07-002713EPP In Re: Progress Energy Florida, Crystal River Unit 3 Uprate Project Power Plant Siting Application No Pa77-09a2 vs. *
 Status: Closed
Recommended Order on Thursday, June 5, 2008.


View Dockets  
Summary: Recommend that the Power Plant Siting Board certify Florida Progress Energy`s Crystal River Unit 3 nuclear generating facility, including the 180 MW Uprate Project.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8IN RE: PROGRESS ENERGY )

13FLORIDA, CRYSTAL RIVER UNIT 3 )

19UPRATE PROJECT POWER PLANT ) Case No. 07-2713EPP

27SITING APPLICATION NO PA77-09A2 )

32)

33RECOMMENDED ORDER ON CERTIFICATION

37The certification hearing in this case was held on

46March 17, 2008, in Crystal River, Florida, before Administrative

55Law Judge Bram D. E. Canter of the Division of Administrative

66Hearings.

67APPEARANCES

68For Florida Power Corporation:

72Douglas S. Roberts, Esquire

76Virginia C. Dailey, Esquire

80Hopping Green & Sams, P.A.

85Post Office Box 6526

89Tallahassee, Florida 32314

92For the Florida Department of Environmental Protection:

99Toni Sturtevant, Esquire

102Department of Environmental Protection

106Douglas Building, Mail Station 35

1113900 Commonwealth Boulevard

114Tallahassee, Florida 32399-3000

117STATEMENT OF THE ISSUE

121The issue to be determined in this case is whether the Siting Board should certify Crystal River Unit 3 at the Crystal River Energy Complex in Citrus County, Florida, owned and

152operated by Florida Power Corporation, doing business as

160Progress Energy Florida, Inc. (Progress Energy).

166PRELIMINARY STATEMENT

168On June 12, 2007, Progress Energy filed its application for

178site certification with the Florida Department of Environmental

186Protection (Department), pursuant to the Florida Electrical

193Power Plant Siting Act, Chapter 403, Part II, Florida Statutes

203(2007), 1 and Florida Administrative Code Chapter 62-17. Copies

212of the application were distributed to other agencies for their

222review and copies were made available for public review at the

233local library. The application for certification was prompted

241by Progress Energy’s proposal to add 180 megawatts (MW) of

251nuclear-powered electrical generating capacity to Crystal River

258not previously been certified, it is the intent of Progress

268Energy and the Department that all of Crystal River Unit 3, both

280the existing facilities and the proposed Uprate Project, be

289certified at this time.

293On July 20, 2007, the Department issued a Determination of

303Incompleteness and requested additional information from

309Progress Energy concerning its application. On August 22, 2007,

318Progress Energy filed its responses to the Department’s

326Determination of Incompleteness. On September 11, 2007, the

334Department determined that the application was complete.

341On August 1, 2007, Citrus County issued its Determination

350of Compliance with Local Land Use Plans and Zoning, pursuant to

361Section 403.50665, Florida Statutes, finding that the Uprate

369Project was consistent with the comprehensive plan and zoning

378ordinances of Citrus County. Following public notice of the

387determination, no person filed a petition to challenge the

396County’s land use consistency determination.

401On February 1, 2008, the Department issued its Staff

410Analysis Report pursuant to Section 403.507(5), Florida

417Statutes. The Staff Analysis Report contained reports from

425other agencies and proposed Conditions of Certification.

432No person sought to intervene and participate as a party in

443the certification hearing. Progress Energy and the Department

451filed a Prehearing Stipulation in which no disputed issues of

461fact or law were identified.

466At the certification hearing, Progress Energy presented the

474live testimony of Ken Wilson, Harold Frediani, Jr., David

483Bruzek, and Kelly Gleaton. The pre-filed testimony of these

492witnesses was also presented by Progress Energy and accepted

501into evidence. Additional pre-filed testimony was presented and

509accepted into evidence for David Bear, Carl Bullock, Jason

518Collins, and Scott Osborne. Progress Energy’s Exhibits 1

526through 9 were admitted into evidence. The Department presented

535the testimony of Cindy Mulkey. The Department’s Exhibits 1 and

5452 were admitted into evidence. No agency other than the

555Department appeared at the hearing.

560Following the presentation of evidence by the parties, a

569hearing was held for the exclusive purpose of receiving

578testimony from members of the general public. Four members of

588the public provided testimony. None opposed the Uprate Project.

597On May 1, 2008, the Administrative Law Judge requested, and

607the parties agreed to file, supplemental written testimony and

616proposed findings of fact regarding the structures, operations,

624and permitting conditions associated with the existing Crystal

632River Unit 3 facilities. The parties jointly filed the

641supplemental information on May 23, 2008, which included

649additional sworn written testimony by Ken Wilson.

656The one-volume Transcript of the hearing was filed with the

666Division of Administrative Hearings. Progress Energy and the

674Department filed a joint proposed recommended order which was

683duly considered in the preparation of this Recommended Order.

692FINDINGS OF FACT

6951. Florida Power Corporation, doing business as Progress

703Energy Florida, Inc., is an investor-owned utility that provides

712electric service to more than 1.7 million customers in its

722Florida service area. Progress Energy’s service area covers

73020,000 square miles in 35 Florida counties.

7382. Crystal River Unit 3 is part of Progress Energy’s 738-

749acre Crystal River Energy Complex, which is located in an

759unincorporated area of northern Citrus County. Yankeetown,

766Inglis, and the City of Crystal River are within a five-mile

777radius of the Complex.

7813. The Crystal River Energy Complex has five electrical

790generating units. Units 1 and 2 are coal-fired units which were

801constructed in the 1960s and produce approximately 900 MW. Unit

8113 is a nuclear-powered unit that went into operation in 1977,

822and also generates about 900 MW. Units 4 and 5 are 750 MW coal-

836fired units which became operational in the mid-1980s after

845being certified under the Power Plant Siting Act. The

854electrical power generated by the five units is delivered to

864Progress Energy’s electrical transmission system through shared

871230 kV and 500 kV switchyards on the Crystal River Energy

882Complex site.

8844. Cooling water for Crystal River Units 1, 2, and 3 is

896withdrawn from an intake canal which connects to Crystal Bay and

907the Gulf of Mexico. Water is pulled from the intake canal by

919pumps, sent through the condensers for Units 1, 2 and 3, where

931it becomes heated, and then is carried out to Crystal Bay via

943the discharge canal. The discharge canal extends approximately

9511.2 miles offshore.

9545. Crystal River Units 1, 2, and 3 share a supplemental or

966“helper” cooling tower system, which uses mechanical draft

974towers through which air is moved by large fans. When the

985temperature of the combined discharge water approaches 96.5

993degrees Fahrenheit, heated water is withdrawn from the discharge

1002canal and sent through the helper tower cells to cool the water

1014enough so that when it is returned to the discharge canal, the

1026combined temperature in the water will not exceed the permitted

1036limit of 96.5 degrees F on a three-hour rolling average.

10466. Progress Energy operates a Mariculture Center at the

1055Complex, which is a multi-species marine hatchery established in

1064the early 1990’s to mitigate fisheries impacts caused by the

1074introduction of heated water into adjacent waters. Progress

1082Energy has also implemented a Department-approved manatee

1089protection plan that establishes a number of guidelines to

1098minimize adverse impacts to manatees at the intake and outfall

1108areas.

11097. A sea turtle monitoring and rescue program has been

1119initiated by Progress Energy to reduce potential sea turtle

1128strandings and mortalities at Crystal River Unit 3. Progress

1137Energy has implemented a Sea Turtle Rescue and Handling Guidance

1147program which provides instructions for sea turtle observation,

1155rescue, handling, notifications, and reporting requirements.

1161Rescued sea turtles are transferred to the Mariculture Center

1170for health evaluation, and either tagged and released or

1179transferred to a qualified center for treatment and

1187rehabilitation, as appropriate.

11908. The land uses in the area immediately surrounding the

1200Complex are primarily undeveloped agricultural and forested

1207lands, and some mining operations. Most of the area within a

1218five-mile radius of the Complex consists of agricultural,

1226industrial, or open lands. The nearest occupied residence is

1235over three miles away to the northeast.

12429. Since Unit 3 began operations, there has been active

1252mining and some rural residential and commercial development

1260along US 19 between Crystal River and the plant site, all of

1272which is more than five miles away.

1279Crystal River Unit 3 – Existing Facilities to be Certified

128910. Crystal River Unit 3 was not previously certified

1298under the Power Plant Siting Act, because it was under

1308construction before the Siting Act took effect. If the Uprate

1318Project is certified, it is the intent of Progress Energy and

1329the Department to make all of Unit 3 subject to the Conditions

1341of Certification and to the Siting Act.

134811. Unit 3 is a pressurized water nuclear reactor. The

1358unit operates in a baseload condition, which means it operates

1368on an almost continuous basis throughout the year except for

1378scheduled outages. The unit is composed of a primary and

1388secondary system. The primary system is comprised of the

1397nuclear reactor, four reactor cooling pumps, and two steam

1406generators. The steam generators convert the heat from the

1415nuclear reaction into steam that is transferred to the secondary

1425system. In the secondary system, the steam is used to drive a

1437steam turbine/electrical generator. Electricity is then sent to

1445the existing electrical onsite switchyards for distribution over

1453Progress Energy’s electrical transmission system.

145812. The condenser is essentially a large metal box with

1468thousands of small diameter tubes through which “circulating

1476water” is flowing. Steam from the steam turbines is introduced

1486into the condenser box and when the steam contacts the outer

1497wall of a water-laden tube, heat is drawn from the steam,

1508through the tube wall, and into the circulating water. This

1518causes the steam to cool and condense. The condensed steam,

1528called "condensate", is collected in the bottom of the box, and

1539recycled to minimize water consumption. Warmed water from Unit

15483 is then released to the discharge canal.

155613. The Unit 3 site is 26.86 acres of developed land

1567within the Crystal River Energy Complex. The site contains no

1577significant environmental features. No archaeological or

1583historical features have been found on the site, but Progress

1593Energy has agreed to consult with the Division of Historical

1603Resources if any archaeological or historical finds are made at

1613the site.

161514. The major components of Unit 3 to be certified are the

1627nuclear reactor and its related facilities. The facilities to

1636be certified include the control complex, the turbine building,

1645and auxiliary and intermediate buildings which are associated

1653with the normal operation of Unit 3, the nuclear administrative

1663building, plant administrative buildings, the technical support

1670center, and warehouse and support buildings, the Unit 3 intake

1680and discharge structures, and the reactor head storage building

1689and maintenance training facility.

169315. Unit 3 is supported by several common facilities that

1703also serve some or all of the other generating units at the

1715Complex. These common facilities include the helper cooling

1723towers along the discharge canal, onsite warehouses, site

1731administrative building, parking lots, electrical switchyards,

1737transmission lines and the site access road. The intake and

1747discharge canals also serve all of the existing units and are

1758considered to be common facilities for the Complex. These

1767common facilities are not being proposed for certification.

177516. There is a potable water treatment facility and a

1785domestic wastewater treatment plant that serve Units 1, 2 and 3.

1796No changes to these facilities are required for the Uprate

1806Project. Both are located outside of the Unit 3 certification

1816area.

1817Existing Permits

181917. There is an existing state industrial wastewater

1827permit that applies to the operation of all five generating

1837units at the Complex. This permit covers a series of basins

1848that act as settling and percolation ponds. The basins are

1858subject to a groundwater monitoring program to monitor for

1867compliance with state groundwater standards.

187218. Under federal delegation, the Department issued a

1880National Pollutant Discharge Elimination System (NPDES) permit

1887for Units 1, 2 and 3. The NPDES permit covers the discharge of

1900once-through condenser cooling water from Units 1, 2 and 3, Unit

19113’s auxiliary cooling water, treated coal pile runoff from Units

19211 and 2, and other liquid waste streams.

192919. The Department has also issued a Title V air operation

1940permit for the Crystal River Energy Complex that covers all five

1951generating units. This permit was issued by the Department

1960under the federal Clean Air Act, acting on behalf of the federal

1972EPA. Unit 3 does not have air emissions that are subject to the

1985permit, except for any air emissions from the existing helper

1995mechanical cooling towers. The Title V permit covers three

2004diesel generators for Unit 3 as unregulated air emissions units.

201420. Progress Energy is operating Crystal River Unit 3 in

2024compliance with all of the conditions of these permits.

203321. The result of certification of the Uprate Project

2042under the Siting Act will be the combining of all required state

2054permits into one complete set of Conditions of Certification.

2063Because several of the existing permits issued to Progress

2072Energy for Unit 3 cover other uncertified units at the Complex,

2083those permits would continue in force and would not be replaced

2094by the Conditions of Certification. Instead, those separate

2102permits are incorporated by reference in the body of, and

2112attached as appendices to, the proposed Conditions of

2120Certification.

212122. The common permits that apply to Unit 3 and other

2132units at the Complex, and which were described above as not part

2144of the Unit 3 certification, would not be renewed pursuant to

2155the Siting Act. They would be renewed under the “normal”

2165procedures applicable to other regulated industrial facilities.

2172However, modified and reissued permits, as they relate to Unit

21823, would be incorporated by reference into the Conditions of

2192Certification.

219323. The permits issued by the Department under the federal

2203Clean Air Act and Clean Water Act are not subject to the Florida

2216Power Plant Siting Act. The Siting Act provides that federal

2226permits are reviewed and issued separately by the Department,

2235but in coordination with the Siting Act process to the extent

2246possible. However, these federal permits would also be attached

2255to and incorporated into the Conditions of Certification for

2264Crystal River Unit 3. As those permits are modified or reissued

2275in the future, they would be incorporated.

228224. The Department has already issued a Prevention of

2291Significant Deterioration (PSD) permit for the proposed South

2299Cooling Tower. The PSD permit is also incorporated by reference

2309into the proposed Conditions of Certification.

231525. The conditions provide for post-certification review

2322of the proposed South Cooling Tower. Progress Energy will

2331design that tower and select its final site. Progress Energy

2341will then submit to the Department documentation on stormwater

2350management and wetland impacts, as well as a wetlands mitigation

2360plan, if necessary, for the cooling tower site. The Department

2370will then review and approve this tower under its Environmental

2380Resource Permitting requirements. Construction of the tower

2387cannot begin until the Department approves it. This post-

2396certification review is typical for power plant siting cases and

2406insures compliance with applicable agency criteria and

2413Conditions of Certification.

2416The Uprate Project

241926. The Uprate Project would add 180 MW of generating

2429capacity to Unit 3, for a total of 1,080 MW. The Uprate Project

2443does not affect the other four generating units within the

2453Crystal River Energy Complex.

245727. Unit 3 would not have to be physically expanded to

2468obtain the additional electrical generation. The Uprate Project

2476involves modifications and replacements of existing plant

2483components to increase the efficiency of the unit, principally

2492within the secondary system of the unit, as well as to support

2504increased electricity production.

250728. The Uprate Project would be undertaken in two phases.

2517In 2009, during an already-scheduled refueling outage and steam

2526generator replacement for Unit 3, the low pressure turbines and

2536electrical generator would be replaced or rebuilt, as needed.

2545Additionally, a number of secondary side components, including

2553heat exchangers and associated piping and valves, would be

2562modified or replaced. The net effect of these initial

2571modifications would be to increase the efficiency of the

2580secondary plant portion of Unit 3 so that the same primary plant

2592output results in approximately 40 MW greater electrical output.

260129. In the second stage of the Uprate Project, additional

2611plant modifications will be undertaken during a scheduled outage

2620in 2011. These modifications would include replacing the high

2629pressure turbines, replacing the condensate, feed-water booster

2636and circulating water pumps and/or motors to increase their flow

2646capacity, and other associated modifications. This second set

2654of modifications is expected to increase the electrical output

2663by an additional 140 MW, and allow Unit 3 to generate

2674approximately 1080 MW.

267730. The Uprate Project would include alterations that

2685would elevate Unit 3’s thermal, or warm water, discharge. As

2695one option for offsetting the increased thermal discharge,

2703Progress Energy has developed a conceptual design plan for a new

2714South Cooling Tower. The planned additional cooling tower would

2723also be operated to avoid or minimize increased flow to the

2734intake canal from Crystal Bay. This would be accomplished by

2744routing a portion of the new cooling tower’s discharge to the

2755intake canal, thus avoiding additional intake or withdrawal of

2764water from Crystal Bay.

276831. The modifications to the circulating water system

2776would be addressed in a detailed engineering study. Options

2785would be discussed with the regulatory agencies. These options

2794would be designed to result in equivalent or less thermal and

2805biological impacts compared to the cooling system that currently

2814exists. The options would maintain existing thermal discharge

2822limits for plant cooling water and minimize impacts to aquatic

2832organisms. The final design of the new South Cooling Tower

2842would be addressed as part of the National Pollutant Discharge

2852Elimination System permit renewal in 2009.

285832. Electricity generated at the Complex is distributed

2866from shared 230 kV and 500 kV switchyards on the site. The

2878Uprate Project will utilize these existing electrical

2885transmission lines. No changes to the transmission system are

2894required for the additional electricity that would be produced.

290333. The Uprate Project will not significantly alter fuel

2912utilization by Unit 3. Additional enriched fuel will be used in

2923the unit following the Uprate Project, through increases in the

2933size of the refueling batches, to supply the energy to support

2944operation of the unit at the higher power levels.

295334. The construction and operation of the uprated Unit 3

2963would not generate any hazardous wastes. Its construction and

2972operation would not cause any change in Progress Energy’s spent

2982fuel storage systems, which store spent nuclear fuel in onsite

2992facilities.

299335. In 2009 (in support of the more substantial uprate

3003activity in 2011), Progress Energy would request that the US

3013Nuclear Regulatory Commission increase the licensed rated

3020thermal output of Unit 3 from 2609 MW thermal to 3010 MW

3032thermal. In a nuclear power plant, the thermal capacity is

3042approximately three times greater than its electrical capacity.

3050Therefore, the plants are often identified by both their thermal

3060capacity (MWt) and their electrical capability (MWe).

3067Uprate Project Impacts

307036. Net environmental impacts associated with construction

3077and operation of the Uprate Project are expected to be minimal.

3088The principal impacts are related to the potential increase in

3098cooling water flow through Unit 3 following the Uprate Project’s

3108completion, and the potential effects of the increased

3116temperature of the cooling water. These effects are expected to

3126be offset by modifications to the circulating water system.

3135Construction impacts of the Uprate Project will be minimal, with

3145expected construction traffic volumes falling within acceptable

3152levels.

315337. The modifications involved in the Uprate Project would

3162be conducted within areas already used for electrical power

3171generation. Therefore, there are no expected impacts to

3179wildlife habitat. Only common bird species typical of

3187urban/industrial areas have been observed within the project

3195area. No threatened, endangered, or plant or animal species of

3205special concern (listed species) are found within the project

3214area. Wading birds classified as species of special concern by

3224the Fish and Wildlife Conservation Commission occasionally

3231forage within wetlands outside of the project area. Gopher

3240tortoises have been observed outside of the project area along

3250the rail line on the Crystal River Energy Complex. However, no

3261adverse impacts to listed species are anticipated as a result of

3272the Uprate Project. Construction “laydown” and parking areas

3280associated with the separate Steam Generator Replacement Project

3288for Unit 3 would also be utilized for the Uprate Project in

3300order to avoid or minimize impacts.

330638. No wetland habitat will be disturbed as a result of

3317the Uprate Project itself. The location of the proposed

3326supplemental cooling tower has not been finalized. The new

3335South Cooling Tower would be located to avoid and minimize

3345impacts to wetlands. If unavoidable wetland impacts would occur

3354at the site that is selected, appropriate mitigation would be

3364provided in accordance with a post-certification Environmental

3371Resource Review.

337339. The Uprate Project is expected to result in an

3383increase in heat produced by the Unit 3 reactor. This increase

3394in heat would result in an increase in the heat rejected by the

3407Unit 3 condenser to the circulating water which is then released

3418to the discharge canal. The heat rejection will increase by an

3429estimated 768 million Btu per hour, an increase of about 13

3440percent over current levels. Progress Energy can accommodate

3448this increase in rejected heat by increasing the circulating

3457water flow rate through Unit 3, by increasing the temperature

3467rise of the circulating water from Unit 3, or by increasing

3478both.

347940. The Unit 3 circulating water pumps may be modified to

3490increase their design flow rate by up to an additional 150,000

3502of the Unit 3 discharge water would decrease. However, if the

3513circulating water flow rate is not increased, the temperature of

3523the discharged water could increase due to the increased heat

3533rejection from the uprated unit. The actual operation is

3542expected to have results somewhere between these two extremes of

3552increased flow and increased temperature of the circulating

3560water.

356141. There are four potential adverse impacts that might

3570result from either increasing Unit 3’s circulating water flow or

3580increasing the temperature of the cooling water discharge from

3589Unit 3. First, there could be an increase in the temperature of

3601the water discharged into Crystal Bay. Second, there could be

3611an increase in the area of offshore waters affected by the

3622heated water discharge. Third, there could be an increase in

3632the number of aquatic organisms “impinged” or trapped on the

3642cooling water intake screens. Fourth, there could be an

3651increase in the number of aquatic organisms entrained in the

3661intake canal and the cooling system. Entrainment refers to

3670passage of eggs and early larval stage organisms through the

3680intake canal, intake screens, and ultimately through the

3688circulating cooling water system. However, Progress Energy

3695intends to avoid or minimize these potential environmental

3703impacts.

370442. To avoid or minimize the impacts of increased cooling

3714water flow and temperature, Progress Energy is evaluating a

3723series of modifications to the existing cooling water system,

3732including the installation of the South Cooling Tower. The

3741intake and flow modifications will be designed to reduce the

3751increased thermal load from the Uprate Project by removing

3760heated effluent from the discharge canal and to avoid or

3770minimize any net increase in the number of organisms being drawn

3781into Unit 3.

378443. The proposed new South Cooling Tower would be located

3794between the intake canal and discharge canal, west of Units 1, 2

3806and 3. Detailed design and location of the South Cooling Tower

3817would be addressed as part of the renewal of the NPDES permit

3829renewal in 2009. That renewed permit would be incorporated into

3839the conditions of certification for Unit 3.

384644. As part of potential cooling water modifications, the

3855South Cooling Tower could withdraw water from the discharge

3864canal to remove the incremental rejected heat anticipated by the

3874Uprate Project. The new South Cooling Tower would be designed

3884to dissipate the increased rejected heat from Unit 3. All or a

3896portion of the cooled water from the South Cooling Tower could

3907be returned to the discharge canal.

391345. In addition to offsetting the increased water

3921temperature, the South Cooling Tower design could be increased

3930in size and provide for the return or recirculation of a portion

3942of the cold water from the Cooling Tower to the intake canal

3954instead of releasing it to the discharge canal. Recirculation

3963of a portion of the South Cooling Tower’s effluent back to the

3975intake canal could be used to maintain the intake flow in the

3987intake canal so as not to increase the existing intake flow rate

3999from Crystal Bay. This would prevent an increase in entrainment

4009of aquatic organisms into the intake canal.

401646. Re-circulating a portion of the South Cooling Water

4025effluent to the intake canal should prevent any increase in

4035impingement associated with increased flow in the intake canal.

4044Although the uprate may result in an increase in through-screen

4054velocity, Progress Energy does not anticipate that this increase

4063in velocity would alter present impingement levels. If

4071increased impingement does occur, Progress Energy would take

4079further steps to avoid or minimize increased impingement.

408747. Progress Energy proposes to continue to evaluate the

4096entrainment and impingement impacts associated with the Uprate

4104Project. These impacts would be addressed during the NPDES

4113renewal which is scheduled for submittal in 2009. The Uprate

4123Project is not expected to have a negative impact to aquatic

4134species.

413548. Progress Energy currently mitigates the impacts on

4143aquatic organisms in the circulating water system in several

4152ways. It operates several helper cooling towers to reduce the

4162thermal discharges from these three units. It seasonally

4170reduces the condenser cooling water flow through Crystal River

4179Units 1 and 2 to reduce impingement and entrainment of aquatic

4190species. Pursuant to the current federal NPDES Permit, Progress

4199Energy also operates a multi-species mariculture facility within

4207the Crystal River Energy Complex. It raises several species of

4217important marine species, such as red drum, spotted sea trout,

4227and pink shrimp which are periodically released to adjacent

4236surface waters. Progress Energy’s mariculture operations have

4243contributed to the restoration of red drum and scallop fisheries

4253in the offshore and adjacent waters.

425949. The associated circulating cooling water flow rate

4267through the new South Cooling Tower will increase air emission

4277impacts associated with increased cooling water flow in the form

4287of particulate matter (PM). PM emissions are the dissolved

4296minerals contained in the “drift” from the new cooling tower.

4306This is most commonly seen as the condensed water vapor plume

4317from a cooling tower. Other regulated air emissions, such as

4327nitrogen oxide (NO x ) and sulfur dioxide (SO 2 ), will not be

4341affected by the Uprate Project, as there will be no additional

4352fossil fuel combustion sources for these pollutants. The Uprate

4361Project will not result in an increase in greenhouse gas

4371emissions.

437250. The South Cooling Tower requires an air construction

4381permit and Prevention of Significant Deterioration (“PSD”)

4388review and approval by the Department. The Department has

4397already issued a PSD permit for the new South Cooling Tower.

4408The term “PSD” denotes a regulatory program, established by the

4418U.S. Congress and implemented by the U.S. Environmental

4426Protection Agency (USEPA) through the states, including Florida,

4434that limits the amount of air quality degradation that can occur

4445from new or modified air emission sources. The new cooling

4455tower will be a modification to an existing major air emissions

4466source, which is the Crystal River Energy Complex. The USEPA

4476and the Department have implemented regulations requiring PSD

4484review and permitting for new or modified sources that increase

4494air emissions above certain threshold amounts.

450051. For the proposed cooling tower, a Best Available

4509Control technology (BACT) analysis was conducted as part of the

4519PSD analysis for PM. BACT is an emission limit based on the

4531maximum degree of reduction of each pollutant which, on a case-

4542by-case basis, taking into account energy, environmental and

4550economic impacts, and other costs, is achievable through

4558available methods, systems and technologies for control of an

4567air pollutant. The net increase of PM exceeds the Department’s

4577significance emission rate and, therefore, is subject to BACT

4586review. Drift eliminators are the best available control

4594technology utilized for cooling towers. Drift eliminators are

4602usually incorporated into the tower design to remove as many

4612droplets as practicable from the air stream before exiting the

4622cooling tower. Highly efficient drift eliminators have been

4630designated for use in the proposed South Cooling Tower to

4640control these emissions.

464352. Crystal River Unit 3 is located in an area classified

4654by the Department as attainment for all criteria air pollutants.

4664Citrus County’s air quality meets all of the federal and state

4675ambient air quality standards. The Chassahowitzka Wilderness

4682Area is the closest Class I area to the Crystal River site.

4694Project air emissions are not expected to have an adverse effect

4705on this Class I area.

471053. The Uprate Project is not expected to result in any

4721increase in the number of employees or truck deliveries after

4731construction and upon operation of the uprated Unit 3. There

4741should be no impact on the existing transportation

4749infrastructure and level of service (LOS) standards as a result

4759of the Project. No permanent traffic capacity improvements are

4768necessary as a result of the Uprate Project.

477654. During construction, the Uprate Project will cause

4784incremental increases in traffic in the Project vicinity, but

4793Progress Energy has agreed to implement traffic control measures

4802if needed.

480455. A noise impact assessment was performed for the

4813Uprate Project, both for construction and operation impacts.

4821Baseline noise measurements were taken and projected noise

4829levels were evaluated for potential changes in noise levels.

4838Construction noise levels were predicted to not exceed

4846applicable County standards. Following completion of

4852construction of the Uprate Project, the Uprate Project will not

4862result in an increase in noise levels in the vicinity of the

4874plant site. The construction and operation of the uprated Unit

48843 will comply with applicable Citrus County noise standards.

4893Land Use and Socioeconomic Effects

489856. The Uprate Project would be compatible with the

4907existing area land uses because Unit 3 is currently in operation

4918and the Uprate Project will not change the existing land use of

4930the site or the area. In addition, there are existing power

4941generation units located to the west and north of Unit 3. The

4953Uprate Project will not have an adverse effect on nearby public

4964recreational or environmentally protected areas.

496957. Construction and operation of the Uprate Project will

4978have a benefit to the local and regional economy. Construction

4988of the Project is in two phases. Phase 1 is anticipated to

5000begin in 2009 and Phase 2 in 2011. The anticipated total

5011workforce during peak construction activities for the Uprate

5019Project could total up to 650 employees in 2009 and 580

5030employees in 2011. The estimated cost for the Uprate Project is

5041$250 million for the installation and equipment upgrade

5049requirements. These costs are split between the two

5057construction phases: Phase I has an estimated $100 million in

5067Project costs and Phase II has an estimated $150 million in

5078Project costs. The major costs associated with this

5086construction Project include approximately $200 million for

5093major equipment and materials and approximately $20 million for

5102labor over the construction period.

510758. Employment opportunities and purchases of goods and

5115services to support the Uprate Project are anticipated to occur

5125over the four-year construction period. It is expected that the

5135majority of the construction wages paid for the Uprate Project

5145construction will be spent within Citrus County and the

5154surrounding region. These wages will create additional demands

5162for goods and services. As this money is spent, it will create

5174a multiplier effect within the area, thereby generating economic

5183activity, including additional jobs and earnings.

518959. Operation of Unit 3 following the Uprate Project will

5199result in positive impacts to the local economy. The annual

5209local property taxes paid by Progress Energy are expected to

5219increase from $8.5 million currently to $10 to 12 million after

5230Project completion. No increase in employment is expected as a

5240result of the Project, and thus, there will be no increase in

5252local residents. The Crystal River Energy Center is largely

5261self-sufficient and does not require public utilities or

5269services such as water and wastewater from local governments.

527860. The Uprate Project would be consistent with the Citrus

5288County Comprehensive Plan, the Withlacoochee Regional Planning

5295Council’s Strategic Regional Policy Plan and the State

5303Comprehensive Plan.

5305Determination of Need

530861. The Florida Public Service Commission determined that

5316there is a need for the Uprate Project. The Project will

5327displace higher-cost fossil-fuel electrical generation with low-

5334cost nuclear power generation, “resulting in substantial fuel

5342savings that provide a net benefit to customers.” Nuclear

5351energy is the lowest cost energy available on Progress Energy’s

5361system. Producing additional electricity with nuclear energy

5368from the Uprate Project would produce electricity at the lowest

5378possible fuel cost. The Uprate Project would also provide a

5388stable source of additional base load power. Nuclear generation

5397is not subject to the same supply interruptions or changes in

5408price volatility that can affect generation with fossil fuels,

5417such as natural gas. The PSC concluded that expanded energy

5427conservation programs cannot displace the Uprate Project.

5434Progress Energy is already exceeding its PSC-approved numeric

5442energy conservation goals.

5445Agency Positions and Stipulations and Conditions

545162. The Department, the FFWCC, the SWFWMD, the Florida

5460Department of Transportation (FDOT), and the Withlacoochee

5467Regional Planning Council prepared written reports on the Uprate

5476Project, and all recommended its approval.

548263. The Department found that it “has reasonable assurance

5491that the Uprate Project would be able to comply with applicable

5502agency standards and criteria as long as compliance with the

5512proposed conditions of certification is achieved.” The FDOT,

5520SWFWMD and FFWCC recommended approval of the Project subject to

5530their proposed conditions, which are included within the

5538Conditions of Certification. The Withlacoochee Regional

5544Planning Council found the Uprate Project to be consistent with

5554the Strategic Regional Policy Plan and recommended approval of

5563the Project.

556564. The Florida Department of Community Affairs did not

5574prepare a report on the Project, but indicated in the Prehearing

5585Stipulation it does not object to the certification of the

5595Uprate Project.

559765. No state, regional or local agency has recommended

5606denial of certification.

560966. Conditions of Certification have been agreed to by

5618Progress Energy and other agencies to ensure the Project’s

5627compliance with state and federal regulatory standards.

5634Public Comments

563667. The public was notified of the specific time and place

5647for providing comments to the Administrative Law Judge regarding

5656the Uprate Project. Very few members of the public attended.

5666Only four persons presented comments under oath. Three persons

5675expressed appreciation for Progress Energy’s charitable work and

5683services to the local communities. Another person asked for and

5693received information about the Uprate Project.

5699CONCLUSIONS OF LAW

570268. The Division of Administrative Hearings has

5709jurisdiction of the parties to and the subject matter of this

5720proceeding pursuant to Chapter 403, Part II, Florida Statutes,

5729the Florida Electrical Power Plant Siting Act.

573669. The Crystal River Unit 3 Uprate Project involves an

5746increase in the steam electric generating capacity of the

5755Crystal River Unit 3. The Power Plant Siting Act, in Section

5766403.506(1), Florida Statutes, provides that any increase in

5774steam electric generating capacity of an existing non-certified

5782power plant requires certification under the Sitiing Act.

5790Certification of the Uprate Project results in Unit 3 being

5800brought under the Siting Act.

580570. The Florida Public Service Commission has certified

5813the need for the electrical generating facility to be supplied

5823by the Crystal River Unit 3 Uprate Project as required by

5834Sections 403.507(4) and 403.519, Florida Statutes.

584071. In accordance with Chapter 120, the Power Plant Siting

5850Act, and Florida Administrative Code Chapter 62-17, notice was

5859given to all persons, entities and parties entitled thereto, as

5869well as to the general public. All necessary and required

5879governmental agencies participated in the certification process.

5886Reports and studies were issued by the Department, SWFWMD,

5895FFWCC, Withlacoochee Regional Planning Council, and FDOT, in

5903accordance with their various statutory duties.

590972. Proposed Conditions of Certification have been

5916recommended by the Department and accepted by Progress Energy.

5925The Conditions of Certification incorporate by reference

5932existing permits that apply to Unit 3 as well as other existing

5944generating units at the Crystal River Energy Complex.

5952Applicable provisions of those separate permits that apply to

5961Unit 3 are made a part of the Conditions of Certification and

5973would become enforceable under the Siting Act.

598073. The Department issued and would continue to issue

5989separate federally-required permits under the federal Clean

5996Water Act and federal Clean Air Act that apply to Unit 3 as well

6010as the other units at the Complex. Applicable provisions of

6020those federal permits that apply to Unit 3 are also incorporated

6031into the Conditions of Certification. A violation of any of the

6042permits incorporated into the Condi tions of Certification, as

6051they relate to Unit 3, would be subject to enforcement under the

6063Siting Act.

606574. Competent substantial evidence presented by Progress

6072Energy demonstrates that Crystal River Unit 3, as modified by

6082the proposed Uprate Project, is entitled to certification

6090pursuant to Section 403.509(3), Florida Statutes. Competent

6097substantial evidence produced at the hearing demonstrates that

6105the construction and operational safeguards for Crystal River

6113Unit 3, as modified by the proposed Uprate Project, is

6123technically sufficient for the welfare and protection of the

6132citizens of Florida, and are reasonable and available methods to

6142achieve that protection. Crystal River Unit 3, with its

6151increased electrical output, would produce minimal adverse

6158effects on human health, the environment, the ecology of the

6168land and its wildlife, and the ecology of state waters and their

6180aquatic life. Crystal River Unit 3, as modified by the proposed

6191Uprate Project, will not conflict with the goals, objectives, or

6201policies of the Citrus County Comprehensive Plan.

620875. If operated and maintained in accordance with this

6217Recommended Order and the recommended Conditions of

6224Certification, Crystal River Unit 3, as modified by the proposed

6234Uprate Project, would comply with the applicable non-procedural

6242requirements of all agencies. Certification of Crystal River

6250Unit 3, as modified by the proposed Uprate Project, would fully

6261balance the demand for electrical power plant location and

6270operation with the broad interests of the public.

6278RECOMMENDATION

6279Based on the foregoing Findings of Fact and Conclusions of

6289Law, it is

6292RECOMMENDED that Progress Energy Florida be granted final

6300certification, pursuant to Chapter 403, Part II, Florida

6308Statutes, for Crystal River Unit 3 at the Crystal River Energy

6319Complex, including the addition of 180 megawatts of nuclear-

6328fueled electrical generating capacity through the Uprate

6335Project, as proposed in the Site Certification Application, and

6344subject to the Conditions of Certification attached to the Staff

6354Analysis Report of the Florida Department of Environmental

6362Protection, Exhibit FDEP-2.

6365DONE AND ENTERED this 5th day of June, 2008, in

6375Tallahassee, Leon County, Florida.

6379BRAM D. E. CANTER

6383Administrative Law Judge

6386Division of Administrative Hearings

6390The DeSoto Building

63931230 Apalachee Parkway

6396Tallahassee, Florida 32399-3060

6399(850) 488-9675 SUNCOM 278-9675

6403Fax Filing (850) 921-6847

6407www.doah.state.fl.us

6408Filed with the Clerk of the

6414Division of Administrative Hearings

6418this 5th day of June, 2008.

6424ENDNOTE

64251 / All references to the Florida Statutes are to the 2007

6437codification.

6438COPIES FURNISHED :

6441Lea Crandall, Agency Clerk

6445Department of Environmental Protection

6449Douglas Building, Mail Station 35

64543900 Commonwealth Boulevard

6457Tallahassee, Florida 32399-3000

6460Tom Beason, General Counsel

6464Department of Environmental Protection

6468Douglas Building, Mail Station 35

64733900 Commonwealth Boulevard

6476Tallahassee, Florida 32399-3000

6479Michael W. Sole, Secretary

6483Department of Environmental Protection

6487Douglas Building

64893900 Commonwealth Boulevard

6492Tallahassee, Florida 32399-3000

6495James V. Antista, General Counsel

6500Florida Fish and Wildlife Commission

6505Bryant Building, Room 108

6509620 South Meridian Street

6513Tallahassee, Florida 32399-1600

6516Mary Anne Helton, Esquire

6520Florida Public Service Commission

65242540 Shumard Oak Boulevard

6528Tallahassee, Florida 32399-0850

6531Kelly A. Martinson, Esquire

6535Department of Community Affairs

65392555 Shumard Oak Boulevard

6543Tallahassee, Florida 32399-2100

6546Douglas S. Roberts, Esquire

6550Hopping, Green & Sams

6554Post Office Box 6526

6558Tallahassee, Florida 32314

6561Robert Battista, Esquire

6564Citrus County Attorney's Office

6568110 North Apopka Avenue

6572Inverness, Florida 33450-4231

6575Marti Moore, Esquire

6578Southwest Florida Water Management District

65832379 Broad Street

6586Brooksville, Florida 34604-6899

6589Frederick E. Landt, Esquire

6593Post Office Box 2045

6597Ocala, Florida 32678

6600Barton Bibler

6602Department of Health

6605Environmental Engineering

66074042 Bald Cypress Way

6611Tallahassee, Florida 32399-1742

6614Laura Kammerer

6616Bureau of Historic Preservation

6620R. A. Gray Building

6624500 South Bronough

6627Tallahassee, Florida 32399

6630Forrest Watson

6632Department of Agriculture &

6636Consumer Services

6638Division of Forestry

66413125 Conner Boulevard

6644Tallahassee, Florida 32399-1650

6647Michael R. Moehiman

6650Withlacoochee Regional

6652Planning Council

66541241 Southwest 10th Street

6658Ocala, Florida 34471

6661Kevin A. Smith

6664Citrus County Development Department

66683600 West Sovereign Path, Suite 140

6674Lecanto, Florida 34461

6677Leon M. Biegalski, Esquire

6681Department of Transportation

6684605 Suwannee Street, Mail Stop 58

6690Tallahassee, Florida 32399-0450

6693Toni Sturtevant, Esquire

6696Department of Environmental Protection

6700Douglas Building, Mail Station 35

67053900 Commonwealth Boulevard

6708Tallahassee, Florida 32399-3000

6711NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

6717All parties have the right to submit written exceptions within

672715 days from the date of this Recommended Order. Any exceptions

6738to this Recommended Order should be filed with the agency that

6749will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 02/13/2009
Proceedings: Position Statement filed.
PDF:
Date: 08/29/2008
Proceedings: Final Order Approving Certification filed.
PDF:
Date: 06/05/2008
Proceedings: Recommended Order
PDF:
Date: 06/05/2008
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 06/05/2008
Proceedings: Department of Transportation`s Notice of Substitution of Counsel filed.
PDF:
Date: 06/05/2008
Proceedings: Recommended Order on Certification (hearing held March 17, 2008). CASE CLOSED.
PDF:
Date: 05/23/2008
Proceedings: Notice of Filing Progress Energy Florida`s and Florida Department of Environmental Protection`s Proposed Supplemental Findings of Fact and Supplemental Conclusions of Law filed.
PDF:
Date: 05/23/2008
Proceedings: Notice of Filing Progress Energy Florida`s and Florida Department of Environmental Protection`s Supplemental Written Testimony filed.
PDF:
Date: 05/01/2008
Proceedings: Order Altering Time Limits.
Date: 05/01/2008
Proceedings: CASE STATUS: Pre-Hearing Conference Held.
Date: 04/23/2008
Proceedings: CASE STATUS: Motion Hearing Held.
PDF:
Date: 04/07/2008
Proceedings: Notice of Filing Progress Energy Florida`s and Florida Department of Environmental Protection`s Joint Proposed Recommended Order filed.
Date: 03/26/2008
Proceedings: Transcript filed.
PDF:
Date: 03/26/2008
Proceedings: Notice of Filing Transcript of Certification Hearing filed.
Date: 03/17/2008
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 03/12/2008
Proceedings: Notice of Filing Prefiled Direct Testimony and Exhibits (exhibits not available for viewing) filed.
PDF:
Date: 03/10/2008
Proceedings: Amended Notice of Hearing (hearing set for March 17 and 18, 2008; 1:00 p.m.; Crystal River, FL; amended as to time).
PDF:
Date: 03/07/2008
Proceedings: Pre-hearing Stipulation filed.
PDF:
Date: 02/01/2008
Proceedings: Notice of Filing Project Analysis.
PDF:
Date: 01/29/2008
Proceedings: Order Altering Time Limit for Issuance of the Project Analysis.
PDF:
Date: 01/17/2008
Proceedings: Notice of Filing Certified Proof of Publication for Notice of Certification Hearing on an Application to Construct and Operate an Electrical Power Plant on a Site to be Located in Citrus County, Florida: Progress Energy Florida Crystal River Unit 3 etc.
PDF:
Date: 01/16/2008
Proceedings: Joint Stipulation and Motion for Alteration of Time Limits for Issuance of FDEP Project Analysis filed.
PDF:
Date: 01/04/2008
Proceedings: Department of Transportation`s Notice of Substitution of Counsel filed.
PDF:
Date: 12/26/2007
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 12/26/2007
Proceedings: Notice of Hearing (hearing set for March 17 and 18, 2008; 9:00 a.m.; Crystal River, FL).
PDF:
Date: 12/21/2007
Proceedings: Letter to Judge Canter from D. Roberts regarding site certification hearing location filed.
PDF:
Date: 09/12/2007
Proceedings: Corrected Department of Environmental Protection`s Determination of Completeness filed.
PDF:
Date: 09/11/2007
Proceedings: Department of Environmental Protection`s Determination of Incompleteness filed.
PDF:
Date: 09/11/2007
Proceedings: Notice of Appearance (filed by T. Sturtevant) filed.
PDF:
Date: 08/22/2007
Proceedings: Notice of Filing Certified Proof of Publication for Notice of Filing Application for Electrical Power Plant Site Certification for a Power Plant to be Located in Citrus County, Florida: Progress Energy Crystal River Unit 3 Uprate Project filed.
PDF:
Date: 08/22/2007
Proceedings: Notice of Filing Certified Proof of Publication for Notice of Receipt of Citrus County`s Determination of Land Use and Zoning Consistency for Electrical Power Plant to be Located in Citrus County, Florida: PEF Crystal River Unit 3 Uprate Project filed.
PDF:
Date: 08/22/2007
Proceedings: Notice of Filing Sufficiency Responses filed.
PDF:
Date: 08/01/2007
Proceedings: Citrus County`s Determination of Compliance with Local Land use Plans and Zoning filed.
PDF:
Date: 07/27/2007
Proceedings: Southwest Florida Water Management District`s Notice of Intent to be a Party filed.
PDF:
Date: 07/20/2007
Proceedings: DEP`s Determination of Incompleteness filed.
PDF:
Date: 07/10/2007
Proceedings: Southwest Florida Water Management District`s Notice of Filing Completeness Comments.
PDF:
Date: 07/02/2007
Proceedings: Department of Community Affairs` Notice of Intent to be a Party filed.
PDF:
Date: 06/29/2007
Proceedings: Department of Transportation`s Notice of Intent to be a Party filed.
PDF:
Date: 06/28/2007
Proceedings: Response to Initial Order filed.
PDF:
Date: 06/26/2007
Proceedings: Department of Enviromental Protection`s Notice of Filing Site Certification Application filed.
PDF:
Date: 06/19/2007
Proceedings: Initial Order.
PDF:
Date: 06/18/2007
Proceedings: Department of Environmental Protection`s Proposed Site Certification Application Schedule filed.
PDF:
Date: 06/18/2007
Proceedings: Department of Environmental Protection`s Statement of Additional Agencies Entitled to Copies of the Application and Amendments filed.
PDF:
Date: 06/18/2007
Proceedings: Schedule for Review of Site Certification Application for Progress Energy Crystal River Nuclear Unit 3 Siting Application No. PA77-09A2 filed.
PDF:
Date: 06/18/2007
Proceedings: Department of Environmental Protection`s Notice of Receipt of Power Plant Siting Application and Request for Assignment of Administrative Law Judge filed.

Case Information

Judge:
BRAM D. E. CANTER
Date Filed:
06/18/2007
Date Assignment:
06/21/2007
Last Docket Entry:
02/13/2009
Location:
Crystal River, Florida
District:
Northern
Agency:
Department of Environmental Protection
Suffix:
EPP
 

Counsels

Related DOAH Cases(s) (1):

Related Florida Statute(s) (5):