00-001526
Florida Engineers Management Corporation vs.
Joseph C. Cash, P.E.
Status: Closed
Recommended Order on Thursday, December 28, 2000.
Recommended Order on Thursday, December 28, 2000.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8FLORIDA ENGINEERS MANAGEMENT )
12CORPORATION, )
14)
15Petitioner, )
17)
18vs. ) Case No. 00-1526
23)
24JOSEPH C. CASH, )
28)
29Respondent. )
31______________________________)
32RECOMMENDED ORDER
34Robert E. Meale, Administrative Law Judge of the Division
43of Administrative Hearings, conducted the final hearing in Port
52Charlotte, Florida, on September 19, 2000.
58APPEARANCES
59For Petitioner: William H. Hollimon
64Ausley & McMullen
67227 South Calh oun Street
72Tallahassee, Florida 32301
75For Respondent: Joseph C. Cash
804422 Mundella Circle
83Port Charlotte, Florida 33948
87STATEMENT OF THE ISSUE
91The issue is whether Respondent engaged in negligence in
100the practice of engineering, in violation of Section
108471.033(1)(g), Florida Statutes.
111PRELIMINARY STATEMENT
113By Administrative Complaint dated January 6, 2000,
120Petitioner alleged that it is charged with providing
128administrative, investigative, and prosecutorial services to the
135Board of Professional Engineers, which is responsible for
143regulating the practice of engineering.
148The Administrative Complaint alleges that on May 27, 1999,
157Respondent submitted an engineering detail to the Charlotte
165County Building Department for use in the Le Porin Residence
175project. The Administrative Complaint alleges that Respondent
182submitted the detail sheet as a plans change to correct a
193problem with truss straps.
197The Administrative Complaint alleges that Respondents
203corrective measures were deficient because they failed to
211specify the required nailing to the truss, they loaded the
221TAPCON anchors beyond the capacity permitted by the 1997
230Standard Building Code, and they loaded the TAPCON anchors
239beyond the capacity recommended by the manufacturer. The
247Administrative Complaint alleges that Respondent therefore
253engaged in negligence in the practice of engineering, in
262violation of Section 471.033(1)(g), Florida Statutes.
268Respondent requested a formal hearing.
273At the hearing, Petitioner called one witness and offer ed
283into evidence six exhibits. Respondent called three witnesses
291and offered into evidence seven exhibits. All exhibits were
300admitted.
301The court reporter filed the Transcript on November 2,
3102000.
311FINDINGS OF FACT
3141. Respondent has been licensed as a professional engineer
323in Florida since 1968, holding license number 18122. He is a
334member of the American Society of Professional Engineers and the
344Florida Engineering Society.
3472. Respondent served as the engineer of record for the
357Le Porin residence in Charlotte County, Florida. This case
366arose from a complaint made by an official with the Charlotte
377County Building Department (Building Department) following the
384submission of what he concluded was an incomplete drawing by
394Respondent in connection with the Le Porin job.
4023. The present case addresses the sufficiency of the
411strapping of the roof truss to the concrete block wall of the
423Le Porin residence. Petitioner does not challenge the
431sufficiency of the straps themselves. Petitioner challenges the
439sufficiency of the nails attaching the top of the straps to the
451roof truss and the sufficiency of the anchors screwing the
461bottom of the straps into the concrete block wall.
4704. In response to the request of the Building Department
480official, Respondent submitted a Correction Detail on May 29,
4891999, to the Charlotte County Building Department. The purpose
498of the detail was to address a concern of the Building
509Department official about missing or missed truss straps. The
518text accompanying the detail asserts that the actual lift-up
527value is 1482 pounds. The text adds: Missed or missing truss
538straps with less than 1000 lbs. of up-lift . . .
5495. The diagram accompanying the detail shows an RT22TW
558retrofit strap extending from the truss down along the interior
568of two filled concrete blocks, which represent the uppermost two
578rows of blocks forming the exterior wall. The diagram depicts
588the strap as attached to the concrete blocks by three 3/16 x 2
601tapcons: one is in the filled center of the uppermost concrete
612block, one is in the solid base of the uppermost concrete block,
624and one is in the filled center of the second uppermost concrete
636block. The portion of the strap abutting the truss reveals six
647dots on alternating sides of the upper portion of the strap,
658although it is unclear if these dots represent nails.
6676. The diagram depicts the upper portion of the strap as
678running along the broad face of the rafter, but not extending
689across the top of the rafter and down the opposite side.
700Respondent supplied a sheet of specifications from the
708manufacturer of the strap, Hughes Manufacturing, Inc., which
716shows a strap extending along one face of the rafter, across the
728top of the rafter, and then down a short distance along the
740opposite face of the rafter. The manufacturers diagram depicts
749a strap with a stronger grip on the rafter than the strap
761depicted in Respondents diagram in his correction detail, which
770shows a strap merely running along one face of the rafter. In
782the manufacturers installation, nails are driven into both
790sides of the rafter; in Respondents installation, nails are
799driven into only one side of the rafter. Evidently, the
809corrective nature of the retrofit straps precluded the
817installation of them over the rafters that had already been
827enclosed by the roof.
8317. The manufacturers specifications show that the RT 22
840strap, which Respondent has proposed, is 14-gauge galvanized
848steel. The TW may refer to the fact that the strap is twisted
861by 90 degrees, so that it can be attached to the wide face of
875the rafter and the side of the concrete wall, which are
886perpendicular to each other. According to the manufacturers
894specifications, the RT 22 strap, which is 22 inches long and one
906inch wide, contains at least 18 symmetrically spaced, 3/16-inch
915holes for fasteners to attach the strap to the surfaces being
926secured. The manufacturers specifications state that the RT 22
935strap requires 18 16d nails, assuming that both surfaces to
945which the strap is being attached are wood.
9538. At least in a wood-on-wood application, the
961manufacturers specifications provide that the normal design
968load of the RT 22 strap is 1116 pounds and the uplift design
981load is 1782 pounds. The specifications note that the
990manufacturer has derived the design loads from the National
999Design Specification for Wood Construction, 1991 Edition.
10069. By letter dated June 1, 1999, to the Building
1016Department, Respondent provided additional information on the
1023strapping of the trusses at the LePorin residence. The letter
1033states that certain trusses were strapped with one RT22TW
1042(1484) instead of a previously indicated strap and that the
1052remedial action is satisfactory when used with [three]
10603/16 x 1 1/2 [long] (min.) Tapcons.
106710. By Plan Review Correction List dated June 3, 1999, the
1078Building Department cites, for two separate notes, the
1086requirement of Standard Building Code (SBC) B 1606.1, which
1095requires that all buildings must be designed to withstand
1104prescribed wind loads. The first note acknowledges the use in
1114the correction detail of three 3/16 Tapcons with straps to
1124correct a problem of missing truss straps. The first note
1134states that the attached specifications for Tapcons indicate
1142shear values of 510 pounds (680 pounds x 0.25 x 3 Tapcons) for
1155hollow block, and the note cautions that 510 pounds is
1165insufficient for 1000 pounds of uplift. The second note
1174requests a correction drawing for the missed straps showing a
1184value of at least 1000 pounds. This latter note appears to be
1196in reference to the truss straps with less than 1000 pounds
1207uplift, as described above in Respondents correction detail.
121511. By letter dated June 9, 1999, to the Building
1225Department, Respondent included manufacturers specifications
1230from Concrete Anchor Systems for the Tapcons. Respondent
1238explained that he used the strength design method for building
1248design. He contended that using the 4:1 ratio as a safety
1259factor, as sought by the plans examiner with whom Respondent had
1270been dealing, would mix working stress design and strength
1279design, which would be a poor engineering practice.
128712. The June 9 letter states that the manufacturer rates
1297at 1782 pounds uplift the RT22TW strap at 14-gauge thickness,
1307one inch width, and holes of 3/16 diameter. The letter
1317contends that this equates to 2004 pounds deformation load
1326(1 -.1875)(.0747)(33,000).
132913. The June 9 letter asserts that the manufacturer rates
1339an HFTM strap using six 3/16 x 1 1/4 inch Tapcons as capable of
1353resisting 1700 pounds of uplift. Doing the calculations for an
1363eccentric strap, Respondent determined that the manufacturers
1370data yield a strength of 1037 pounds, which exceeds the design
1381load of 1000 pounds.
138514. Noting that strength design uses factored loads, not
1394safety factors, Respondent contended in the June 9 letter that
1404the three Tapcons for the 3500-pound concrete at 3/16 x 1 1/4
1416is equal to 852 x 3 = 2556 (shear); 2556 -1 x 1000 = 0.4; and
14320.4 x the yield stress is equal to the nominal stress.
1443Combining this with the factored load, Respondent contended, is
1452good engineering practice and consistent with applicable codes.
146015. Accompanying Respondents June 9 letter is a June 9,
14701999, letter from ITWRamset/Red Head, which manufactures the
1478Tapcon anchors. The manufacturers letter sets forth the
1486ultimate shear failure loads of the 3/16 x 1 1/4 anchors; in
14983000 psi concrete, the shear strength is 852 pounds. The
1508manufacturers letter adds that a safety factor of 4:1 (or 25
1519percent of this ultimate load capacity) is used for long-term
1529static loads, not for short-term hurricane loads. The letter
1538warns that the performance characteristics of Tapcon anchors are
1547based on the embedment depth of the anchor and the base material
1559into which the anchor is installed.
156516. Accompanying materials describing the specifications
1571of the ITWRamset/Red Head Tapcon anchors state that, for
1580embedment in solid concrete, one 3/16 x 1 1/4 anchor provides
1591ultimate pullout strength of 581 pounds. (As noted by
1600Respondent in his proposed recommended order, 1 1/4 inches is
1610the depth to which the two-inch anchors would be embedded in
1621concrete.) The same materials describe the ultimate shear
1629strength for one 3/16 x 1 1/4 anchor, embedded in 3145 psi
1641hard rock concrete, as 852 pounds. A cautionary installation
1650note in the accompanying materials warns that safe working
1659loads for single installations under static loading should not
1668exceed 25% of ultimate load capacity.
167417. At the hearing, a state-certified general contractor
1682testified for Respondent. He has worked extensively with
1690Respondent for the past five years. Testifying that the general
1700contractor is responsible for installing the straps, the
1708contractor testified that he could drive six nails into the
1718strap, but, if the strap had been wrapped over, he could have
1730driven three nails on each side of the rafter.
173918. Petitioner has proved by clear and convincing evidence
1748that Respondents proposed method of attachment of the strap to
1758the rafter does not conform to the manufacturers specifications
1767and constitutes negligence in the practice of engineering. The
1776inability of Respondent to wrap the rafter was exacerbated by
1786his failure to specify the number, weight, and location of
1796nails. Without regard to whether such specifications are
1804required in typical situations, in this situation, involving a
1813retrofit of straps where a contractor and carpenter might be
1823unable easily to drive nails, the engineers specification of
1832the number, weight, and location of the nails was imperative.
184219. At the hearing, a state-registered structural engineer
1850testified for Respondent. Based on his analysis, the three
1859Tapcon anchors could safely withstand 1000 pounds of uplift.
186820. Respondents calculations use strength-design
1873analysis, not allowable stress design analysis, and there is a
1883question, under the SBC, as to the use of strength design in
1895masonry, at least for wind loads. At the hearing, a state-
1906registered engineer testified for Petitioner. He explained that
1914the use of masonry, in strength-design analysis, is of limited
1924usefulness, except for earthquakes, because of the difficulty in
1933using the correct load and resistance factors, and the preferred
1943characteristic of wood, as for wind loads, to resist higher
1953forces for shorter durations (as contrasted to steel and
1962masonry, whose ability to resist loads is unrelated to the
1972duration of the load).
197621. Petitioners engineer testified that the SBC employs a
1985testing affiliate, which has determined that the allowable
1993stress on each of the subject Tapcons is 183 pounds, so that
2005three Tapcons of the type specified could resist 549 pounds.
2015Even with the historical, although now controversial, factor
2023increasing the allowable stress for these three Tapcons by one-
2033third, they could still not resist a 1000-pound shear load.
204322. Petitioners evidence challenging the sufficiency of
2050the three Tapcon anchors is persuasive, but not quite clear and
2061convincing. As noted below, negligence in engineering is
2069especially dependent upon applied engineering practices and
2076principles, and the testimony of Respondents expert is
2084sufficient to insulate Respondent from an adverse finding as to
2094the Tapcon anchors.
2097CONCLUSIONS OF LAW
210023. The Division of Administrative Hearings has
2107jurisdiction over the subject matter. Section 120.57(1),
2114Florida Statutes. (All references to Sections are to Florida
2123Statutes. All references to Rules are to the Florida
2132Administrative Code.)
213424. Section 471.038(3) authorizes Petitioner, a Florida
2141not-for-profit corporation, to provide administrative,
2146investigative, and prosecutorial service to the Board of
2154Professional Engineers.
215625. Section 471.033(1)(g) authorizes the Board of
2163Engineering to impose discipline for negligence in the practice
2172of engineering.
217426. Rule 61G15-19.001(4) defines negligence as the
2181failure by a professional engineer to utilize due care in
2191performing in an engineering capacity or failing to have due
2201regard for acceptable standards of engineering principles.
220827. Rule 61G15-19.004(2)(m) provides that the minimum
2215penalty for negligence is a reprimand, two-year probation, and
2224$1000 fine. Such a combined penalty would be disproportionate
2233to the offense. Respondent has practiced engineering for many
2242years, and the record discloses no prior discipline. The
2251demonstrated insufficiency in his failure to specify the number,
2260weight, and location of nails, although significant, is an
2269omission that, given a careful contractor or even carpenter, may
2279well prove immaterial. The proper penalty is a reprimand.
2288RECOMMENDATION
2289It is
2291RECOMMENDED that the Board of Professional Engineers enter
2299a final order finding Respondent guilty of negligence in the
2309practice of engineering and issuing a reprimand.
2316DONE AND ENTERED this 28th day of December, 2000, in
2326Tallahassee, Leon County, Florida.
2330___________________________________
2331ROBERT E. MEALE
2334Administrative Law Judge
2337Division of Administrative Hearings
2341The DeSoto Building
23441230 Apalachee Parkway
2347Tallahassee, Florida 32399-3060
2350(850) 488-9675 SUNCOM 278-9675
2354Fax Filing (850) 921-6847
2358www.doah.state.fl.us
2359Filed with the Clerk of the
2365Division of Administrative Hearings
2369this 28th day of December, 2000.
2375COPIES FURNISHED:
2377Dennis Barton, Executive Director
2381Board of Professional Engineers
2385Florida Engineers Management Corporation
23891208 Hays Street
2392Tallahassee, Florida 32301
2395Barbara D. Auger, General Counsel
2400Department of Business and
2404Professional Regulation
24061940 North Monroe Street
2410Tallahassee, Florida 32399-0792
2413Natalie A. Lowe, Esquire
2417V.P. for Legal Affairs
2421Florida Engineers Management Corporation
24251208 Hays street
2428Tallahassee, Florida 32301
2431William H. Hollimon
2434Ausley & McMullen
2437227 South Calhoun Street
2441Tallahassee, Florida 32301
2444Joseph C. Cash
24474422 Mundella Circle
2450Port Charlotte, Florida 33948
2454NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
2460All parties have the right to submit written exceptions within
247015 days from the date of this recommended order. Any exceptions
2481to this recommended order must be filed with the agency that
2492will issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 12/28/2000
- Proceedings: Recommended Order issued (hearing held September 19, 2000) CASE CLOSED.
- PDF:
- Date: 11/16/2000
- Proceedings: Proposed Recommended Order (prepared by Petitioner, filed by Respondent via facsimile).
- PDF:
- Date: 11/06/2000
- Proceedings: Letter to Judge R. Meale from J. Cash In re: brief clarification of points in case filed.
- Date: 11/02/2000
- Proceedings: Transcript (Volume 1) filed.
- Date: 09/18/2000
- Proceedings: CASE STATUS: Hearing Held; see case file for applicable time frames.
- Date: 09/15/2000
- Proceedings: Order Denying Request for Continuance issued.
- Date: 09/15/2000
- Proceedings: Misch Data (V) filed.
- Date: 09/15/2000
- Proceedings: Hurricane Ties Comparable Design Analysis (IV) filed.
- Date: 09/15/2000
- Proceedings: Hurricane Ties Strength Test Data (III) filed.
- Date: 09/15/2000
- Proceedings: Hurricane Ties Design Data (II) filed.
- Date: 09/15/2000
- Proceedings: Hurricane Ties Connection Data filed.
- Date: 09/15/2000
- Proceedings: Deposition (of Jim Power and Sumary) filed.
- Date: 09/15/2000
- Proceedings: Letter to Judge Meale from J. Cash In re: Hearing Summary filed.
- PDF:
- Date: 09/14/2000
- Proceedings: Ltr. to Judge R. Meale from J. Cash In re: request for summary order without hearing filed.
- Date: 07/24/2000
- Proceedings: Subpoena Ad Testificandum (5) filed.
- Date: 07/24/2000
- Proceedings: Affidavit of Service (5) filed.
- PDF:
- Date: 07/14/2000
- Proceedings: Order Granting Continuance and Re-scheduling Hearing sent out. (hearing set for September 18, and 19, 2000; 9:00 a.m.; Port Charlotte, Fl.)
- PDF:
- Date: 07/12/2000
- Proceedings: Respondent`s Counsel`s Motion to Withdraw as Counsel of Record (filed via facsimile)
- Date: 06/26/2000
- Proceedings: Notice of Filing Discovery Request (Petitioner) filed.
- Date: 05/09/2000
- Proceedings: (Petitioner) Notice of Filing Response to Discovery filed.
- Date: 05/01/2000
- Proceedings: Respondent`s First Request for Production of Documents filed.
- PDF:
- Date: 04/20/2000
- Proceedings: Notice of Hearing sent out. (hearing set for July 17 and 18, 2000; 9:00 a.m.; Punta Gorda, FL)
- Date: 04/12/2000
- Proceedings: Initial Order issued.