Commonwealth Boulevard, Mail Station 35
4906Tallahassee, Florida 32399-3000
4909NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
4915All parties have the right to submit written exceptions within 15
4926days from the date of this Recommended Order. Any exceptions to
4937this Recommended Order should be filed with the agency that will
4948issue the Final Order in this case.
![](/images/view_pdf.png)
- Date
- Proceedings
- Date: 10/12/1999
- Proceedings: Department of Environmental Protection`s Exceptions to the Recommended Order filed.
- Date: 09/21/1999
- Proceedings: Affidavit of Court Reporter filed.
- Date: 09/17/1999
- Proceedings: Department of Environmental Protection`s Proposed Recommended Order filed.
- Date: 09/17/1999
- Proceedings: CC: Letter to C. Rowe from J. T. LaVia, III (RE: deadline for filing proposed recommended Order) (filed via facsimile).
- Date: 09/17/1999
- Proceedings: Notice of Filing Proposed Recommended Order by Oleander Power Project; Recommended Order (for Judge Signature); Order (for Judge Signature); Disk filed.
- Date: 09/14/1999
- Proceedings: Letter to D. Arter from D. Dee Re: Errors in transcript; Exhibit 1 filed.
- Date: 09/08/1999
- Proceedings: Letter to C. Rowe from D. Dee Re: Filing proposed recommended Order (filed via facsimile).
- Date: 09/07/1999
- Proceedings: (2 Volumes) Transcript of Proceedings filed.
- Date: 08/30/1999
- Proceedings: CASE STATUS: Hearing Held.
- Date: 08/26/1999
- Proceedings: Oleander Power Project`s Notice of Filing Response to Clarence Rowe`s Request for Production of Documents; Oleander Power Project`s Response to Clarence Rowe`s Request for Production of Documents filed.
- Date: 08/26/1999
- Proceedings: Oleander Power Project`s Notice of Serving Responses to Clarence Rowe`s First Set of Interrogatories filed.
- Date: 08/26/1999
- Proceedings: Letter to Judge Manry from C. Rowe Re: Order denying Extension of time filed.
- Date: 08/23/1999
- Proceedings: (5) Subpoena ad Testificandum (C. Rowe) filed.
- Date: 08/19/1999
- Proceedings: Clarence Rowe`s First Set of Interrogatories to Oleander Power Project, L.P.; Clarence Rowe`s Request for Production of Documents to Oleander Power Project, L. P. filed.
- Date: 08/16/1999
- Proceedings: Oleander Power Project`s Motion in Limine and Response to Rowe`s Request to Allow Public Testimony filed.
- Date: 08/12/1999
- Proceedings: Oleander Power Project`s Notice of Rowe`s Failure to Comply With Order Denying Extension of Time filed.
- Date: 08/10/1999
- Proceedings: Letter to Judge Manry from D. Dee Re: Letter dated 8/6/99; Letter to Judge Manry from C. Rowe Re: Two questions regarding hearing filed.
- Date: 08/09/1999
- Proceedings: Letter to Judge Manry from C. Rowe (RE: request for subpoena) filed.
- Date: 08/05/1999
- Proceedings: Subpoena Duces Tecum (D. Dee) filed.
- Date: 08/04/1999
- Proceedings: Order Denying Extension of Time sent out.
- Date: 07/30/1999
- Proceedings: Amended Notice of Hearing sent out. (hearing set for 9:30am; Viera; 8/30/99)
- Date: 07/30/1999
- Proceedings: Oleander Power Project`s Motion to Compel Discovery and Response to Rowe`s Motion for Extension of Time filed.
- Date: 07/30/1999
- Proceedings: Oleander Power Project`s Motion to Strike filed.
- Date: 07/29/1999
- Proceedings: (Petitioner) Motion for Extension of Time (filed via facsimile).
- Date: 07/27/1999
- Proceedings: Notice of Hearing sent out. (hearing set for 9:30am; Viera; 8/25/99)
- Date: 07/19/1999
- Proceedings: (C. Rowe) Petition for Administrative Hearing (filed via facsimile).
- Date: 07/09/1999
- Proceedings: Order sent out. (Motion to dismiss is granted with Leave to amend)
- Date: 07/09/1999
- Proceedings: (C. Fancy) Intent to Issue Air Construction Permit w/cover letter filed.
- Date: 07/02/1999
- Proceedings: Letter to Judge Manry from W. Beason Re: Requesting an Extension to respond to initial Order (filed via facsimile).
- Date: 06/23/1999
- Proceedings: Oleander Power Project`s Notice of Service of First Set of Interrogatories to Clarence Rowe; Oleander Power Project`s Request for Production of Documents to Clarence Rowe filed.
- Date: 06/23/1999
- Proceedings: Oleander Power Project`s First Set of Interrogatories to Clarence Rowe; Oleander Power Project`s Motion to Dismiss or in the Alternative Motion to Strike filed.
- Date: 06/18/1999
- Proceedings: Order Denying Consolidation sent out.
- Date: 06/16/1999
- Proceedings: Oleander Power Project`s Response to the Department of Environmental Protection`s Motion to Consolidate filed.
- Date: 06/15/1999
- Proceedings: Initial Order issued.
- Date: 06/09/1999
- Proceedings: Department of Environmental Protection`s Notice of Related Cases & Motion to Consolidate; Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Intent to Issue Air Construction Permit filed.