05-002049PL
Florida Engineers Management Corporation vs.
Lester M. Maples, P.E.
Status: Closed
Recommended Order on Thursday, October 13, 2005.
Recommended Order on Thursday, October 13, 2005.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8FLORIDA ENGINEERS )
11MANAGEMENT CORPORATION, )
14)
15Petitioner, )
17)
18vs. ) Case No. 05-2049
23)
24LESTER M. MAPLES, P.E., )
29)
30Respondent. )
32)
33RECOMMENDED ORDER
35Pursuant to notice a hearing was held on August 11, 2005,
46in the above-styled case by Stephen F. Dean, assigned
55Administrative Law Judge of the Division of Administrative
63Hearings, in Panama City, Florida.
68APPEARANCES
69For Petitioner: Bruce A. Campbell, Esquire
75Florida Engineers Management Corp.
792507 Callaway Road, Suite 200
84Tallahassee, Florida 32303
87For Respondent: Alvin L. Petters, Esquire
93Peters and Scoon
9625 East 8th Street
100Panama City, Florida 32401
104STATEMENT OF THE ISSUE
108Did the Respondent violate the provisions of Chapter 471, Florida Statutes, as alleged in the Administrative Complaint?
125PRELIMINARY STATEMENT
127The Petitioner filed a two-count Administrative Complaint
134against the Respondent on April 1, 2005, alleging that the
144Respondent, a licensed professional engineer, violated Chapter
151471, Florida Statutes, by negligence in practice of engineering
160with regard to plans for the fire sprinkler system to be
171installed in the gymnasium at Gulf Coast Community College, and
181by failing to date said plans.
187The Respondent requested a formal hearing, to consider
195disputed factual allegations contained in the Administrative
202Complaint, and raised laches and the statute of limitations as
212affirmative defenses. The case was referred to the Division of
222Administrative Hearings to conduct the formal hearing.
229Prior to the hearing, the presiding Administrative Law
237Judge (ALJ) determined that the proceedings were not barred by
247laches or statute of limitations. At the hearing, the
256Respondent filed a motion to dismiss for failure to comply with
267Section 455.225(4), Florida Statutes, requiring a determination
274of probable cause by the probable cause panel. The ALJ
284presiding at the hearing denied the motion to dismiss, observing
294that laches did not apply in administrative proceedings against
303a board or agency, but that the Respondent was not precluded
314from showing that the delay in prosecution prevented the
323Respondent from presenting evidence due to loss, destruction or
332unavailability of evidence or testimony. This was shown to be a
343problem as evidence was presented. See Tx-p. 21.
351The Petitioner called four witnesses: Lester Maples, the
359Respondent; Gene Schmidt; Ken Caldwell; and Larry Simmons. The
368Petitioner introduced into the record Petitioner's Exhibits 1
376through 4. The Respondent called Chris Thomas and Richard
385Lovejoy as witnesses, and testified in his own behalf. The
395Respondent introduced Respondent's Exhibits 1 and 2 into the
404record. The parties stipulated to the introduction of Joint
413Exhibit 1, calculations which accompanied the original drawings
421and were a part of the plans package.
429Both parties filed Proposed Recommended Orders containing
436their proposed findings of fact and their arguments on the law,
447which were read and considered.
452FINDINGS OF FACT
4551. The Respondent is a licensed professional engineer.
4632. The Respondent holds license number PE 10214.
4713. The Respondent signed and sealed on or about
480November 15, 2001, a set of plans for the water fire sprinkler
492system for the new student gymnasium at Gulf Coast Community
502College consisting of three pages, and a set of calculations
512consisting of 14 pages for said sprinkler system. All
521discussions herein of sprinkler systems and the statutes related
530to such systems is limited to water-based systems.
5384. The calculations are intended to show that the
547performance of the sprinklers is sufficient in the area defined
557by the National Fire Protection Association (NFPA) standards as
566the hydraulically most demanding. The hydraulically most
573demanding area is the 1500 square feet fartherest away and
583highest from the "fire riser" or the source of water to feed to
596the system.
5985. The area defined as the hydraulically most demanding
607was identified on the plans as being in the southwest corner of
619the building, taking the top of the plan as pointing due north,
631or that portion of the building on the bottom, left corner of
643the building consisting of the women's showers and women's
652toilets.
6536. The calculations were generated by a computer based
662upon data provided on the size, height, length, and diameter of
673the pipes servicing the system and the number of sprinkler heads
684required in the hydraulically most demanding area. These
692calculations assume all the sprinkler heads in the hydraulically
701most demanding area will be activated, but no other sprinkler
711heads in the system will be activated.
7187. The calculations, Joint Exhibit 1, contained an error
727regarding the nodes and their length. See page 3 of Joint
738Exhibit 1, Nodes 20 and 25 at the bottom of the page. The best
752demonstrative evidence of the nature of the error is contained
762in Petitioner's Exhibit 3 in the diagram marked Piping
771Isometric. In sum, there should have been another node in the
782calculation of 61 feet.
7868. Testimony was received regarding the plans, their
794modification and actual construction of the system. The best
803presentation of the ultimate construction is represented in
811Respondent's Exhibit 1, which clearly shows two service pipes
820into the women's shower area. According to the uncontroverted
829testimony of the contractor, the intent was always to have two
840pipes servicing this area, one suspended under the other on the
851same set of supports, each pipe servicing the same number of
862heads in the area of the women's shower room. This was not
874adequately shown in the original drawings, and a second drawing
884clearly showing the two pipes was prepared to satisfy the
894general contractor.
8969. The calculations for the second pipe would be
905essentially the same as the first pipe because they are the same
917length and both have the same "load." There was testimony
927regarding new calculations supporting the plans, R-1, these
935calculations were introduced as R-2. They also show the
944pressure was adequate.
94710. The plans were approved by the State Fire Marshall's
957Office, by the Department of Education, and the Petitioner's
966expert witness opined that two pipes would supply sufficient
975water to service the area.
98011. Credible testimony was received that the quality and
989performance standards for valves, alarm checks, and switches
997were contained in the specifications provided to the bidders by
1007the general contractor. These were not necessary in the
1016Respondent's plan.
101812. Credible testimony was received that the entire
1026project had one classification of hazard occupancy, as stated on
1036the calculations, Joint Exhibit 1. No credible evidence was
1045received that electrical or mechanical rooms have a different
1054hazard occupancy and should have been treated any differently.
106313. The Board's witness testified that one of the design
1073approaches is hydraulic calculation, See Tx 75-75. It is clear
1083from the calculations, Joint Exhibit 1, that this was the method
1094used.
109514. The installation of the backflow preventer was the
1104responsibility of the general contractor and not part of the
1114Respondent's responsibility. Further, pipes, valves, etc., were
1121contained in the general contractor's specifications. Lastly,
1128there is a four-inch check valve shown in the detail for the
1140fire riser, which is a four-inch pipe and is the responsibility
1151of the Respondent.
115415. The source of water is city water, which is treated.
1165There would be no microbial corrosion concerns.
117216. The first page of the plans marked Petitioner's
1181Exhibit 1, shows the fire riser as being located in the
1192northwest corner of the building. The second and third pages
1202show the fire riser as being located in the northeast corner of
1214the building. Testimony was received concerning the
1221modification of the plans to conform to the location of the fire
1233main. Except for computation of the hydraulically most
1241demanding area, location of the riser is not particularly
1250important. The location of the fire riser was in fact, on the
1262northeast corner, and this was the location used for calculation
1272of the hydraulically most demanding area. The "as built"
1281drawings, Petitioner's Exhibit 2, clearly show the riser in its
1291proper location. To the extent that page one fails to reflect
1302the same location as pages two and three, it is of no real
1315significance.
131617. Under the contract for the sprinkler system, the
1325general contractor was responsible for providing water to the
1334fire riser and the sprinkler contractor was responsible for the
1344system from that point. In sum, the plans incorporated those
1354specifications given.
135618. Section 633.021(18), Florida Statutes, defines the
"1363point of service" as the point at which the underground piping
1374for a sprinkler system using water as the extinguishing agent
1384becomes used exclusively for the sprinkler system. The statute
1393provides that the point of service is designated by the engineer
1404who sealed the plans for a system of more than 50 heads.
141619. The Respondent was not responsible for designing or
1425presenting plans for the underground water service "mainward" of
1434the fire riser. The riser by definition is not underground
1444service. Therefore, the Respondent was not responsible for that
1453portion of the total system at which the point of service would
1465have been designated.
146820. No evidence was presented to establish that the
1477definition of point of service creates a requirement for an
1487engineer designing sprinkler design to control the system design
1496to that point. No evidence was presented regarding the
1505practices of the profession when this factual situation arises.
1514No evidence was presented on the importance of the point of
1525service in terms of a sprinkler system, and no testimony was
1536offered regarding how an engineer would sign and seal plans that
1547were beyond the scope of the work he was engaged to do.
1559Special Findings Regarding the Various Sets of Plans
156721. As stated above, there were several sets of plans
1577introduced at hearing. Petitioner's Exhibit 1 was identified as
1586the set of plans signed and sealed by the Respondent; however,
1597there was no evidence that these plans were used to build any
1609portion of the project. In fact, the testimony was to the
1620contrary, that these plans were expected to be modified and were
1631modified prior to construction.
163522. Petitioner's Exhibit 2 was identified by Mr. Caldwell
1644as a set of plans which he "red lined" as "as built" drawings
1657after the construction was completed. He did not identify what
1667iteration of the original plans he used; however, inspection and
1677comparison show that they are virtually identical to the set,
1687Petitioner's Exhibit 1. Mr. Caldwell qualified his additions to
1696the plans to state that they reflected only what he could see
1708without removal of tiles or materials.
171423. Respondent's Exhibit 1 was identified by Chris Thomas
1723as being plans that were amended to address the concerns of
1734Mr. Schmidt. These plans show two pipes where the original
1744plans showed one pipe servicing the women's shower room.
1753Because of the delay in prosecuting this case and the losses due
1765to storms these plans are received and accepted as definitive
1775because to do otherwise would raise due process issues the
1785Petitioner having been aware of the alleged problems since
1794before the plans were executed.
179924. No evidence was received regarding the customary
1807practice in signing and sealing multiple versions of plans.
181625. There was no evidence presented regarding amended
1824calculations in support of the drawings. In the absence of such
1835testimony, it is concluded that only one set of calculations
1845were prepared, and they were determined by the approving
1854authorities to be sufficient.
185826. The Respondent admits that he did not date the
1868calculations or the plans.
1872CONCLUSIONS OF LAW
187527. The Division of Administrative Hearings has
1882jurisdiction over the parties and subject matter pursuant to
1891Sections 120.57 and 455.225, Florida Statutes.
189728. The Board of Professional Engineers is authorized by
1906Section 471.033(1), Florida Statutes, to discipline licensed
1913professional engineers, and may revoke, suspend or otherwise
1921discipline them for violations of the statutes and rules
1930governing their professional conduct.
193429. Count I of the Administrative Complaint alleges
1942specifically that:
1944a. The Point of Service is not accurately
1952identified;
1953b. The classification of hazard occupancy is
1960not identified for specific rooms;
1965c. The plans do not provide a design
1973approach for the rooms primarily housing
1979electrical or mechanical equipment;
1983d. The plans show two different locations
1990for the water main riser and a different
1998water pressure than that used for
2004calculations;
2005e. The plans and calculations do not
2012specifically identify the water supply nor
2018consider the potential for microbial induced
2024corrosion;
2025f. The detail on the plans of the backflow
2034preventer shows a six inch pipe, but the
2042submitted check valve manufacturer's
2046information uses a four inch pipe;
2052g. The plans and specifications lack quality
2059and performance specifications for gate
2064valves, alarm checks, trim switch, gong
2070switch and tamper switches.
207430. The allegations contained in subparagraphs b, c, e, f,
2084and g, above, were not proven. See Finding of Facts 11, 12, 13,
209714, and 15.
210031. Considered in the light that the allegations of
2109subparagraph a, above, are alleged to be negligence in the
2119practice of professional engineering, they were not proven. See
2128Findings of Facts 18, 19, and 20. The facts did not identify in
2141the situation presented who would be responsible for identifying
2150the point of service, and clearly did not establish that this
2161was a substantive departure for standard engineering practice.
216932. Considered in the light that the allegations of
2178subparagraph d, above, are alleged to be negligence in the
2188practice of professional engineering, they were not proven. See
2197Findings of Facts 16 and 17. The facts did not clearly
2208establish that this was a substantive departure for standard
2217engineering practice. The allegations of subparagraph d, above,
2225were not proven.
222833. Regarding the allegations that the system as designed
2237would not provide sufficient service to the hydraulically most
2246demanding area, the facts reveal that the system as designed and
2257built provided sufficient service to the hydraulically most
2265demanding area. There was no question that the system was built
2276with two pipes serving the women's shower room, and the
2286Petitioner's expert opined that such service would meet the
2295requirements.
229634. The allegations in Count I were not proven.
230535. The Respondent admits that he did not date the plans
2316at the time he signed and sealed them. He explained that this
2328was because he viewed them as preliminary plans. He also
2338explained that he has changed his practice and now stamps
2348initial drawings as "Preliminary Drawings." This is a violation
2357of Florida Administrative Code Rule 61G15-23.002 and Section
2365471.033(1)(a), Florida Statutes. This is a technical violation,
2373the same one the Board found the Respondent guilty of violating
2384several years ago in preparing a set of contemporaneously drawn
2394plans. Since that time, the Respondent has altered his
2403procedures and practices to conform to the Board's rule.
241236. In light of the previous prosecution with identical
2421results in DOAH Case Number 02-0128 and the willingness of the
2432Respondent to admit not having properly dating the plans, it
2442would serve no useful purpose to fine the Respondent for this
2453technical violation after forcing him to defend the other
2462charges.
2463RECOMMENDATION
2464Based upon the foregoing Findings of Fact and Conclusions
2473of Law set forth herein, it is
2480RECOMMENDED that the Board dismiss the complaint against
2488the Respondent.
2490DONE AND ENTERED this 13th day of October, 2005, in
2500Tallahassee, Leon County, Florida.
2504S
2505__
2506STEPHEN F. DEAN
2509Administrative Law Judge
2512Division of Administrative Hearings
2516The DeSoto Building
25191230 Apalachee Parkway
2522Tallahassee, Florida 32399-3060
2525(850) 488-9675 SUNCOM 278-9675
2529Fax Filing (850) 921-6847
2533www.doah.state.fl.us
2534Filed with the Clerk of the
2540Division of Administrative Hearings
2544this 13th day of October, 2005.
2550COPIES FURNISHED :
2553Leon Biegalski, General Counsel
2557Department of Business and
2561Professional Regulation
25631940 North Monroe Street
2567Tallahassee, Florida 32399-2202
2570Bruce A. Campbell, Esquire
2574Florida Engineers Management Corp.
25782507 Callaway Road, Suite 200
2583Tallahassee, Florida 32303
2586Alvin L. Petters, Esquire
2590Peters and Scoon
259325 East 8th Street
2597Panama City, Florida 32401
2601Doug Sunshine, Esquire
2604V.P. for Legal Affairs
2608Florida Engineers Management Corp.
26122507 Callaway Road
2615Tallahassee, Florida 32303-5267
2618Paul J. Martin, Executive Director
2623Florida Engineers Management Corp.
26272507 Callaway Road
2630Tallahassee, Florida 32303-5267
2633NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
2639All parties have the right to submit written exceptions within
264915 days from the date of this recommended order. Any exceptions to
2661this recommended order should be filed with the agency that will
2672issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 05/24/2006
- Proceedings: Order Remanding the Case to the Division of Administrative Hearings filed with the Board of Professional Engineers.
- PDF:
- Date: 01/27/2006
- Proceedings: Letter to B. Campbell from A. Cole forwarding copy of Order issued on December 14, 2005.
- PDF:
- Date: 12/14/2005
- Proceedings: Order (Petitioner`s Motion to Reopen the Formal Hearing is denied).
- PDF:
- Date: 10/25/2005
- Proceedings: Respondent, Lester M. Maples` Response to Petitioner`s Motion to Reopen the Formal Hearing filed.
- PDF:
- Date: 10/13/2005
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 09/13/2005
- Proceedings: Proposed Findings of Fact and Conclusions of Law on Behalf of Respondent, Lester M. Maples, P.E. filed.
- Date: 08/11/2005
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 07/01/2005
- Proceedings: Notice of Serving Respondent`s First Set of Interrogatories to Petitioner, Florida Engineers Management Corporation filed.
- PDF:
- Date: 06/29/2005
- Proceedings: Notice of Serving Answers to Petitioner`s First Set of Interrogatories filed.
- PDF:
- Date: 06/22/2005
- Proceedings: Notice of Hearing (hearing set for August 11, 2005; 10:00 a.m., Central Time; Panama City, FL).
Case Information
- Judge:
- ELLA JANE P. DAVIS
- Date Filed:
- 06/06/2005
- Date Assignment:
- 05/24/2006
- Last Docket Entry:
- 12/18/2006
- Location:
- Panama City, Florida
- District:
- Northern
- Agency:
- ADOPTED IN PART OR MODIFIED
- Suffix:
- PL
Counsels
-
Bruce Campbell, Esquire
Address of Record -
Alvin Lee Peters, Esquire
Address of Record