07-002713EPP
In Re: Progress Energy Florida, Crystal River Unit 3 Uprate Project Power Plant Siting Application No Pa77-09a2 vs.
*
Status: Closed
Recommended Order on Thursday, June 5, 2008.
Recommended Order on Thursday, June 5, 2008.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8IN RE: PROGRESS ENERGY )
13FLORIDA, CRYSTAL RIVER UNIT 3 )
19UPRATE PROJECT POWER PLANT ) Case No. 07-2713EPP
27SITING APPLICATION NO PA77-09A2 )
32)
33RECOMMENDED ORDER ON CERTIFICATION
37The certification hearing in this case was held on
46March 17, 2008, in Crystal River, Florida, before Administrative
55Law Judge Bram D. E. Canter of the Division of Administrative
66Hearings.
67APPEARANCES
68For Florida Power Corporation:
72Douglas S. Roberts, Esquire
76Virginia C. Dailey, Esquire
80Hopping Green & Sams, P.A.
85Post Office Box 6526
89Tallahassee, Florida 32314
92For the Florida Department of Environmental Protection:
99Toni Sturtevant, Esquire
102Department of Environmental Protection
106Douglas Building, Mail Station 35
1113900 Commonwealth Boulevard
114Tallahassee, Florida 32399-3000
117STATEMENT OF THE ISSUE
121The issue to be determined in this case is whether the Siting Board should certify Crystal River Unit 3 at the Crystal River Energy Complex in Citrus County, Florida, owned and
152operated by Florida Power Corporation, doing business as
160Progress Energy Florida, Inc. (Progress Energy).
166PRELIMINARY STATEMENT
168On June 12, 2007, Progress Energy filed its application for
178site certification with the Florida Department of Environmental
186Protection (Department), pursuant to the Florida Electrical
193Power Plant Siting Act, Chapter 403, Part II, Florida Statutes
203(2007), 1 and Florida Administrative Code Chapter 62-17. Copies
212of the application were distributed to other agencies for their
222review and copies were made available for public review at the
233local library. The application for certification was prompted
241by Progress Energys proposal to add 180 megawatts (MW) of
251nuclear-powered electrical generating capacity to Crystal River
258not previously been certified, it is the intent of Progress
268Energy and the Department that all of Crystal River Unit 3, both
280the existing facilities and the proposed Uprate Project, be
289certified at this time.
293On July 20, 2007, the Department issued a Determination of
303Incompleteness and requested additional information from
309Progress Energy concerning its application. On August 22, 2007,
318Progress Energy filed its responses to the Departments
326Determination of Incompleteness. On September 11, 2007, the
334Department determined that the application was complete.
341On August 1, 2007, Citrus County issued its Determination
350of Compliance with Local Land Use Plans and Zoning, pursuant to
361Section 403.50665, Florida Statutes, finding that the Uprate
369Project was consistent with the comprehensive plan and zoning
378ordinances of Citrus County. Following public notice of the
387determination, no person filed a petition to challenge the
396Countys land use consistency determination.
401On February 1, 2008, the Department issued its Staff
410Analysis Report pursuant to Section 403.507(5), Florida
417Statutes. The Staff Analysis Report contained reports from
425other agencies and proposed Conditions of Certification.
432No person sought to intervene and participate as a party in
443the certification hearing. Progress Energy and the Department
451filed a Prehearing Stipulation in which no disputed issues of
461fact or law were identified.
466At the certification hearing, Progress Energy presented the
474live testimony of Ken Wilson, Harold Frediani, Jr., David
483Bruzek, and Kelly Gleaton. The pre-filed testimony of these
492witnesses was also presented by Progress Energy and accepted
501into evidence. Additional pre-filed testimony was presented and
509accepted into evidence for David Bear, Carl Bullock, Jason
518Collins, and Scott Osborne. Progress Energys Exhibits 1
526through 9 were admitted into evidence. The Department presented
535the testimony of Cindy Mulkey. The Departments Exhibits 1 and
5452 were admitted into evidence. No agency other than the
555Department appeared at the hearing.
560Following the presentation of evidence by the parties, a
569hearing was held for the exclusive purpose of receiving
578testimony from members of the general public. Four members of
588the public provided testimony. None opposed the Uprate Project.
597On May 1, 2008, the Administrative Law Judge requested, and
607the parties agreed to file, supplemental written testimony and
616proposed findings of fact regarding the structures, operations,
624and permitting conditions associated with the existing Crystal
632River Unit 3 facilities. The parties jointly filed the
641supplemental information on May 23, 2008, which included
649additional sworn written testimony by Ken Wilson.
656The one-volume Transcript of the hearing was filed with the
666Division of Administrative Hearings. Progress Energy and the
674Department filed a joint proposed recommended order which was
683duly considered in the preparation of this Recommended Order.
692FINDINGS OF FACT
6951. Florida Power Corporation, doing business as Progress
703Energy Florida, Inc., is an investor-owned utility that provides
712electric service to more than 1.7 million customers in its
722Florida service area. Progress Energys service area covers
73020,000 square miles in 35 Florida counties.
7382. Crystal River Unit 3 is part of Progress Energys 738-
749acre Crystal River Energy Complex, which is located in an
759unincorporated area of northern Citrus County. Yankeetown,
766Inglis, and the City of Crystal River are within a five-mile
777radius of the Complex.
7813. The Crystal River Energy Complex has five electrical
790generating units. Units 1 and 2 are coal-fired units which were
801constructed in the 1960s and produce approximately 900 MW. Unit
8113 is a nuclear-powered unit that went into operation in 1977,
822and also generates about 900 MW. Units 4 and 5 are 750 MW coal-
836fired units which became operational in the mid-1980s after
845being certified under the Power Plant Siting Act. The
854electrical power generated by the five units is delivered to
864Progress Energys electrical transmission system through shared
871230 kV and 500 kV switchyards on the Crystal River Energy
882Complex site.
8844. Cooling water for Crystal River Units 1, 2, and 3 is
896withdrawn from an intake canal which connects to Crystal Bay and
907the Gulf of Mexico. Water is pulled from the intake canal by
919pumps, sent through the condensers for Units 1, 2 and 3, where
931it becomes heated, and then is carried out to Crystal Bay via
943the discharge canal. The discharge canal extends approximately
9511.2 miles offshore.
9545. Crystal River Units 1, 2, and 3 share a supplemental or
966helper cooling tower system, which uses mechanical draft
974towers through which air is moved by large fans. When the
985temperature of the combined discharge water approaches 96.5
993degrees Fahrenheit, heated water is withdrawn from the discharge
1002canal and sent through the helper tower cells to cool the water
1014enough so that when it is returned to the discharge canal, the
1026combined temperature in the water will not exceed the permitted
1036limit of 96.5 degrees F on a three-hour rolling average.
10466. Progress Energy operates a Mariculture Center at the
1055Complex, which is a multi-species marine hatchery established in
1064the early 1990s to mitigate fisheries impacts caused by the
1074introduction of heated water into adjacent waters. Progress
1082Energy has also implemented a Department-approved manatee
1089protection plan that establishes a number of guidelines to
1098minimize adverse impacts to manatees at the intake and outfall
1108areas.
11097. A sea turtle monitoring and rescue program has been
1119initiated by Progress Energy to reduce potential sea turtle
1128strandings and mortalities at Crystal River Unit 3. Progress
1137Energy has implemented a Sea Turtle Rescue and Handling Guidance
1147program which provides instructions for sea turtle observation,
1155rescue, handling, notifications, and reporting requirements.
1161Rescued sea turtles are transferred to the Mariculture Center
1170for health evaluation, and either tagged and released or
1179transferred to a qualified center for treatment and
1187rehabilitation, as appropriate.
11908. The land uses in the area immediately surrounding the
1200Complex are primarily undeveloped agricultural and forested
1207lands, and some mining operations. Most of the area within a
1218five-mile radius of the Complex consists of agricultural,
1226industrial, or open lands. The nearest occupied residence is
1235over three miles away to the northeast.
12429. Since Unit 3 began operations, there has been active
1252mining and some rural residential and commercial development
1260along US 19 between Crystal River and the plant site, all of
1272which is more than five miles away.
1279Crystal River Unit 3 Existing Facilities to be Certified
128910. Crystal River Unit 3 was not previously certified
1298under the Power Plant Siting Act, because it was under
1308construction before the Siting Act took effect. If the Uprate
1318Project is certified, it is the intent of Progress Energy and
1329the Department to make all of Unit 3 subject to the Conditions
1341of Certification and to the Siting Act.
134811. Unit 3 is a pressurized water nuclear reactor. The
1358unit operates in a baseload condition, which means it operates
1368on an almost continuous basis throughout the year except for
1378scheduled outages. The unit is composed of a primary and
1388secondary system. The primary system is comprised of the
1397nuclear reactor, four reactor cooling pumps, and two steam
1406generators. The steam generators convert the heat from the
1415nuclear reaction into steam that is transferred to the secondary
1425system. In the secondary system, the steam is used to drive a
1437steam turbine/electrical generator. Electricity is then sent to
1445the existing electrical onsite switchyards for distribution over
1453Progress Energys electrical transmission system.
145812. The condenser is essentially a large metal box with
1468thousands of small diameter tubes through which circulating
1476water is flowing. Steam from the steam turbines is introduced
1486into the condenser box and when the steam contacts the outer
1497wall of a water-laden tube, heat is drawn from the steam,
1508through the tube wall, and into the circulating water. This
1518causes the steam to cool and condense. The condensed steam,
1528called "condensate", is collected in the bottom of the box, and
1539recycled to minimize water consumption. Warmed water from Unit
15483 is then released to the discharge canal.
155613. The Unit 3 site is 26.86 acres of developed land
1567within the Crystal River Energy Complex. The site contains no
1577significant environmental features. No archaeological or
1583historical features have been found on the site, but Progress
1593Energy has agreed to consult with the Division of Historical
1603Resources if any archaeological or historical finds are made at
1613the site.
161514. The major components of Unit 3 to be certified are the
1627nuclear reactor and its related facilities. The facilities to
1636be certified include the control complex, the turbine building,
1645and auxiliary and intermediate buildings which are associated
1653with the normal operation of Unit 3, the nuclear administrative
1663building, plant administrative buildings, the technical support
1670center, and warehouse and support buildings, the Unit 3 intake
1680and discharge structures, and the reactor head storage building
1689and maintenance training facility.
169315. Unit 3 is supported by several common facilities that
1703also serve some or all of the other generating units at the
1715Complex. These common facilities include the helper cooling
1723towers along the discharge canal, onsite warehouses, site
1731administrative building, parking lots, electrical switchyards,
1737transmission lines and the site access road. The intake and
1747discharge canals also serve all of the existing units and are
1758considered to be common facilities for the Complex. These
1767common facilities are not being proposed for certification.
177516. There is a potable water treatment facility and a
1785domestic wastewater treatment plant that serve Units 1, 2 and 3.
1796No changes to these facilities are required for the Uprate
1806Project. Both are located outside of the Unit 3 certification
1816area.
1817Existing Permits
181917. There is an existing state industrial wastewater
1827permit that applies to the operation of all five generating
1837units at the Complex. This permit covers a series of basins
1848that act as settling and percolation ponds. The basins are
1858subject to a groundwater monitoring program to monitor for
1867compliance with state groundwater standards.
187218. Under federal delegation, the Department issued a
1880National Pollutant Discharge Elimination System (NPDES) permit
1887for Units 1, 2 and 3. The NPDES permit covers the discharge of
1900once-through condenser cooling water from Units 1, 2 and 3, Unit
19113s auxiliary cooling water, treated coal pile runoff from Units
19211 and 2, and other liquid waste streams.
192919. The Department has also issued a Title V air operation
1940permit for the Crystal River Energy Complex that covers all five
1951generating units. This permit was issued by the Department
1960under the federal Clean Air Act, acting on behalf of the federal
1972EPA. Unit 3 does not have air emissions that are subject to the
1985permit, except for any air emissions from the existing helper
1995mechanical cooling towers. The Title V permit covers three
2004diesel generators for Unit 3 as unregulated air emissions units.
201420. Progress Energy is operating Crystal River Unit 3 in
2024compliance with all of the conditions of these permits.
203321. The result of certification of the Uprate Project
2042under the Siting Act will be the combining of all required state
2054permits into one complete set of Conditions of Certification.
2063Because several of the existing permits issued to Progress
2072Energy for Unit 3 cover other uncertified units at the Complex,
2083those permits would continue in force and would not be replaced
2094by the Conditions of Certification. Instead, those separate
2102permits are incorporated by reference in the body of, and
2112attached as appendices to, the proposed Conditions of
2120Certification.
212122. The common permits that apply to Unit 3 and other
2132units at the Complex, and which were described above as not part
2144of the Unit 3 certification, would not be renewed pursuant to
2155the Siting Act. They would be renewed under the normal
2165procedures applicable to other regulated industrial facilities.
2172However, modified and reissued permits, as they relate to Unit
21823, would be incorporated by reference into the Conditions of
2192Certification.
219323. The permits issued by the Department under the federal
2203Clean Air Act and Clean Water Act are not subject to the Florida
2216Power Plant Siting Act. The Siting Act provides that federal
2226permits are reviewed and issued separately by the Department,
2235but in coordination with the Siting Act process to the extent
2246possible. However, these federal permits would also be attached
2255to and incorporated into the Conditions of Certification for
2264Crystal River Unit 3. As those permits are modified or reissued
2275in the future, they would be incorporated.
228224. The Department has already issued a Prevention of
2291Significant Deterioration (PSD) permit for the proposed South
2299Cooling Tower. The PSD permit is also incorporated by reference
2309into the proposed Conditions of Certification.
231525. The conditions provide for post-certification review
2322of the proposed South Cooling Tower. Progress Energy will
2331design that tower and select its final site. Progress Energy
2341will then submit to the Department documentation on stormwater
2350management and wetland impacts, as well as a wetlands mitigation
2360plan, if necessary, for the cooling tower site. The Department
2370will then review and approve this tower under its Environmental
2380Resource Permitting requirements. Construction of the tower
2387cannot begin until the Department approves it. This post-
2396certification review is typical for power plant siting cases and
2406insures compliance with applicable agency criteria and
2413Conditions of Certification.
2416The Uprate Project
241926. The Uprate Project would add 180 MW of generating
2429capacity to Unit 3, for a total of 1,080 MW. The Uprate Project
2443does not affect the other four generating units within the
2453Crystal River Energy Complex.
245727. Unit 3 would not have to be physically expanded to
2468obtain the additional electrical generation. The Uprate Project
2476involves modifications and replacements of existing plant
2483components to increase the efficiency of the unit, principally
2492within the secondary system of the unit, as well as to support
2504increased electricity production.
250728. The Uprate Project would be undertaken in two phases.
2517In 2009, during an already-scheduled refueling outage and steam
2526generator replacement for Unit 3, the low pressure turbines and
2536electrical generator would be replaced or rebuilt, as needed.
2545Additionally, a number of secondary side components, including
2553heat exchangers and associated piping and valves, would be
2562modified or replaced. The net effect of these initial
2571modifications would be to increase the efficiency of the
2580secondary plant portion of Unit 3 so that the same primary plant
2592output results in approximately 40 MW greater electrical output.
260129. In the second stage of the Uprate Project, additional
2611plant modifications will be undertaken during a scheduled outage
2620in 2011. These modifications would include replacing the high
2629pressure turbines, replacing the condensate, feed-water booster
2636and circulating water pumps and/or motors to increase their flow
2646capacity, and other associated modifications. This second set
2654of modifications is expected to increase the electrical output
2663by an additional 140 MW, and allow Unit 3 to generate
2674approximately 1080 MW.
267730. The Uprate Project would include alterations that
2685would elevate Unit 3s thermal, or warm water, discharge. As
2695one option for offsetting the increased thermal discharge,
2703Progress Energy has developed a conceptual design plan for a new
2714South Cooling Tower. The planned additional cooling tower would
2723also be operated to avoid or minimize increased flow to the
2734intake canal from Crystal Bay. This would be accomplished by
2744routing a portion of the new cooling towers discharge to the
2755intake canal, thus avoiding additional intake or withdrawal of
2764water from Crystal Bay.
276831. The modifications to the circulating water system
2776would be addressed in a detailed engineering study. Options
2785would be discussed with the regulatory agencies. These options
2794would be designed to result in equivalent or less thermal and
2805biological impacts compared to the cooling system that currently
2814exists. The options would maintain existing thermal discharge
2822limits for plant cooling water and minimize impacts to aquatic
2832organisms. The final design of the new South Cooling Tower
2842would be addressed as part of the National Pollutant Discharge
2852Elimination System permit renewal in 2009.
285832. Electricity generated at the Complex is distributed
2866from shared 230 kV and 500 kV switchyards on the site. The
2878Uprate Project will utilize these existing electrical
2885transmission lines. No changes to the transmission system are
2894required for the additional electricity that would be produced.
290333. The Uprate Project will not significantly alter fuel
2912utilization by Unit 3. Additional enriched fuel will be used in
2923the unit following the Uprate Project, through increases in the
2933size of the refueling batches, to supply the energy to support
2944operation of the unit at the higher power levels.
295334. The construction and operation of the uprated Unit 3
2963would not generate any hazardous wastes. Its construction and
2972operation would not cause any change in Progress Energys spent
2982fuel storage systems, which store spent nuclear fuel in onsite
2992facilities.
299335. In 2009 (in support of the more substantial uprate
3003activity in 2011), Progress Energy would request that the US
3013Nuclear Regulatory Commission increase the licensed rated
3020thermal output of Unit 3 from 2609 MW thermal to 3010 MW
3032thermal. In a nuclear power plant, the thermal capacity is
3042approximately three times greater than its electrical capacity.
3050Therefore, the plants are often identified by both their thermal
3060capacity (MWt) and their electrical capability (MWe).
3067Uprate Project Impacts
307036. Net environmental impacts associated with construction
3077and operation of the Uprate Project are expected to be minimal.
3088The principal impacts are related to the potential increase in
3098cooling water flow through Unit 3 following the Uprate Projects
3108completion, and the potential effects of the increased
3116temperature of the cooling water. These effects are expected to
3126be offset by modifications to the circulating water system.
3135Construction impacts of the Uprate Project will be minimal, with
3145expected construction traffic volumes falling within acceptable
3152levels.
315337. The modifications involved in the Uprate Project would
3162be conducted within areas already used for electrical power
3171generation. Therefore, there are no expected impacts to
3179wildlife habitat. Only common bird species typical of
3187urban/industrial areas have been observed within the project
3195area. No threatened, endangered, or plant or animal species of
3205special concern (listed species) are found within the project
3214area. Wading birds classified as species of special concern by
3224the Fish and Wildlife Conservation Commission occasionally
3231forage within wetlands outside of the project area. Gopher
3240tortoises have been observed outside of the project area along
3250the rail line on the Crystal River Energy Complex. However, no
3261adverse impacts to listed species are anticipated as a result of
3272the Uprate Project. Construction laydown and parking areas
3280associated with the separate Steam Generator Replacement Project
3288for Unit 3 would also be utilized for the Uprate Project in
3300order to avoid or minimize impacts.
330638. No wetland habitat will be disturbed as a result of
3317the Uprate Project itself. The location of the proposed
3326supplemental cooling tower has not been finalized. The new
3335South Cooling Tower would be located to avoid and minimize
3345impacts to wetlands. If unavoidable wetland impacts would occur
3354at the site that is selected, appropriate mitigation would be
3364provided in accordance with a post-certification Environmental
3371Resource Review.
337339. The Uprate Project is expected to result in an
3383increase in heat produced by the Unit 3 reactor. This increase
3394in heat would result in an increase in the heat rejected by the
3407Unit 3 condenser to the circulating water which is then released
3418to the discharge canal. The heat rejection will increase by an
3429estimated 768 million Btu per hour, an increase of about 13
3440percent over current levels. Progress Energy can accommodate
3448this increase in rejected heat by increasing the circulating
3457water flow rate through Unit 3, by increasing the temperature
3467rise of the circulating water from Unit 3, or by increasing
3478both.
347940. The Unit 3 circulating water pumps may be modified to
3490increase their design flow rate by up to an additional 150,000
3502of the Unit 3 discharge water would decrease. However, if the
3513circulating water flow rate is not increased, the temperature of
3523the discharged water could increase due to the increased heat
3533rejection from the uprated unit. The actual operation is
3542expected to have results somewhere between these two extremes of
3552increased flow and increased temperature of the circulating
3560water.
356141. There are four potential adverse impacts that might
3570result from either increasing Unit 3s circulating water flow or
3580increasing the temperature of the cooling water discharge from
3589Unit 3. First, there could be an increase in the temperature of
3601the water discharged into Crystal Bay. Second, there could be
3611an increase in the area of offshore waters affected by the
3622heated water discharge. Third, there could be an increase in
3632the number of aquatic organisms impinged or trapped on the
3642cooling water intake screens. Fourth, there could be an
3651increase in the number of aquatic organisms entrained in the
3661intake canal and the cooling system. Entrainment refers to
3670passage of eggs and early larval stage organisms through the
3680intake canal, intake screens, and ultimately through the
3688circulating cooling water system. However, Progress Energy
3695intends to avoid or minimize these potential environmental
3703impacts.
370442. To avoid or minimize the impacts of increased cooling
3714water flow and temperature, Progress Energy is evaluating a
3723series of modifications to the existing cooling water system,
3732including the installation of the South Cooling Tower. The
3741intake and flow modifications will be designed to reduce the
3751increased thermal load from the Uprate Project by removing
3760heated effluent from the discharge canal and to avoid or
3770minimize any net increase in the number of organisms being drawn
3781into Unit 3.
378443. The proposed new South Cooling Tower would be located
3794between the intake canal and discharge canal, west of Units 1, 2
3806and 3. Detailed design and location of the South Cooling Tower
3817would be addressed as part of the renewal of the NPDES permit
3829renewal in 2009. That renewed permit would be incorporated into
3839the conditions of certification for Unit 3.
384644. As part of potential cooling water modifications, the
3855South Cooling Tower could withdraw water from the discharge
3864canal to remove the incremental rejected heat anticipated by the
3874Uprate Project. The new South Cooling Tower would be designed
3884to dissipate the increased rejected heat from Unit 3. All or a
3896portion of the cooled water from the South Cooling Tower could
3907be returned to the discharge canal.
391345. In addition to offsetting the increased water
3921temperature, the South Cooling Tower design could be increased
3930in size and provide for the return or recirculation of a portion
3942of the cold water from the Cooling Tower to the intake canal
3954instead of releasing it to the discharge canal. Recirculation
3963of a portion of the South Cooling Towers effluent back to the
3975intake canal could be used to maintain the intake flow in the
3987intake canal so as not to increase the existing intake flow rate
3999from Crystal Bay. This would prevent an increase in entrainment
4009of aquatic organisms into the intake canal.
401646. Re-circulating a portion of the South Cooling Water
4025effluent to the intake canal should prevent any increase in
4035impingement associated with increased flow in the intake canal.
4044Although the uprate may result in an increase in through-screen
4054velocity, Progress Energy does not anticipate that this increase
4063in velocity would alter present impingement levels. If
4071increased impingement does occur, Progress Energy would take
4079further steps to avoid or minimize increased impingement.
408747. Progress Energy proposes to continue to evaluate the
4096entrainment and impingement impacts associated with the Uprate
4104Project. These impacts would be addressed during the NPDES
4113renewal which is scheduled for submittal in 2009. The Uprate
4123Project is not expected to have a negative impact to aquatic
4134species.
413548. Progress Energy currently mitigates the impacts on
4143aquatic organisms in the circulating water system in several
4152ways. It operates several helper cooling towers to reduce the
4162thermal discharges from these three units. It seasonally
4170reduces the condenser cooling water flow through Crystal River
4179Units 1 and 2 to reduce impingement and entrainment of aquatic
4190species. Pursuant to the current federal NPDES Permit, Progress
4199Energy also operates a multi-species mariculture facility within
4207the Crystal River Energy Complex. It raises several species of
4217important marine species, such as red drum, spotted sea trout,
4227and pink shrimp which are periodically released to adjacent
4236surface waters. Progress Energys mariculture operations have
4243contributed to the restoration of red drum and scallop fisheries
4253in the offshore and adjacent waters.
425949. The associated circulating cooling water flow rate
4267through the new South Cooling Tower will increase air emission
4277impacts associated with increased cooling water flow in the form
4287of particulate matter (PM). PM emissions are the dissolved
4296minerals contained in the drift from the new cooling tower.
4306This is most commonly seen as the condensed water vapor plume
4317from a cooling tower. Other regulated air emissions, such as
4327nitrogen oxide (NO x ) and sulfur dioxide (SO 2 ), will not be
4341affected by the Uprate Project, as there will be no additional
4352fossil fuel combustion sources for these pollutants. The Uprate
4361Project will not result in an increase in greenhouse gas
4371emissions.
437250. The South Cooling Tower requires an air construction
4381permit and Prevention of Significant Deterioration (PSD)
4388review and approval by the Department. The Department has
4397already issued a PSD permit for the new South Cooling Tower.
4408The term PSD denotes a regulatory program, established by the
4418U.S. Congress and implemented by the U.S. Environmental
4426Protection Agency (USEPA) through the states, including Florida,
4434that limits the amount of air quality degradation that can occur
4445from new or modified air emission sources. The new cooling
4455tower will be a modification to an existing major air emissions
4466source, which is the Crystal River Energy Complex. The USEPA
4476and the Department have implemented regulations requiring PSD
4484review and permitting for new or modified sources that increase
4494air emissions above certain threshold amounts.
450051. For the proposed cooling tower, a Best Available
4509Control technology (BACT) analysis was conducted as part of the
4519PSD analysis for PM. BACT is an emission limit based on the
4531maximum degree of reduction of each pollutant which, on a case-
4542by-case basis, taking into account energy, environmental and
4550economic impacts, and other costs, is achievable through
4558available methods, systems and technologies for control of an
4567air pollutant. The net increase of PM exceeds the Departments
4577significance emission rate and, therefore, is subject to BACT
4586review. Drift eliminators are the best available control
4594technology utilized for cooling towers. Drift eliminators are
4602usually incorporated into the tower design to remove as many
4612droplets as practicable from the air stream before exiting the
4622cooling tower. Highly efficient drift eliminators have been
4630designated for use in the proposed South Cooling Tower to
4640control these emissions.
464352. Crystal River Unit 3 is located in an area classified
4654by the Department as attainment for all criteria air pollutants.
4664Citrus Countys air quality meets all of the federal and state
4675ambient air quality standards. The Chassahowitzka Wilderness
4682Area is the closest Class I area to the Crystal River site.
4694Project air emissions are not expected to have an adverse effect
4705on this Class I area.
471053. The Uprate Project is not expected to result in any
4721increase in the number of employees or truck deliveries after
4731construction and upon operation of the uprated Unit 3. There
4741should be no impact on the existing transportation
4749infrastructure and level of service (LOS) standards as a result
4759of the Project. No permanent traffic capacity improvements are
4768necessary as a result of the Uprate Project.
477654. During construction, the Uprate Project will cause
4784incremental increases in traffic in the Project vicinity, but
4793Progress Energy has agreed to implement traffic control measures
4802if needed.
480455. A noise impact assessment was performed for the
4813Uprate Project, both for construction and operation impacts.
4821Baseline noise measurements were taken and projected noise
4829levels were evaluated for potential changes in noise levels.
4838Construction noise levels were predicted to not exceed
4846applicable County standards. Following completion of
4852construction of the Uprate Project, the Uprate Project will not
4862result in an increase in noise levels in the vicinity of the
4874plant site. The construction and operation of the uprated Unit
48843 will comply with applicable Citrus County noise standards.
4893Land Use and Socioeconomic Effects
489856. The Uprate Project would be compatible with the
4907existing area land uses because Unit 3 is currently in operation
4918and the Uprate Project will not change the existing land use of
4930the site or the area. In addition, there are existing power
4941generation units located to the west and north of Unit 3. The
4953Uprate Project will not have an adverse effect on nearby public
4964recreational or environmentally protected areas.
496957. Construction and operation of the Uprate Project will
4978have a benefit to the local and regional economy. Construction
4988of the Project is in two phases. Phase 1 is anticipated to
5000begin in 2009 and Phase 2 in 2011. The anticipated total
5011workforce during peak construction activities for the Uprate
5019Project could total up to 650 employees in 2009 and 580
5030employees in 2011. The estimated cost for the Uprate Project is
5041$250 million for the installation and equipment upgrade
5049requirements. These costs are split between the two
5057construction phases: Phase I has an estimated $100 million in
5067Project costs and Phase II has an estimated $150 million in
5078Project costs. The major costs associated with this
5086construction Project include approximately $200 million for
5093major equipment and materials and approximately $20 million for
5102labor over the construction period.
510758. Employment opportunities and purchases of goods and
5115services to support the Uprate Project are anticipated to occur
5125over the four-year construction period. It is expected that the
5135majority of the construction wages paid for the Uprate Project
5145construction will be spent within Citrus County and the
5154surrounding region. These wages will create additional demands
5162for goods and services. As this money is spent, it will create
5174a multiplier effect within the area, thereby generating economic
5183activity, including additional jobs and earnings.
518959. Operation of Unit 3 following the Uprate Project will
5199result in positive impacts to the local economy. The annual
5209local property taxes paid by Progress Energy are expected to
5219increase from $8.5 million currently to $10 to 12 million after
5230Project completion. No increase in employment is expected as a
5240result of the Project, and thus, there will be no increase in
5252local residents. The Crystal River Energy Center is largely
5261self-sufficient and does not require public utilities or
5269services such as water and wastewater from local governments.
527860. The Uprate Project would be consistent with the Citrus
5288County Comprehensive Plan, the Withlacoochee Regional Planning
5295Councils Strategic Regional Policy Plan and the State
5303Comprehensive Plan.
5305Determination of Need
530861. The Florida Public Service Commission determined that
5316there is a need for the Uprate Project. The Project will
5327displace higher-cost fossil-fuel electrical generation with low-
5334cost nuclear power generation, resulting in substantial fuel
5342savings that provide a net benefit to customers. Nuclear
5351energy is the lowest cost energy available on Progress Energys
5361system. Producing additional electricity with nuclear energy
5368from the Uprate Project would produce electricity at the lowest
5378possible fuel cost. The Uprate Project would also provide a
5388stable source of additional base load power. Nuclear generation
5397is not subject to the same supply interruptions or changes in
5408price volatility that can affect generation with fossil fuels,
5417such as natural gas. The PSC concluded that expanded energy
5427conservation programs cannot displace the Uprate Project.
5434Progress Energy is already exceeding its PSC-approved numeric
5442energy conservation goals.
5445Agency Positions and Stipulations and Conditions
545162. The Department, the FFWCC, the SWFWMD, the Florida
5460Department of Transportation (FDOT), and the Withlacoochee
5467Regional Planning Council prepared written reports on the Uprate
5476Project, and all recommended its approval.
548263. The Department found that it has reasonable assurance
5491that the Uprate Project would be able to comply with applicable
5502agency standards and criteria as long as compliance with the
5512proposed conditions of certification is achieved. The FDOT,
5520SWFWMD and FFWCC recommended approval of the Project subject to
5530their proposed conditions, which are included within the
5538Conditions of Certification. The Withlacoochee Regional
5544Planning Council found the Uprate Project to be consistent with
5554the Strategic Regional Policy Plan and recommended approval of
5563the Project.
556564. The Florida Department of Community Affairs did not
5574prepare a report on the Project, but indicated in the Prehearing
5585Stipulation it does not object to the certification of the
5595Uprate Project.
559765. No state, regional or local agency has recommended
5606denial of certification.
560966. Conditions of Certification have been agreed to by
5618Progress Energy and other agencies to ensure the Projects
5627compliance with state and federal regulatory standards.
5634Public Comments
563667. The public was notified of the specific time and place
5647for providing comments to the Administrative Law Judge regarding
5656the Uprate Project. Very few members of the public attended.
5666Only four persons presented comments under oath. Three persons
5675expressed appreciation for Progress Energys charitable work and
5683services to the local communities. Another person asked for and
5693received information about the Uprate Project.
5699CONCLUSIONS OF LAW
570268. The Division of Administrative Hearings has
5709jurisdiction of the parties to and the subject matter of this
5720proceeding pursuant to Chapter 403, Part II, Florida Statutes,
5729the Florida Electrical Power Plant Siting Act.
573669. The Crystal River Unit 3 Uprate Project involves an
5746increase in the steam electric generating capacity of the
5755Crystal River Unit 3. The Power Plant Siting Act, in Section
5766403.506(1), Florida Statutes, provides that any increase in
5774steam electric generating capacity of an existing non-certified
5782power plant requires certification under the Sitiing Act.
5790Certification of the Uprate Project results in Unit 3 being
5800brought under the Siting Act.
580570. The Florida Public Service Commission has certified
5813the need for the electrical generating facility to be supplied
5823by the Crystal River Unit 3 Uprate Project as required by
5834Sections 403.507(4) and 403.519, Florida Statutes.
584071. In accordance with Chapter 120, the Power Plant Siting
5850Act, and Florida Administrative Code Chapter 62-17, notice was
5859given to all persons, entities and parties entitled thereto, as
5869well as to the general public. All necessary and required
5879governmental agencies participated in the certification process.
5886Reports and studies were issued by the Department, SWFWMD,
5895FFWCC, Withlacoochee Regional Planning Council, and FDOT, in
5903accordance with their various statutory duties.
590972. Proposed Conditions of Certification have been
5916recommended by the Department and accepted by Progress Energy.
5925The Conditions of Certification incorporate by reference
5932existing permits that apply to Unit 3 as well as other existing
5944generating units at the Crystal River Energy Complex.
5952Applicable provisions of those separate permits that apply to
5961Unit 3 are made a part of the Conditions of Certification and
5973would become enforceable under the Siting Act.
598073. The Department issued and would continue to issue
5989separate federally-required permits under the federal Clean
5996Water Act and federal Clean Air Act that apply to Unit 3 as well
6010as the other units at the Complex. Applicable provisions of
6020those federal permits that apply to Unit 3 are also incorporated
6031into the Conditions of Certification. A violation of any of the
6042permits incorporated into the Condi tions of Certification, as
6051they relate to Unit 3, would be subject to enforcement under the
6063Siting Act.
606574. Competent substantial evidence presented by Progress
6072Energy demonstrates that Crystal River Unit 3, as modified by
6082the proposed Uprate Project, is entitled to certification
6090pursuant to Section 403.509(3), Florida Statutes. Competent
6097substantial evidence produced at the hearing demonstrates that
6105the construction and operational safeguards for Crystal River
6113Unit 3, as modified by the proposed Uprate Project, is
6123technically sufficient for the welfare and protection of the
6132citizens of Florida, and are reasonable and available methods to
6142achieve that protection. Crystal River Unit 3, with its
6151increased electrical output, would produce minimal adverse
6158effects on human health, the environment, the ecology of the
6168land and its wildlife, and the ecology of state waters and their
6180aquatic life. Crystal River Unit 3, as modified by the proposed
6191Uprate Project, will not conflict with the goals, objectives, or
6201policies of the Citrus County Comprehensive Plan.
620875. If operated and maintained in accordance with this
6217Recommended Order and the recommended Conditions of
6224Certification, Crystal River Unit 3, as modified by the proposed
6234Uprate Project, would comply with the applicable non-procedural
6242requirements of all agencies. Certification of Crystal River
6250Unit 3, as modified by the proposed Uprate Project, would fully
6261balance the demand for electrical power plant location and
6270operation with the broad interests of the public.
6278RECOMMENDATION
6279Based on the foregoing Findings of Fact and Conclusions of
6289Law, it is
6292RECOMMENDED that Progress Energy Florida be granted final
6300certification, pursuant to Chapter 403, Part II, Florida
6308Statutes, for Crystal River Unit 3 at the Crystal River Energy
6319Complex, including the addition of 180 megawatts of nuclear-
6328fueled electrical generating capacity through the Uprate
6335Project, as proposed in the Site Certification Application, and
6344subject to the Conditions of Certification attached to the Staff
6354Analysis Report of the Florida Department of Environmental
6362Protection, Exhibit FDEP-2.
6365DONE AND ENTERED this 5th day of June, 2008, in
6375Tallahassee, Leon County, Florida.
6379BRAM D. E. CANTER
6383Administrative Law Judge
6386Division of Administrative Hearings
6390The DeSoto Building
63931230 Apalachee Parkway
6396Tallahassee, Florida 32399-3060
6399(850) 488-9675 SUNCOM 278-9675
6403Fax Filing (850) 921-6847
6407www.doah.state.fl.us
6408Filed with the Clerk of the
6414Division of Administrative Hearings
6418this 5th day of June, 2008.
6424ENDNOTE
64251 / All references to the Florida Statutes are to the 2007
6437codification.
6438COPIES FURNISHED :
6441Lea Crandall, Agency Clerk
6445Department of Environmental Protection
6449Douglas Building, Mail Station 35
64543900 Commonwealth Boulevard
6457Tallahassee, Florida 32399-3000
6460Tom Beason, General Counsel
6464Department of Environmental Protection
6468Douglas Building, Mail Station 35
64733900 Commonwealth Boulevard
6476Tallahassee, Florida 32399-3000
6479Michael W. Sole, Secretary
6483Department of Environmental Protection
6487Douglas Building
64893900 Commonwealth Boulevard
6492Tallahassee, Florida 32399-3000
6495James V. Antista, General Counsel
6500Florida Fish and Wildlife Commission
6505Bryant Building, Room 108
6509620 South Meridian Street
6513Tallahassee, Florida 32399-1600
6516Mary Anne Helton, Esquire
6520Florida Public Service Commission
65242540 Shumard Oak Boulevard
6528Tallahassee, Florida 32399-0850
6531Kelly A. Martinson, Esquire
6535Department of Community Affairs
65392555 Shumard Oak Boulevard
6543Tallahassee, Florida 32399-2100
6546Douglas S. Roberts, Esquire
6550Hopping, Green & Sams
6554Post Office Box 6526
6558Tallahassee, Florida 32314
6561Robert Battista, Esquire
6564Citrus County Attorney's Office
6568110 North Apopka Avenue
6572Inverness, Florida 33450-4231
6575Marti Moore, Esquire
6578Southwest Florida Water Management District
65832379 Broad Street
6586Brooksville, Florida 34604-6899
6589Frederick E. Landt, Esquire
6593Post Office Box 2045
6597Ocala, Florida 32678
6600Barton Bibler
6602Department of Health
6605Environmental Engineering
66074042 Bald Cypress Way
6611Tallahassee, Florida 32399-1742
6614Laura Kammerer
6616Bureau of Historic Preservation
6620R. A. Gray Building
6624500 South Bronough
6627Tallahassee, Florida 32399
6630Forrest Watson
6632Department of Agriculture &
6636Consumer Services
6638Division of Forestry
66413125 Conner Boulevard
6644Tallahassee, Florida 32399-1650
6647Michael R. Moehiman
6650Withlacoochee Regional
6652Planning Council
66541241 Southwest 10th Street
6658Ocala, Florida 34471
6661Kevin A. Smith
6664Citrus County Development Department
66683600 West Sovereign Path, Suite 140
6674Lecanto, Florida 34461
6677Leon M. Biegalski, Esquire
6681Department of Transportation
6684605 Suwannee Street, Mail Stop 58
6690Tallahassee, Florida 32399-0450
6693Toni Sturtevant, Esquire
6696Department of Environmental Protection
6700Douglas Building, Mail Station 35
67053900 Commonwealth Boulevard
6708Tallahassee, Florida 32399-3000
6711NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
6717All parties have the right to submit written exceptions within
672715 days from the date of this Recommended Order. Any exceptions
6738to this Recommended Order should be filed with the agency that
6749will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 06/05/2008
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 06/05/2008
- Proceedings: Department of Transportation`s Notice of Substitution of Counsel filed.
- PDF:
- Date: 06/05/2008
- Proceedings: Recommended Order on Certification (hearing held March 17, 2008). CASE CLOSED.
- PDF:
- Date: 05/23/2008
- Proceedings: Notice of Filing Progress Energy Florida`s and Florida Department of Environmental Protection`s Proposed Supplemental Findings of Fact and Supplemental Conclusions of Law filed.
- PDF:
- Date: 05/23/2008
- Proceedings: Notice of Filing Progress Energy Florida`s and Florida Department of Environmental Protection`s Supplemental Written Testimony filed.
- Date: 05/01/2008
- Proceedings: CASE STATUS: Pre-Hearing Conference Held.
- Date: 04/23/2008
- Proceedings: CASE STATUS: Motion Hearing Held.
- PDF:
- Date: 04/07/2008
- Proceedings: Notice of Filing Progress Energy Florida`s and Florida Department of Environmental Protection`s Joint Proposed Recommended Order filed.
- Date: 03/26/2008
- Proceedings: Transcript filed.
- Date: 03/17/2008
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 03/12/2008
- Proceedings: Notice of Filing Prefiled Direct Testimony and Exhibits (exhibits not available for viewing) filed.
- PDF:
- Date: 03/10/2008
- Proceedings: Amended Notice of Hearing (hearing set for March 17 and 18, 2008; 1:00 p.m.; Crystal River, FL; amended as to time).
- PDF:
- Date: 01/17/2008
- Proceedings: Notice of Filing Certified Proof of Publication for Notice of Certification Hearing on an Application to Construct and Operate an Electrical Power Plant on a Site to be Located in Citrus County, Florida: Progress Energy Florida Crystal River Unit 3 etc.
- PDF:
- Date: 01/16/2008
- Proceedings: Joint Stipulation and Motion for Alteration of Time Limits for Issuance of FDEP Project Analysis filed.
- PDF:
- Date: 01/04/2008
- Proceedings: Department of Transportation`s Notice of Substitution of Counsel filed.
- PDF:
- Date: 12/26/2007
- Proceedings: Notice of Hearing (hearing set for March 17 and 18, 2008; 9:00 a.m.; Crystal River, FL).
- PDF:
- Date: 12/21/2007
- Proceedings: Letter to Judge Canter from D. Roberts regarding site certification hearing location filed.
- PDF:
- Date: 09/12/2007
- Proceedings: Corrected Department of Environmental Protection`s Determination of Completeness filed.
- PDF:
- Date: 09/11/2007
- Proceedings: Department of Environmental Protection`s Determination of Incompleteness filed.
- PDF:
- Date: 08/22/2007
- Proceedings: Notice of Filing Certified Proof of Publication for Notice of Filing Application for Electrical Power Plant Site Certification for a Power Plant to be Located in Citrus County, Florida: Progress Energy Crystal River Unit 3 Uprate Project filed.
- PDF:
- Date: 08/22/2007
- Proceedings: Notice of Filing Certified Proof of Publication for Notice of Receipt of Citrus County`s Determination of Land Use and Zoning Consistency for Electrical Power Plant to be Located in Citrus County, Florida: PEF Crystal River Unit 3 Uprate Project filed.
- PDF:
- Date: 08/01/2007
- Proceedings: Citrus County`s Determination of Compliance with Local Land use Plans and Zoning filed.
- PDF:
- Date: 07/27/2007
- Proceedings: Southwest Florida Water Management District`s Notice of Intent to be a Party filed.
- PDF:
- Date: 07/10/2007
- Proceedings: Southwest Florida Water Management District`s Notice of Filing Completeness Comments.
- PDF:
- Date: 07/02/2007
- Proceedings: Department of Community Affairs` Notice of Intent to be a Party filed.
- PDF:
- Date: 06/29/2007
- Proceedings: Department of Transportation`s Notice of Intent to be a Party filed.
- PDF:
- Date: 06/26/2007
- Proceedings: Department of Enviromental Protection`s Notice of Filing Site Certification Application filed.
- PDF:
- Date: 06/18/2007
- Proceedings: Department of Environmental Protection`s Proposed Site Certification Application Schedule filed.
- PDF:
- Date: 06/18/2007
- Proceedings: Department of Environmental Protection`s Statement of Additional Agencies Entitled to Copies of the Application and Amendments filed.
Case Information
- Judge:
- BRAM D. E. CANTER
- Date Filed:
- 06/18/2007
- Date Assignment:
- 06/21/2007
- Last Docket Entry:
- 02/13/2009
- Location:
- Crystal River, Florida
- District:
- Northern
- Agency:
- Department of Environmental Protection
- Suffix:
- EPP
Counsels
-
James V. Antista, Esquire
Address of Record -
Robert Battista, Esquire
Address of Record -
Barton Bibler
Address of Record -
Leon M. Biegalski, Esquire
Address of Record -
Jack Chisolm, Esquire
Address of Record -
Kelly M. Fernandez, Esquire
Address of Record -
Mary Anne Helton, Esquire
Address of Record -
Laura Kammerer
Address of Record -
Frederick E. Landt, Esquire
Address of Record -
Michael R Moehiman
Address of Record -
Martha A. Moore, Esquire
Address of Record -
Douglas S. Roberts, Esquire
Address of Record -
Kevin A Smith
Address of Record -
Toni L. Sturtevant, Esquire
Address of Record -
Forrest Watson
Address of Record -
Alexis M. Yarbrough
Address of Record -
Doug S. Roberts, Esquire
Address of Record