14-003674
Department Of Environmental Protection vs.
South Palafox Properties, Llc
Status: Closed
Recommended Order on Monday, March 2, 2015.
Recommended Order on Monday, March 2, 2015.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8DEPARTMENT OF ENVIRONMENTAL
11PROTECTION,
12Petitioner ,
13vs. Case No. 1 4 - 3674
20SOUTH PALAFOX PROPERTIES, INC.,
24Respondent.
25______________________ _________/
27RECOMMENDED ORDER
29T his matter was heard before the Division of Administrative
39Hearings (DOAH) by its assigned Administrative Law Judge, D . R.
50Alexander, on December 9 - 1 1 , 2014, in Pensacola , Florida.
61APPEARANCES
62For Petitioner : B. Jack Chisolm, Jr., Esquire
70Mar garet E. Seward, Esquire
75Department of Environmental Protection
79Mail Station 35
823900 Commonwealth Boulevard
85Tallahassee, Florida 32399 - 3000
90For Respondent: V. Nicholas Dancaescu, Esquire
96Christopher T. Dawson, Esquire
100Ashley E. Hoffman, Esquire
104GrayRobinson, P.A.
106Suite 1400
108301 East Pine Street
112Orlando , Florida 32 801 - 2741
118STATEMENT OF THE ISSUE
122The issue is whether Respondent's Construction and
129Demolition Debris Disposal Facility Permit No. 003397 - 013 - SO
140( the Permit) should be revoked and the facility closed for the
152reasons stated in the Department of Environmental Protection's
160(Department's) Notice of Revocation (Notice) issued on July 31,
1692014.
170PRELIMINARY STATEMENT
172In a n eight - count Notice , the Departme nt propose s to revoke
186Respondent's Permit and close its facility for violati ng Permit
196conditions and rules that govern the operation of the facility ,
206including a failure to comply with certain time frames and/or
216deadlines required by a 2012 Consent Order . Respondent timely
226requested a hearing to contest th e proposed agency action, and
237the matter was referred to DOAH to conduct a hearing.
247At the final hearing, the Department presented the
255testimony of five witnesses . Department Exhibits 1 through 8,
26514, 18, 20, 22, 23, 30, 36, and 40 were received in evidence.
278Respondent presented the testimony of four witnesses .
286Respondent 's Exhibits 1 through 5, 27, and 28 were accepted in
298evidence. The deposition of one witness was submitted by
307Respondent on a proff er basis only. Joint Exhibits 1 and 2 were
320also admitted. Finally, official recognition of the following
328matters was taken: chapter 120, Florida Statutes (2014);
336sections 403.021, 403.031, 403.061, 403.087, 403.121, 403.161,
343403.703, 403.704, and 403.70 7; Florida Administrative Code
351C hapters 62 - 4, 62 - 302, 62 - 701, and 62 - 780; rules 62 - 210.200 and
37162 - 296 . 320; and 40 C.F.R. Part 264, Subpart II, adopted by
385reference at rule 62 - 701.630.
391A three - volume Transcript of the hearing has been prepared.
402Proposed Recommended Orders (PROs) were filed by the parties ,
411and they have been considered in the preparation of this
421Recommended Order.
423FINDINGS OF FACT
426A . The Parties , the Property, and the Dispute
4351. The Depar tment administers and enforces t he provisions
445of chapter 403 and the rules promulgated thereunder , including
454those applicable to construction and demolition debris (C & D)
464disposal facilities.
4662. Respondent is a Florida limited liability corporation
474that owns real property located at 6990 Rolling Hills Road,
484Pensacola, Escambia County (County) , Florida . The large, odd -
494shaped p arcel (whose exact size is unknown) is south - south west
507of the intersection of Interstate 10 and Pensacola Boulevard
516(U.S. Highway 29) and has C lass III fresh surface waters run nin g
530in a northeast - southwest direction through the middle of the
541property . See Resp. Ex. 28. The entire site is surrounded by a
554six - foot tall fence or is separated from adjoining properties by
566natural barriers. A railroad track borders on the eastern side
576of the parcel; the western boundary fronts on Rolling Hills
586Road ; and the northern boundary appears to be just south of West
598Pinestead Road . Id. The area immediately south of the parcel
609appears to be largely undeveloped. See Dept. Ex. 40. The
619E merald Coast Utilit ies Authority (ECUA) , a local government
629body, has an easement that runs along the eastern side of the
641property adjacent to the railroad track on which a 48 - inch sewer
654pipe is located.
6573. An older residential area, known as Wedgewood, is
666loc ated northeast of the facility on the north side of West
678Pinestead Road. Id. The closest Wedgewood homes appear to be
688around 4 00 or 500 feet from the edge of Respondent's property.
700A community and recreational center , the Marie K. Young Center ,
710also kno wn as the Wedgewood Center, serves the Wedgewood
720community , is north west of the facility , and lies around 500
731feet from the edge of the property. Established in 2012 where a
743school once stood , it has more than 200 members . Although no n -
757parties, it is fai r to say that the Wedgewood community and
769County strongly support th e Department 's efforts to revoke
779Respondent ' s permit.
7834 . Respondent acquired the property in 2007. At that
793time, an existing C & D disposal facility (the facility) was
804located on the pro perty operating under a p ermit issued by the
817Department. The Permit was re newed in February 2013 and will
828expire in early 2018. Besides the general and specific
837conditions , the renewed Permit incorporate s the terms and
846conditions of a Consent Order execu ted in November 2012 , as well
858as detailed requirements relat ing to the operation of the
868facility, water quality monitoring, an odor remediation plan,
876financial assurance and cost estimates, and closure of the
885facility. The latter requirements are found in four Appendices
894attached to the Permit.
8985 . The facility operates u nder the name of Rolling Hills
910Construction and Demolition Recycling Center. All material
917received by the facility is disposed of in an active disposal
928pile known as cell 2, located in the middle of the northern
940section of the parcel . Cell 1 , southwest of cell 2 and just
953east of Rolling Hills Road , was cl osed a number of years ago by
967the prior operator .
9716. Respondent operates the only C & D facility in the
982County. 1/ It currently ser ves around 50 to 60 active customers ,
994employs 16 persons, and operates between the hours of 7:00 a.m.
1005and 5:00 p.m. The former manager , Charl es Davidson, who had
1016overseen operations since 20 10 , was replaced in June 2014, and
1027Respondent blames him for igno ring or failing to address most of
1039the problems encountered during the last three years . Since
1049June , the managing partner of the LLC, Scott C. Miller, has
1060overseen the operations.
10637 . Unlike Class I or III landfills, a C & D landfill may
1077accept only cons truction and demolition debris. Co nstruction
1086and demolition debris is defined as "discarded materials
1094generally considered to be not water soluble and non - hazardous
1105in nature." § 403.703(6), Fla. Stat.; Fl a. Admin. Code R. 62 -
1118701.200(24). D ebris include s not only items such as steel,
1129glass, brick, concrete, asphalt material, pipe, gypsum
1136wallboard, and lumber that are typically associated with
1144construction or demolition projects , but also rocks, soils, tree
1153remains, trees, and other vegetative matter tha t normally result
1163from land clearing or land development operations. Id. No
1172solid waste other than construction and demolition debris may be
1182disposed of a t the facility. See Fla. Admin. Code R. 62 -
11957 0 1.730(4)(d).
11988 . To address and resolve certain v iol ations that predated
1210the renewal of the Permit , the Department and Respondent entered
1220into a Consent Order on November 14, 2012. See Dep t. Ex. 2 .
1234These violations occurred in 2011 and included the storage
1243and/or disposal of non - C & D debris, and a failur e to timely
1258submit an appropriate Remedial Action Plan (RAP). Id. Among
1267other things, t he Consent Order required that within a time
1278certain Respondent submit for Department review and approval a n
1288RAP ; and after its approval to " continue to follow the tim e
1300frames and requirements of Ch apter 62 - 780, F.A.C. " Id. Th ose
1313requirements included the initiation of an active remediation
1321system and site rehabilitation within a time certain, and the
1331continued monitoring and related corrective action for any water
1340qu ality violations or impacts . Id.
13479 . To ensure that it ha s the financial ability to
1359undertake any required c orrective action , the Permit requires
1368Respondent t o provide proof of financial assurance for the
1378corrective action program cost estimates. See F la. Admin. Code
1388R. 62 - 701.730(11)(d); § 2, Spec . Cond. F.1. This can be done
1402through a number of mechanisms, such as a performance bond,
1412letter of credit, or cash escrow. The Permit also requires
1422Re spondent to provide proof of financial assurance to
1431demo nstrat e that it has the financial ability to close the
1443facility and otherwise provide for the long - term care cost
1454estimates of the facility. See Fla. Admin. Code R. 62 - 701.630;
1466§ 2, Spec. Cond. F.2. Rather than using a cash escrow or letter
1479of credit , Re spondent has chosen to use a performance bond for
1491both requirements. These bonds must be updated annually to
1500include an inflation adjustment.
150410 . Given the many requirements imposed by the Permit and
1515Consent Order, in 2013 and 2014 s e veral follow - up site
1528inspections of the facility were conducted by the Department ,
1537and a review of the operations was made to determine if the
1549various deadlines had been met. Also, in 2014, the Department
1559received complaints from the County and neighboring property
1567owners , a lmost exclusively by those residing in the Wedgewood
1577community , re garding offensive odors emanating from t he
1586facility.
158711 . Based on field observations , the review of operations ,
1597and odor complaints, on July 31, 2014, t he Department issued a
1609Notice conta ining eight counts of wrongdoing. The Notice was
1619issued under section 403.087(7) (b), which authorizes the
1627Department to revoke a permit when it finds the permit holder
1638has " [ v ] iolated law, department orders, rules, or regulations,
1649or permit conditions." To Respondent's consternation, the
1656Department opted to use that enforcement mechanism rather than
1665initiating an enforcement action under section 403.121 or
1673executing a nother consent order , both of which would likely
1683result in a sanction less severe than pe rmit revocation . 2/
16951 2 . The Notice contains the following charges: exceeding
1705surface water quality standards in r ules 62 - 302.500 and 62 -
1718302.530 (Count I); fail ing to implement a n R AP as required by
1732the Consent Order and Permit (Count II); fail ing to provi de
1744adequate financial assurance s for facility closure costs (Count
1753III); fail ing to provide financial assurances for the corrective
1763action required by the RAP (Count IV); fail ing to reduce on - site
1777and off - site objectionable odors and to implement a routine odor
1789monitoring program (Count V); dispos ing non - C & D waste on site
1803(Count VI); fail ing to remove unauthorized waste (Count VII);
1813and disposing solid waste outside of its permitted (vertical)
1822dimension of 130 feet N ational Geodetic Vertical Datum (N GVD )
1834(Count VIII). These allegations are discussed separately below.
184213. Although the Notice is based on violations that
1851occurred on or before July 31, 2014, the undersigned denied the
1862Department's motion in limine that would preclude Respondent
1870from presen ting mitigating evidence concerning circumstances
1877surrounding the violations and efforts to remediate them after
1886July 31, 2014. Given that ruling, t he Department was allowed to
1898present evidence to show that Respondent's remediation efforts
1906have not been s uccessful and that some violations still existed
1917as of the date of final hearing.
19241 4 . Respondent disputes the allegations and contends that
1934most, if not all, are either untrue, inaccurate, have been
1944remedied, or are in the process of being remedied. As n oted
1956above, Respondent considers the revocation of its permit too
1965harsh a penalty in light of its continued efforts to comply with
1977Department rules and enforcement guidelines. It contends that
1985the Department is acting at the behest of the County, which
1996de sires to close the facility to satisfy the odor complaints of
2008the Wedgewood residents , and to ultimately use the property for
2018a new road that it intends to build in the future.
2029B. Count I - Water Quality Violations
20361 5 . The Notice alleges that two water q uality monitoring
2048reports filed by Respondent reflect that it exceeded surface
2057water quality standards at two monitoring locations (MW - 2 and
2068SW - 6) sampled on August 26, 2013, and at one monitoring location
2081(MW - 2) sampled on March 4, 2014. The Notice alleg e s that these
2096exceedances constitute a failure to comply with Class III fresh
2106surface water quality standards in rules 62 - 302.500 and 62 -
2118302.530 and therefore violate conditions in the P ermit. These
2128standards apply in areas beyond the edge of the discharg e area
2140(or zone of discharge) established by the Permit.
21481 6 . To ensure compliance with water quality standards,
2158w hen the Permit was renewed in 2013, a Water Quality Monitoring
2170Report (Appendix 3) was attached to the Permit. It required
2180Respondent to mo nitor surface water for contamination, identif y
2190the locations at which samples must be collected, and specif y
2201the testing parameters. All of these conditions were accepted
2210by Respondent and its consultant(s).
22151 7 . The monitoring network , already in place when
2225Respondent purchased the facility, consists of six ground water
2234monitoring wells and three surface water monitoring stations.
2242The surface water stations , which must be sampled to determine
2252compliance with water quality criteria , are SW - 5, a backgroun d
2264location, and SW - 6 and MW - 2, both compliance locations located
2277outside the zone of discharge . A background location is placed
2288upstream of an activity in order to determine the quality of the
2300water before any impacts by the activity. A compliance locati on
2311is placed downstream of an activity to determine any impacts of
2322the facility on surface water.
23271 8 . The Water Quality Monitoring Plan and Permit require
2338Respondent to submit semi - annual water quality reports. To
2348conduct the preparation and filing of the reports, Respondent
2357used an outside consulting firm, Enviro Pro Tech, Inc. (EPT).
2367On November 5, 2013, EPT submitted a Second Semi - Annual 2013
2379report. See Dept. Ex. 5. According to Mr. Miller, who now
2390oversees operations at the facility, EPT did not provide
2399Respondent a copy of the report , or even discuss its findings,
2410before filing it with the Department.
24161 9 . A Department engineer reviewed the report and noted
2427that surface water samples exceeded the Class III Fresh Water
2437Quality Standards for iro n, copper, lead, zinc, nickel, and
2447mercury at SW - 6 and for iron at MW - 2. See Dept. Ex. 6. A copy
2465of the Department's report was provided to Respondent and EPT.
2475Notably, the report indicated that background levels were lower
2484than the down - gradient result s. Under Department protocol, if
2495the sample s at the compliance locations exceed both the
2505regulatory levels and the background, th ere is a violation of
2516water quality s tandards. This accepted protocol differs from
2525Respondent's suggested protocol that the b ackground level should
2534be added to the regulatory standard before a comparison with the
2545sample results is made. In sum, e xcept for the reported n ickel
2558value at SW - 6 , a violation which the Department now says it will
2572not pursue, all exceedances shown on De partment Exhibits 5 and 6
2584are violations of the standards.
258920 . On April 1, 2014, EPT submitted a First Semi - Annual
26022014 report. See Dept. Ex. 7. A Department engineer reviewed
2612the report and noted that the surface water samples at one
2623monitoring locat ion, MW - 2, did not meet water quality standards
2635for iron; however, background levels for iron were much higher
2645than downstream. See Dept. Ex. 8. No other exceedances were
2655shown. Although the Department engineer considered the higher
2663background level for iron to be an "inconsistency" since it
2673varied from the prior reports, the reported iron value was
2683treated as a violation when the Notice was drafted. In its PRO,
2695however, the Department concedes that it did not establish a
2705violation of standards for iron , as alleged in paragraph 7 of
2716the Notice.
27182 1 . While having no concerns with sampling taken at MW - 2,
2732Respondent's expert contends that the reported values for SW - 6
2743are unreliable because the samples taken from that location were
2753turbid and filled with lar ge amounts of suspended solid matter.
2764He noted that the well is located in a wetland area that is
" 2777clogged with vegetation ." The expert estimated the turbidity
2786at the site to be in the range of 480 to 500 Nephelometric
2799Turbidity Units (NTUs) and believes the sample was taken in a
"2810high turbid sediment laden area , " thus rendering it unreliable.
2819However, at the time of the sample collection, turbidity was
2829measured at 164 NTUs , or much less than the amount estimated by
2841the expert . See Dept. Ex. 5, p. 147.
28502 2 . There is no rule or procedure that disallows the use
2863of turbid samples. In fact, they can be representative of
2873actual water quality. Also, r ule 62 - 302.500(2)(d) provides that
2884if an applicant for a C & D permit believes that turbid samples
2897are not representative of water quality, it may use filtered
2907samples by establishing a "translator" during the permitting
2915process. Respondent did not request a translator during the
2924permitting process, nor is any such translator provision found
2933in the Permit.
29362 3 . The expert also criticized EPT for holding the 2013
2948sample for iron for 22 days after collection before reanalyzing
2958it without providing any explanation for this delay . A
2968reasonable inference to draw from the data, however, is that
2978iron was present i n the original sample at levels that required
2990dilution and reanalysis.
29932 4 . Respondent 's expert testified that even though off -
3005site stormwater is discharged onto the property, no offsite
3014monitoring locations exist, and therefore any offsite
3021exceedances w ould not be reported. He also criticized the
3031sampling locations that were selected by EPT. In fairness to
3041Respondent, a repositioning of the monitoring network and
3049retesting of the samples might have produced more favorable
3058results . But these are measur es that should have been addressed
3070long before this proceeding was initiated. Finally,
3077Respondent 's expert testified that the implementation of its
3086RAP, now partially completed, will cure all of the reported
3096exceedances. A ssuming this unrefuted testimony is true, it
3105should be taken into account in determining an appropriate
3114penalty.
3115C. Count II - Failure to Implement a n RAP
31252 5 . In this Count, the Department alleges that after the
3137issuance of a n RAP Approval Order on July 3, 2013, Respondent
3149was required to implement the RAP within 120 days. The Notice
3160allege s that as of July 31, 2014, the RAP had not been
3173implemented.
31742 6 . A n RAP was first filed by Respondent on November 15,
31882010. See Dept. Ex. 3. When the Department determined that
3198changes to the R AP were necessary , the Consent Order imposed a
3210requirement that a n RAP addendum be filed within 150 days. The
3222date on which the addendum was filed is n ot known. However, a n
3236RAP Approval Order was issued on July 3, 2013. See Dept. Ex. 4.
3249The terms and c onditions in the RAP were incorporated into the
3261renewed Permit. The work required by the RAP consist s of two
3273phases, with all work to be completed within 365 days , or by
3285early July 2014 .
32892 7 . Phase I related to the initiation of an active
3301remediation sy stem within 120 days, or by October 31, 2013.
3312This phase require s Respondent to install a pump and treat
3323system at the facility, which will withdraw contaminated
3331groundwater through recovery wells, pump the water to aeration
3340basins to treat the water, and then re - infiltrate the treated
3352water back into the ground. As noted below, the system was not
3364operational until the second week in December 2014.
33722 8 . Respondent's failure to implement the approved RAP by
3383the established deadline constitutes a violation of rules 62 -
3393780.700(11) and 62 - 780.790 and Permit conditions, as charged in
3404the Notice.
34062 9 . While Respondent concedes that it did not comply
3417with the deadline for implementing the RAP , it points out that
3428work on Phase I was begun in a timely manner. Ho wever, on
3441October 16, 2013, or just before the 120 days had run, a Notice
3454of Violation was issued by the County. See Resp. Ex. 2. The
3466effect of the Notice of Violation was to halt m uch of the work
3480on Phase I until Respondent obtained a County stormwater permit .
3491Respondent asserts that this was responsible for all, or most,
3501of the delay.
350430. T he record shows that the EPT consultant did not a pply
3517for the County permit until September 10, 2014 , or almost one
3528year after the Notice of Violation was issued . Additional
3538information was required by the County, which was supplied on
3548October 23, 2014, but final sealed documents were not filed by
3559the consultant until a round Thanksgiving. The permit was issued
3569by the County " a week or so " before the final hearin g .
35823 1 . Respondent attributes the delay in applying for a
3593County permit to its former manager and his failure to
3603coordinate with the EPT engineers assigned to the project. It
3613also claims that the County failed to process the application in
3624an expeditiou s fashion . However , the facts suggest otherwise .
3635Once the permit was issued, Phase I was completed on December 8,
36472014 , and it was operational at the time of the final hearing.
36593 2 . Respondent 's expert , hired in August 2014, has
3670proposed a modification to the RAP t hat would avoid impacting
3681the existing stormwater pond. However, the modification must be
3690reviewed and approved by the Department, and as of the date of
3702the hearing, it had not been formally submitted. The Department
3712asserts that the only re ason the modification is being sought is
3724to reduce the cost of a performance bond. In any event, i n its
3738P RO, Respondent does not argue that the proposed modification
3748excuses its 13 - month delay in completing the requirements of
3759Phase I, or the second pha se of the project , which should have
3772been completed by early July 2014.
3778D. Count III - Failure to Provide Financial Assurance
37873 3 . This Count alleges that Respondent failed to provide
3798the required annual 2014 financial assurance mechanism that
3806demonstrate s proof of financial assurance for closure and long -
3817term cost estimates of the facility.
38233 4 . At the beginning of 2014, Respondent had an
3834$836,000.00 financial performance bond in place for closure and
3844long - term costs . T he Permit requires that on or befor e March 1
3860of each year Respondent revise the closure cost estimates to
3870account for inflation in accordance with rule 62 - 701.630(4).
3880See § 2, Spec. Cond. F.2. Once the estimates are approved, the
3892performance bond must be updated within 60 days. In this c ase,
3904an increase of around $18,000.00 was required.
39123 5 . The annual inflation adjustment estimate was not
3922submitted until April 15, 2014. The Department approved the
3931cost estimates the following day and established a due date of
3942June 16, 2014, for submitt ing a revised financial assurance .
3953Respondent did not have a revised performance bond in place
3963until a "week or two" before the hearing. Other than
3973Respondent's manager indicating that he had a new bonding agent,
3983no evidence was presented to mitigate thi s violation.
39923 6 . The failure to timely update its financial assurance
4003for closure and long - term costs constitutes a violation of rule
401562 - 701.630, as charged in the Notice.
4023E. Count IV - Financial Assurances for Corrective Action
40323 7 . In the same vein as Count III, the Notice alleges that
4046Respondent failed to maintain a financial assurance mechanism to
4055demonstrate proof that it can undertake the corrective action
4064program required under the RAP.
40693 8 . Respondent was required to submit proof of financial
4080assurance for corrective actions within 120 days after the
4089corrective action remedy was selected. On July 3, 2013, t he RAP
4101Approval Order selected the appropriate remedy . On August 8,
41112013, the Department approved Respondent's corrective action
4118program cost estimates of $566,325.85 and established a deadline
4128of October 31, 2013, for Respondent to submit this proof. When
4139the Notice was issued, a corrective action bond had not been
4150secured , and none was in place at the time of the final hearing .
4164Th is con stitutes a violation of rule 62 - 701.730(11)(d) and
4176applicable Permit conditions.
41793 9 . Respondent's manager , Mr. Miller, concedes that this
4189requirement has not been met. He testified that he was not
4200aware a new bond was required until he took over manageme nt of
4213the facility and met with Department staff on June 17 , 2014.
4224Due to the Notice, Mr. Miller says he has had significant
4235difficulty in securing a bond . He explained that the bonding
4246company is extremely reluctant to issue a bond to an entity
4257faced wi th possible revocation of its permit , especially if such
4268revocation might occur within a matter of months. Mr. Miller
4278says the bonding company wants 100 percent collateralization to
4287put a bond in place . Nonetheless, he is confident that a bond
4300can be sec ured if only because its cost will dramatically drop
4312when the RAP project is completed. However, even at hearing, he
4323gave no timeline on when this requirement will be fulfilled.
4333F. Count V - Objectionable Odors
433940 . One of the driving force s behind the i ssuance of the
4353Notice is the complaint about off - site objectionable odors. A
4364considerable amount of testimony was devoted to this issue by
4374witnesses representing the Department, County, Wedgewood
4380community , and Respondent . The Notice alleges that during
4389routine inspections in April, May, and July 2014, mainly in
4399response to citizen complaints, Department inspectors detected
4406objectionable odors both at the facility and off - site. The
4417Notice further alleges that Respondent failed to immediately
4425take steps t o reduce the odors, submit an odor remediation plan,
4437and implement that plan in violation of rules 62 - 296.320(2) and
444962 - 701.730(7)(e) and section 2, Specific Condition E of the
4460Permit . Notably, the Department has never revoked a landfill
4470permit due solely to objectionable odors.
44764 1 . Several Department rules apply to this Count . First,
4488objectionable odors are defined in rule 62 - 210.200(200).
4497Second, a C & D facility must control objectionable odors in
4508accordance with rule 62 - 296.320(2). Finally, i f odor s are
4520detected off - site, the facility must comply with the
4530requirements of rule 62 - 701.530(3)(b). That rule provides that
4540once off - site odors have been confirmed, as they were here, the
4553facility must "immediately take steps to reduce the
4561objectionable odo rs," "submit to the Department for approval an
4571odor remediation plan," and "implement a routine odor monitoring
4580program to determine the timing and extent of any off - site
4592odors, and to evaluate the effectiveness of the odor remediation
4602plan." These same regulatory requirements are embodied in the
4611Permit conditions. See § 2, Spec. Cond. E.
46194 2 . A t least occasionally, every landfill has
4629objectionable odors emanating from the facility. As one expert
4638noted, "The trick is, how can you treat it." The technic al
4650witnesses who addressed this issue agree that the breakdown of
4660drywall, wall board, and gypsum board , all commonly recycled at
4670C & D facilit ies , will produce hydrogen sulfide, which has a
4682very strong " rotten egg " type smell. The most effective
4691techniqu es for reducing or eliminating these odors are to spray
4702reactant on the affected areas, place more cover, such as dirt
4713or hydrated lime, on the pile, and have employees routinely
4723patrol the perimeters of the property and the active cell to
4734report any odors that they smell.
47404 3 . Although the facility has been accepting waste
4750products for a number of years, the last seven by Respondent,
4761the re is no evidence that the Department was aware of any odor
4774complaints before April 2014. While not an active participa nt
4784in the operations until recently, Mr. Miller also testified that
4794he was unaware of any citizen complaints being reported to the
4805facility prior to that date. However, i n response to citizen
4816complaints that more than likely were directed initially to the
4826County , on April 14, 21, and 24, 2014, the Department conducted
4837routine inspection s of the facility. During at least one of the
4849visit s , objectionable odors were detected both on - site,
4859emanating from cell 2, and off - site on West Pinestead Road, just
4872north of the facility. See Dept. Ex. 14. Because the inspector
4883created a single report for all three visits, he was unsure
4894whether odors were detected on more than one visit. After the
4905inspection report was generated, Department practice was to send
4914a copy b y email to the facility's former manager, Mr. Davidson.
49264 4 . A Department engineer who accompanied the inspector on
4937at least one visit in April 2014 testified that she has visited
4949the site on several occasions, and on two of those visits, the
4961odor was stro ng enough to make her physically ill.
49714 5 . On a follow - up inspection by the Department o n May 22,
49872014, the inspector did not detect any objectionable odors. See
4997Dept. Ex. 17. In June 2014, however, a County inspector visited
5008the Wedgewood Center area in response to a complaint that dust
5019was coming from the facility . He testified that he detected a
5031rotten egg type smell on the Wedgewood Center property.
50404 6 . At a meeting attended by Mr. Miller and County and
5053Department representatives on June 17, 2014 , the Department
5061advised Respondent of its findings and provided Mr. Miller with
5071copies of the inspection reports.
50764 7 . On July 1, 2014, the Department conducted a follow - up
5090inspection of the facility. The inspector noted a hydrogen
5099sulfide odor on the no rth, south, and west sides of the disposal
5112area of the facility, and on the top of the disposal pile at the
5126facility. See Dept. Ex. 18. Another inspection conducted on
5135July 9, 2014, did not find any objectionable odors. See Dept.
5146Ex. 19.
51484 8 . On July 18 , 2014, the Department conducted a follow - up
5162inspection of the facility. The inspector again noted
5170objectionable odors at the facility but none off - site . Id.
518249. On July 24, 2014, Department inspectors noted
5190objectionable odors on top of the pile, the toe of the north
5202slopes, and off - site on West Pinestead Road. See Dept. Ex. 20.
5215An inspection performed the following day noted objectionable
5223odors on top of the pile and the toe of the north slopes , but
5237none off - site . Id. The Notice, which was alread y being drafted
5251in mid - July, was issued a week later.
526050 . In response to the meeting on June 17, 2014,
5271Respondent prepared a draft odor remediation plan, made certain
5280changes suggested by the Department, and then submitted a
5289revised odor remediation plan prior to July 31, 2014. A
5299Department engineer agrees that "in the strict sense it meets
5309the requirements of the rule" and "could work," but there are
"5320two or three things that still needed . . . to be submitted in
5334order for it to be completely approvable. " For example, she was
5345uncertain as to how and when dirt cover would be applied, and
5357how erosion would be controlled. Although the plan was filed,
5367it was never formally approved or rejected , and the "two or
5378three things" that the witness says still neede d to be done were
5391n ever disclosed to Respondent. Under these circumstances, it is
5401reasonable to accept Respondent's assertion that it assumed the
5410plan was satisfactory and complied with the rule .
54195 1 . After the Notice was issued, Respondent set up a
5431hot line for community members to call and report odors. A sign
5443on the property gives a telephone number to call in the event of
5456odors. At an undisclosed point in time, Respondent began
5465requiring employees to walk the perimeter of the facility each
5475day to mo nitor for odors; spreading and mixing hydrated lime to
5487reduce the odors around the facility; and increasing the amount
5497of cover applied to the working face of the facility. The
5508parties agree that the se measures are the best available
5518practices to monitor and eliminate objectionable odors at a
5527C & D facility. Despite these good faith measures, Mr. Miller
5538acknowledged that he visited the facility during the evening a
5548few days before the final hearing in December 2014 and smelled
5559hydrogen sulfide around the ECUA sewer pipe and "a very mild
5570level" by the debris pile.
55755 2 . Respondent does not deny that odors were emanating
5586from the facility during the months leading up to the issuance
5597of the Notice. But i n April 2014, the County experienced a 500 -
5611year stor m event which caused significant flooding and damaged a
5622number of homes. Because Respondent operates the only C & D
5633facility in the County and charges less than the County
5643landfill , it received a n abnormal amount of soaked and damaged
5654C & D debris , which it contends could have generated some, if
5666not all , of the odors that month . Given the magnitude of the
5679storm, this is a reasonable explanation for the source of the
5690odors at that time .
569553. Respondent also presented evidence that an underground
5703ECUA se wer pipe that runs on the eastern side of the property
5716was damaged during the storm, causing it to rupture and be
5727exposed. Although ECUA eventually repaired the damaged pipe at
5736a later date , the pipe is still exposed above ground. Until the
5748pipe was repa ired, Respondent's assumption that it likely
5757contributed to some of the odors detected by the Department
5767appears to be valid . Finally, Respondent's expert attributes
5776some of the odors to biological degradation from other sources
5786both on - site and off - site , including a large wetland area
5799running through the middle of the property . To a small degree,
5811County testing later that fall confirms this assertion.
58195 4 . The County has also been a n active participant in the
5833odor complaint issue. In response to complai nts re ceived from
5844residents of Wedgewood , in July 2014 it began collecting
5853hydrogen sulfide data using a device known as the Jerome 631X
5864Hydrogen Sulfur D etector . This equipment is used to monitor for
5876the presence of hydrogen sulfur.
58815 5 . On July 21 and 22, 2014, samples were taken
5893documenting that hydrogen sulfide was coming from the facility.
5902In early September the County set up a fixed station at the
5914Wedgewood Center, around 500 feet from the edge of Respondent's
5924property, to continuously and automat ically collect the data.
5933During September and October 2014 the detector reported the
5942presence of hydrogen sulfide at that location 64 percent of the
5953days in those months, and this continued into the month of
5964November. Seventy - five percent of the exceedan ces occurred when
5975wind was blowing from the south, or when winds were calm. The
5987data also reflect ed that when the wind was blowing from the
5999meter to the facility , or to the south, hydrogen sulfide was
6010still detected on some occasions .
60165 6 . A resident of the Wedgewood community testified that
6027on multiple occasions she has smelled objectionable odors in her
6037home and yard and at the Wedgewood Center , and that the se odors
6050have been emanating from the facility for a number of years.
6061Because of the odors, she says fewer citizens are participating
6071i n programs hosted by the Wedgewood Center. 3 /
60815 7 . The evidence establishes that b efore the Notice was
6093issued, Respondent filed an odor remediation plan that was never
6103rejected; therefore, the allegation that a plan was not
6112submitted has not been proven . However, ob jectionable odors
6122were detected off - site in June and July 2014 , or after the April
6136inspection reports were provided to the facility, and they
6145continued throughout much of the fall . Therefore, the
6154Departme nt has established that the plan was not properly
6164implemented. These same findings sustain the allegation that
6172s teps were not immediately taken to reduce the objectionable
6182odors.
6183G. Count s VI and V II - Disposal and Failure to Remove
6196Unauthorized Waste
61985 8 . Count s V I and V II allege that on April 14, 2014, the
6215Department documented the disposal of prohibited or unauthorized
6223waste, including waste tires ; and that on July 18, 2014, the
6234Department conducted a follow - up inspection that documented the
6244disposal of unauthorized waste, including waste tires, clothing,
6252shoes, and Class I waste, including one electronic item and a
6263grill, in violation of rule 62 - 701.730(4)(d).
62715 9 . The Permit specifies that the facility can only accept
6283for disposal C & D debris. Se e § 2, Spec. Cond. C.2. Another
6297condition provides that if unauthorized debris is spotted after
6306a load is received, the unpermitted waste should be removed and
6317placed in temporary storage in a bin at the sorting area. See
6329§ 2, Spec. Cond. C.3. The Oper ations Plan spells out th ese
6342procedures in great detail.
634660 . Photographs received in evidence show that during the
6356inspection on April 14, 2014, the following unauthorized items
6365were observed at the facility : tires, a basketball goal,
6375Quiklube material, chromated copper arsenate treated wood, a
6383toy, and a crushed electronic item. See Dept. Ex. 22.
63936 1 . Photographs received in evidence show that during an
6404inspection on July 18, 2014, the following unauthorized items
6413were observed at the facility : blan ket or clothing, a shoe, a
6426bag of Class I garbage, several bags of household garbage,
6436furniture, an electronic item and garbage, drilling mud, a
6445suitcase, and tires. See Dept. Ex. 23.
64526 2 . Respondent's expert , who has trained numerous
6461spotters, includi ng a current Department inspector , established
6469that a de minimis amount of unpermitted waste, which is easily
6480hidden in the debris, is not unusual and would not constitute a
6492violation of the rule. For example, when a building is torn
6503down, numerous thermo stats containing mercury vile will be in a
6514C & D container but very difficult to see. Also, workers at
6526construction sites may throw small amounts of leftover food in
6536the pile of debris that goes to the facility. However, he
6547agrees that most , if not all, of the items observed during the
6559two inspection s would not be considered de minim i s.
65706 3 . Respondent does not deny that the unauthorized waste
6581was present on two occasions. However, it contends that one
6591would expect to find some of the items in a C & D dumpster. It
6606also argues that the amount of unauthorized waste was minimal
6616and not so serious as to warrant revocation of its Permit.
66276 4 . The evidence supports a finding that on two occasions
6639Respondent violated two condition s in its Permit by accepting
6649non - C & D waste and failing to remove it . Therefore, the
6663charges in Counts VI and VII have been proven.
6672H. Count VIII - Facility Outside of Permitted Dimensions
66816 5 . This Count alleges that on May 22, 2014, the
6693Department conducted a n inspection of the f acility in response
6704to a complaint that Respondent had disposed of solid waste
6714outside its permitted (vertical) limit of 130 NGVD ; that on
6724July 25, 2014, the Department had a survey performed at the
6735facility that confirmed this violation ; and that this ac tivity
6745violated s ection 2.3 of the facility's Operation Plan and
6755Specific Condition C.10 in the Permit.
67616 6 . Section 2.3 provides that "the proposed upper
6771elevation of waste at the [facility] will range up to 130 - feet,
6784NGVD, which is slightly above origi nal grade[,]" while Specific
6795Condition C.10 provides that "[t]he final (maximum) elevation of
6804the disposal facility shall not exceed 130 feet NGVD as shown on
6816Attachment 3 - Cell 2 Closure Grading Plan."
68246 7 . Respondent admits that on July 25, 2014, the maximum
6836height of the disposal pile exceeded 130 feet NGVD. However, it
6847argues that, pursuant to Specific Condition C.10, which in turn
6857refers to the Permit 's Cell 2 Closure Grading Plan, the 1 30 - foot
6872height limitation comes into play only when c ell 2 is being
6884closed and is no longer active. This interpretation of the
6894condition s is rejected for at least two reasons. First, a
6905disposal pile in excess of the established height would trigger
6915concerns about the integrity of the foundation of the facility.
6925Wh en the 130 - foot ceiling was established by the Department at
6938the permitting stage, it was based on calculations that the
6948ground could support the weight of the waste. Second, the
6958facility's financial assurance calculations are based on a set
6967dimension of the site; these calculations would likely be
6976impacted if there were no height restrictions. The Department's
6985interpretation is more reasonable and limits the height of the
6995pile to no more than 130 feet NVGD at any time when the cell is
7010active .
70126 8 . The De partment has established that Respondent
7022violated Permit condition s by disposing of waste outside its
7032maximum permitted height of 130 feet NVGD.
703969 . To Respondent's credit, its new consultant, Charles
7048Miller, completed preparation of a height reduction pl an on
7058September 3, 2014 . See Resp. Ex. 4. Although Mr. Miller says
7070the plan was being implemented at the time of final hearing, it
7082has never been formally submitted to the Department for
7091approval. Under the plan, Respondent proposes to extract all of
7101th e existing waste from the pile in the next two years. To
7114reduce the volume of new waste being accepted, Respondent
7123recently purchased a Caterpillar bulldozer , low - speed grinder ,
7132and Trommel screener . New waste will be shred d ed , screened to
7145separate sand and dirt from the material, and then ground and
7156compacted. Mr. Miller anticipates that the facility can achieve
7165u p to an eight to one (or at a minimum a five to one) reduction
7181in the size of the waste . This will dramatically reduce the
7193height of the pile and bring it well below 130 feet at closure.
7206But w hether c ell 2 is now below 130 feet NGVD is unknown. In
7221any event, t hese proposed remediation steps should be taken into
7232account in assessing an appropriate penalty.
7238CONCLUSION S OF LAW
72427 0 . Section 403 .087(7) (b) authorizes the Department to
7253revoke any permit issued if it finds that the permit holder has
"7265[v]iolated law, department orders, rules, or conditions that
7273directly relate to the permit." See also Fla. Admin. Code R.
728462 - 4.100(3)(b) ; § 403.704(10 ) , Fla. Stat.
72927 1 . The Department a rgues that it must prove the
7304allegations in the Notice by a preponderance of the evidence .
7315Respondent asserts that the charges should be proven by clear
7325and convincing evidence. Neither party has cited an
7333administrativ e decision or appellate case that directly
7341addresses th is issue , probably because section 403.087 (7) is an
7352enforcement tool that is rarely used. Notably, most of the
7362charges in the Notice were admitted by Respondent, and m uch of
7374its evidence was to mitiga te those violations.
73827 2 . Section 120.57(1)(j) provides that "[f]indings of fact
7392shall be based on a preponderance of the evidence, except in
7403penal or licensure disciplinary proceedings or except as
7411otherwise provided by statute." Un like an enforcement action
7420under section 403.121(2) (d) , the Legislature did not provide a
7430burden of proof to be applied in revocation proceedings under
7440section 403.087 (7) . By definition, h owever, the term "license"
7451includes a permit and "licensing" includes the agency proces s of
7462revocation . See § 120.52(10) and (11), Fla. Stat. Also, permit
7473revocation proceedings are penal in nature. Thus, the
7481proceeding can be fairly characterized as a "penal or licensure
7491disciplinary proceeding" because Respondent has contested the
7498Depar tment's decision to revoke its permit.
75057 3 . Case law makes a distinction between proceedings in
7516which sanctions involving a professional license are being
7524sought and other licensure disciplinary proceedings. In a
7532professional license setting, sanctions against the licensee
7539must be proven by clear and convincing evidence. See, e.g. ,
7549Dep't of Banking & Fin . v. Osborne , 670 So. 2d 932 (Fla. 1996).
7563In contrast, a C & D permit is not a professional license and
7576does not implicate the loss of livelihood . And , section 403.087
7587specifically provides that a permit issued under that provision
"7596shall not become a vested interest in the permittee . " Where
7607these circumstances are present, at least one court has held
7617that the proper standard of proof is preponderance of the
7627evidence. See Haines v. Dep't of Children and Famil i es , 983 So.
76402d 602 (Fla. 5th DCA 2008) (where statute provide s that a foster
7653care license d oes not create a property right in the rec i pient,
7667a preponderance of the evidence is the appropriate stand ard to
7678use in a license revocation proceeding) . 4 / But no matter which
7691standard is used, the Department has proven the charges set
7701forth below by clear and convincing evidence .
77097 4 . In a ruling at hearing, the undersigned denied the
7721Department's motion in limine that would preclude Respondent
7729from presenting evidence in mitigation of the charges. In its
7739PRO, the Department again argues that this proceeding is limited
7749to nothing more than proving (or disproving) that the permit
7759holder committed the alleg ed violation s . It points out that ,
7771unlike section 403.121 (10) , section 403.087 does not require it
7781to consider mitigating factors before revoking a permit.
778975. T he Department has allowed mitigating evidence in at
7799least two permit revocation proceeding s . See Dep't of Envtl.
7810Prot. v. Mahon , Case No. 11 - 2276 (Fla. DOAH Dec. 30, 2011; Fla.
7824DEP Mar. 20, 2012) ; Dep't of Envtl. Reg. v. Vail , Case No. 87 -
78384242 (Fla. DOAH Mar. 11, 1988; Fla. DER May 11, 1988) . While
7851the Department cites four revocation cases in which it contends
7861mi ti gating evidence was not allowed , all are distinguishable.
7871In three cases, the permit holder did not request a hearing.
7882The fourth case was decided primarily on a stipulation of facts
7893submitted by the parties . The Recommended and F inal Orders do
7905not say one way or the other whether evidence of mitigation was
7917presented. See Dep 't of Envtl. Reg. v. City of North Miami ,
7929Case No. 80 - 1168, 1981 Fla. ENV LEXIS 24 (Fla. DOAH Feb. 24,
79431981; DER Mar. 18, 1981). The undersigned is persuaded that the
7954concept of due process accords a permit holder the right to
7965present evidence of mitigation. The ruling on the motion in
7975limine is reaffirmed.
79787 6 . By clear and convincing evidence, the Department has
7989proven that Respondent exceeded surface water quality standards
7997for all analytes except nickel , as alleged in paragraph 6 of
8008Count I; that it failed to timely implement an RAP, as alleged
8020in Count II; that it failed to timely provide adequate financial
8031assurance for the facility, as alleged in Count III; that it
8042failed to provide financial assurance for corrective action, as
8051alleged in Count IV; that it failed to timely take steps to
8063reduce objectionable odors, and it failed to timely implement a
8073routine odor monitoring program, as alleged in Count V; that it
8084disposed of unauthorized waste, as alleged in Count VI; that it
8095failed to remove unauthorized waste, as alleged in Count VII;
8105and that it disposed of solid waste outside of its permitted
8116dimension of 130 feet NGVD, as alleged in Count VIII. The
8127r emaining charges should be dismissed.
81337 7 . Section 403.087( 7 ) provides that the Department "may"
8145revoke any permit if it finds that the permit holder has
"8156violated law, department orders, rules, or regulations, or
8164permit conditions." The Department has st eadfastly contended
8172that the Permit should be revoked . On the other hand ,
8183Respondent recommends that it be given a date certain on which
8194to obtain a bond, placed on probation for a specified period of
8206time, required to reduce the height of cell 2 below 13 0 feet
8219NGVD by a date certain, and required to continue to follow
8230Permit conditions related to monitoring , screening of waste , and
8239implementation of the RAP. In short, Respondent is seeking a
8249new set of deadlines to replace those first established in
8259Nove mber 2012 and February 2013 by the Consent Order and Permit,
8271respectively.
827278. The troubling aspect of this case is Respondent's
8281across - the - board failure to adhere to a number of deadlines and
8295Permit conditions established several years ago , and to make a ny
8306serious effort to comply with those requirements until it was
8316faced with possible revocation of its Permit. P erhaps this was
8327due to negligence and/or inattention by the former manager , who
8337was replaced in June 2014 , but this does not excuse its conduct .
8350At the same time, t he undersigned recognizes that once the
8361Notice was issued, with a new manager at the helm, Respondent
8372has inve sted a large amount of capital to purchase new equipment
8384and retain new consultants in an effort to bring the facility
8395into compliance. Even so , the date on which full compliance can
8406be achieved cannot be predicted.
841179. While revocation of the Permit seems especially harsh,
8420and the undersigned would impose a less draconian measure than
8430revocation given the evidence of mitig ation, the Department has
8440established the facts necessary to take that action.
8448Accordingly, Respondent's Permit should be revoked.
8454RECOMMENDATION
8455Based on the foregoing Findings of Fact and Conclusions of
8465Law, it is
8468RECOMMENDED that the Department of Envi ronmental Protection
8476enter a final order revoking Respondent's C & D Permit.
8486DONE AND ENTERED this 2nd day of March , 201 5 , in
8497Tallahassee, Leon County, Florida.
8501S
8502D. R. ALEXANDER
8505Administrative Law Judge
8508Division of Admi nistrative Hearings
8513The DeSoto Building
85161230 Apalachee Parkway
8519Tallahassee, Florida 32399 - 3060
8524(850) 488 - 9675
8528Fax Filing (850) 921 - 6847
8534www.doah.state.fl.us
8535Filed with the Clerk of the
8541Division of Administrative Hearings
8545this 2nd day of March , 201 5 .
8553EN DNOTE S
85561/ The County operates a large landfill that also accepts C & D
8569waste products. However, it is located west of Pensacola on the
8580Alabama state line , and the charges for using that service are
8591higher than Respondent's charges .
85962/ The Departmen t has a wide range of options in implementing its
8609enforcement process, ranging from a noncompliance letter to a
8618criminal referral. Thus, it has the discretion to use a notice
8629of revocation under section 403.087(7).
86343/ A Wedgewood resident testified that she believes the facility
8644has been contaminating her water supply. However, the water
8653supply in the Wedgewood community is served by the City of
8664Pensacola . There are no wells .
86714/ In contrast, where the imposition of an administrative fine is
8682sought i n an enforcement action under section 161.054, the
8692Department m ust prove those charges by clear and convincing
8702evidence. See, e.g. , Withers v. Dep't of Envtl. Prot. , Case No.
871302 - 0621 (Fla. DOAH Jan. 9, 2003; Fla. DEP Feb. 21, 2003).
8726COPIES FURNISHED:
8728Le a Crandall, Agency Clerk
8733Department of Environmental Protection
8737Mail Station 35
87403900 Commonwealth Boulevard
8743Tallahassee, Florida 32399 - 3000
8748(eServed)
8749B. Jack Chisolm, Jr., Esquire
8754Department of Environmental Protection
8758Mail Station 35
87613900 Commonwealth B oulevard
8765Tallahassee , Florida 32 399 - 3000
8771(eServed)
8772V. Nicholas Dancaescu, Esquire
8776GrayRobinson, P.A.
8778Post Office Box 3068
8782Orlando , Florida 32 802 - 3068
8788(eServed)
8789Craig D. Varn, General Counsel
8794Department of Environmental Protection
8798Mail Station 35
88013900 Commonwealth Boulevard
8804Tallahassee, Florida 32399 - 3000
8809(eServed)
8810Jonathan P. Steverson, Secretary
8814Department of Environmental Protection
8818Mail Station 35
88213900 Commonwealth Boulevard
8824Tallahassee, Florida 32399 - 3000
8829(eServed)
8830NOTICE OF RIGHT TO SUBMIT EXCE PTIONS
8837All parties have the right to submit written exceptions within 15
8848days of the date of this Recommended Order. Any exceptions to
8859this Recommended Order should be filed with the agency that will
8870render a final order in this matter.
- Date
- Proceedings
- PDF:
- Date: 05/29/2015
- Proceedings: Department's Response to South Palafox's Exceptions to Recommended Order filed.
- PDF:
- Date: 03/02/2015
- Proceedings: Recommended Order (hearing held December 9 through 11, 2014). CASE CLOSED.
- PDF:
- Date: 03/02/2015
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 02/10/2015
- Proceedings: (Respondent's) Proposed Findings of Fact and Conclusions of Law and Recommended Order filed.
- PDF:
- Date: 02/09/2015
- Proceedings: Department of Environmental Protection's Proposed Recommended Order filed.
- Date: 01/09/2015
- Proceedings: Transcript Volumes I-III (not available for viewing) filed.
- PDF:
- Date: 12/30/2014
- Proceedings: South Palafox Properties, LLC's Designation of Deposition Excerpts (Mike Keethler) filed.
- PDF:
- Date: 12/30/2014
- Proceedings: South Palafox Properties, LLC's Designation of Deposition Excerpts (Rosa Sestnov) filed.
- Date: 12/09/2014
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 12/08/2014
- Proceedings: South Palafox Motion in Limine to Exclude Evidence Related to Height of Facility filed.
- PDF:
- Date: 12/05/2014
- Proceedings: Florida Department of Environmental Protections Motion in Limine filed.
- PDF:
- Date: 12/03/2014
- Proceedings: Florida Department of Environmental Protection's Motion for Official Recognition filed.
- PDF:
- Date: 11/26/2014
- Proceedings: FDEP's Response to South Palafox Properties, LLC's First Request for Production to Petitioner filed.
- PDF:
- Date: 11/26/2014
- Proceedings: Notice of Serving State of Florida Department of Environmental Protection's Answers of First Interrogatories to Respondent filed.
- PDF:
- Date: 11/25/2014
- Proceedings: FDEP's Response to South Palafox Properties, LLC's First Requests for Admission to FDEP filed.
- PDF:
- Date: 11/18/2014
- Proceedings: Notice of Taking Depositions (of Terrance Davis, Chips Kirschenfeld, and Judy Cook) filed.
- PDF:
- Date: 11/18/2014
- Proceedings: Notice of Taking Depositions (of Chad Nowling, Dawn Templin, Alex Webster, Shawn Hamilton, and Rosa Setnov) filed.
- PDF:
- Date: 11/18/2014
- Proceedings: Amended Notice of Hearing (hearing set for December 9 through 12, 2014; 9:00 a.m., Central Time; Pensacola, FL; amended as to hearing room location).
- Date: 11/13/2014
- Proceedings: CASE STATUS: Motion Hearing Held.
- PDF:
- Date: 11/10/2014
- Proceedings: Amended Notice of Taking Deposition (of Scott Miller, Kevin Parsley, and Gary Bishop) filed.
- PDF:
- Date: 11/05/2014
- Proceedings: Notice of Taking Deposition (of Kevin Parsley, Scott Miller, Charlie Miller, and Gary Bishop) filed.
- PDF:
- Date: 10/27/2014
- Proceedings: Respondent South Palafox Properties, LLC's First Request for Production to Petitioner filed.
- PDF:
- Date: 10/27/2014
- Proceedings: Notice of Service of Respondent's First Set of Interrogatories filed.
- PDF:
- Date: 10/27/2014
- Proceedings: Notice of Service of Respondent's First Set of Interrogatories filed.
- PDF:
- Date: 10/27/2014
- Proceedings: Respondent South Palafox Properties. LLC's First Requests for Admissions to Petitioner filed.
- PDF:
- Date: 09/18/2014
- Proceedings: State of Florida Department of Environmental Protection's First Request for Production to Respondent filed.
- PDF:
- Date: 09/18/2014
- Proceedings: State of Florida Department of Environmental Protection's First Request for Admissions to Respondent filed.
- PDF:
- Date: 09/18/2014
- Proceedings: Notice of Serving State of Florida Department of Environmental Protection's First Interrogatories to Respondent filed.
- PDF:
- Date: 09/12/2014
- Proceedings: Department of Environmental Protection's Response in Opposition to Respondent South Palafox Properties, LLC's Request for Mediation filed.
- PDF:
- Date: 09/09/2014
- Proceedings: Petitioner's Unopposed Motion for Extension of Time to File Response to Respondent's Request for Mediation filed.
- PDF:
- Date: 09/09/2014
- Proceedings: Respondent South Palafox Properties, LLC's Request for Mediation filed.
Case Information
- Judge:
- D. R. ALEXANDER
- Date Filed:
- 08/12/2014
- Date Assignment:
- 08/14/2014
- Last Docket Entry:
- 01/15/2016
- Location:
- Pensacola, Florida
- District:
- Northern
- Agency:
- ADOPTED IN PART OR MODIFIED
Counsels
-
Jack Chisolm, Esquire
Address of Record -
V. Nicholas Dancaescu, Esquire
Address of Record -
Christopher T. Dawson, Esquire
Address of Record -
Margaret E. Seward, Esquire
Address of Record -
Christine Sue Cook, Attorney
Address of Record