86-000039 Port Everglades Authority vs. Department Of Environmental Regulation
 Status: Closed
Recommended Order on Friday, February 20, 1987.


View Dockets  
Summary: Application by port authority to construct turning notch failed to satisfy criteria of Walter Henderson Wetlands Protection Act.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8PORT EVERGLADES AUTHORITY , )

12)

13Petitioner , )

15)

16vs. ) CASE NO. 86-0039

21)

22DEPARTMENT OF ENVIRONMENTAL )

26REGULATION , )

28)

29Respondent , )

31and )

33)

34FLORIDA CHAPTER SIERRA CLUB and )

40FLORIDA AUDUBON SOCIETY and )

45BROWARD COUNTY AUDUBON SOCIETY , )

50)

51Intervenors . )

54__________________________________)

55RECOMMENDED ORDER

57Pursuant to notice, the Division of Administrative Hearings, by its duly

68designated Hearing Officer, William J. Kendrick, held a public hearing in the

80above-styled case on November 12-14, 1986, in Tallahassee, Florida.

89APPEARANCES

90For Petitioner : David S. Dee, Esquire

97Martha H. Hall, Esquire

101Carlton, Fields, Ward, Emmanuel,

105Smith, Cutler & Kent, P.A.

110Post Office Drawer 190

114Tallahassee, Florida 32302

117For Respondent : Deborah Getzoff, Esquire

123Karen A. Brodeen, Esquire

127Department of Environmental Regulation

1312600 Blair Stone Road

135Tallahassee, Florida 32301

138For Intervenor , Peter B. Belmont, Esquire

144Florida Chapter 511 - 31st Avenue North

151Sierra Club : St. Petersburg, Florida 33704

158For Intervenors,

160Florida Audubon

162Society and Charles Lee, Qualified Representative

168Broward County 1101 Audubon Way

173Audubon Society : Maitland, Florida 32751

179PRELIMINARY STATEMENT

181At issue in this proceeding is whether the application of Petitioner, Port

193Everglades Authority, for a dredge and fill Permit to excavate an 18.37 acre

206turning notch from an existing 71 acre mangrove forest should be granted.

218The transcript of hearing was filed with the Division of Administrative

229Hearings on December 2, 1986, and the parties were granted leave, at their

242request, until December 23, 1986, to file proposed findings of fact.

253Consequently, the parties waived the requirement that a recommended order be

264filed within 30 days of the date a transcript is filed. Rule 221-6.31, Florida

278Administrative Code. The parties' proposed findings of fact have been addressed

289in the appendix to this recommended order.

296FINDINGS OF FACT

2991. On September 10, 1984, Petitioner, Port Everglades Authority

308(Applicant), filed an application with the Department of Environmental

317Regulation (Department) for a dredge and fill permit to construct a turning

329notch to serve a new container facility it proposes to construct. The

341application was deemed complete on September 16, 1985, and on December 13, 1985,

354the Department gave notice of its intent to deny the application. The Applicant

367filed a timely request for formal administrative review of the Department's

378action.

379The Applicant

3812. The Applicant is a public corporation of Florida, a body politic,

393created by Special Act of the Legislature to further commerce in the state. The

407Applicant is a nonprofit entity whose profits are reinvested in port activities.

4193. Under the Applicant's charter, approximately 2,500 acres of land are

431designated as the "Port Everglades Jurisdictional Area". This area includes

442most of the land south of 17th Street (Ft. Lauderdale), east of Miami Road and

457Federal Highway, north of the Dania Cut-off Canal, and west of the Atlantic

470Intercoastal Waterway (ICW). Within this area the applicant enjoys the right to

482exercise police powers; landuse, platting and zoning powers; and, the powers of

494eminent domain. Additionally, the Applicant has Ad Valorem taxing power within

505the boundaries of Broward County.

5104. Currently, within its jurisdictional area, the Applicant owns

519approximately 750 acres of upland and 260 acres of submerged land in the turning

533basin, slips and channels. Much of the interface between land and water is

546occupied by steel and concrete bulkheads providing about 16,000 lineal feet of

559birthing for ships. About 230 acres of the property owned by the Applicant are

573undeveloped, and mostly used for the deposit of spoil from maintenance and new

586construction dredging.

588A New Container Facility

5925. To meet a presumed need, the Applicant is proposing to construct a new

606container terminal (south port) adjacent to the western edge of the ICW and

619approximately 7,300' south of the Port Everglades turning basin. This facility,

631to consist of 2,800' of bulkhead immediately north of the Dania Cutoff Canal, is

646designed to simultaneously berth two of the new generation of container ships

658and one of the current generation.

6646. Applicant owned lands available for construction of the facility

674presently consist of approximately 100 acres with 2,000' frontage on the ICW.

687These lands are located 800'-900' north of the Dania Cut-off Canal. To gain its

701desired 2,800' bulkhead line, the Applicant has undertaken condemnation

711proceedings against the owner (Hollywood, Inc.) of the property which abuts its

723southern boundary and extends to the Dania Cut-off Canal. Through this

734acquisition the Applicant will acquire an additional 91 acres to add to its

747holdings.

7487. Located immediately north of the Proposed container terminal is a 71-

760acre mangrove forest. Within these lands, the Applicant proposes to excavate

77118.37 acres to create a turning notch for ships using the new terminal. Impacts

785of the Proposed Turning Notch

7908. The mangrove forest is roughly rectangular in shape, with its long axis

803running north to south adjacent to the ICW. The north boundary of the forest is

818formed by the Florida Power and Light Company (FP&L) discharge canal. From this

831canal, several tidal creeks penetrate the forest. Generally, the forest can be

843described as a mature and healthy fringe mangrove system. The system is well

856flushed in the areas near the tidal creeks and the ICW, but less well flushed as

872one moves to the southwest.

8779. The proposed turning notch will occupy 18.37 acres in the southeast

889portion of the forest, abutting the new terminal and the ICW. The bottom

902dimensions of the notch will be 800' north to south and 900' east to west. Due

918to the 1:1 side slopes on the north and west sides of the notch, the top

934dimensions will measure 840' by 940'. The north and west sides of the notch

948will be constructed of rip-rap from a dredged depth of - 44' ML (mean low water)

964to 6' MLW. A sheet pile bulkhead will be installed along the southern

977boundary of the notch.

98110. The ICW is designated a Class III waterbody where it meets the notch

995area. The Applicant will take appropriate steps to minimize turbidity and water

1007quality impacts during construction. Among other things, the Applicant will

1017leave a "plug" adjacent to the ICW while the interior of the notch is dredged.

1032To ensure compliance with Department standards, turbidity monitoring will be

1042conducted during dredging activities. Built as proposed, and subject to the

1053Department's conditions, the Applicant has provided reasonable assurances that

1062construction of the proposed notch will not violate water quality standards.

1073The Applicant has failed, however, to provide reasonable assurances that its

1084project is not contrary to the public interest, as mandated by Subsection

1096403.918(2), Florida Statutes.

109911. In determining whether a project is not contrary to the public

1111interest, Subsection 403.91B(2)(a), Florida Statutes, requires that the

1119Department consider and balance seven criteria. These seven criteria are as

1130follows:

11311. Whether the project will

1136adversely affect the public health,

1141safety or welfare or the property

1147of others;

11492. Whether the project will

1154adversely affect the conservation

1158of fish and wildlife, including

1163endangered or threatened species,

1167or their habitats;

11703. Whether the project will

1175adversely affect navigation or the

1180flow of water or cause harmful

1186erosion or shoaling;

11894. Whether the project will

1194adversely affect the fishing or

1199recreational values or marine

1203productivity in the vicinity of the

1209project;

12105. Whether the project will be

1216of a temporary or permanent nature;

12226. Whether the project will

1227adversely affect or will enhance

1232significant historical and archaeo-

1236logical resources under the pro-

1241visions of s. 267.061; and

12467. The current condition and

1251relative value of functions being

1256performed by areas affected by the

1262proposed activity.

126412. The proof establishes that the proposed notch will be permanent, and

1276will result in the loss of approximately 26 percent of a mature, healthy, and

1290well flushed mangrove forest. This forest, as with all such forests, provides a

1303natural-habitat, as well as the base of a complex food chain, which shelters and

1317nurtures all the animals who live on the forest floor or in the adjacent waters.

1332Consequently, in addition to the loss of 18.37 acres of habitat and the animals

1346who dwell there, construction of the notch wilt also adversely impact the food

1359source for animals who live in the surrounding areas.

136813. The macroinvertebrate fauna (i.e.: crabs and snails) which dwell on

1379the forest floor and the trees themselves include large populations of at least

1392five species of crabs and two species of snails. An estimate of the population

1406size of these crabs, the most obvious inhabitants of the forest floor, range

1419from approximately 130,000 to an acre 50 yards west of the ICW to approximately

143446,000 to an acre close to the western edge of the proposed notch. These

1449numbers do not, however, include the population size of the tree-dwelling

1460mangrove crab. Construction of the notch will result in the loss of all of the

1475crabs and snails that occupy the site, as well as habitat for future

1488generations. While placement of rip-rap within the notch will provide a

1499substrate for organisms, such substrate will support an entirely different

1509community than exists presently, and will not offer any replacement for the

1521production of leave base which will be lost to the area.

153214. The bird population which frequents the notch site is not unique, and

1545no rare, endangered, or threatened species were observed. Three species of

1556special concern were, however, seen on-site : the little blue heron, tricolored

1568heron, and white ibis. While no evidence of nesting was observed, the notch

1581area is deep enough to support it and the area provides a ready food source for

1597both aquatic and land birds. This habitat would be lost through construction of

1610the notch.

161215. The warm waters discharged by FP&L into the canal which forms the

1625northern boundary of the forest are habitat for the manatee, an endangered

1637species. During the winter months, as the ambient water temperature begins to

1649drop, these animals are attracted to the discharge canal. At these times, up to

1663236 manatee have been observed in the port area.

167216. Manatee feed on a variety of aquatic plants; however, mangroves do not

1685constitute a significant part of their diet and the removal of the mangroves in

1699the area of the notch should have no adverse impact on the animals. Further,

1713the increased ship traffic anticipated at the new terminal, 400-500 ships a

1725year, should have no adverse impact on the manatee. These ships will be moving

1739at a maximum speed of 5 knots in a channel that is at least 500' wide. Under

1756such circumstances, the manatee should have little trouble avoiding injury.

176617. While the manatee will not be adversely impacted by construction of

1778the notch, the fish population of the area will lose a food source and habitat.

1793A tidal creek enters the northeast corner of the forest from the discharge

1806canal, and runs though the notch area. This tidal creek is quite deep on the

1821high tide, and provides a protective habitat for small fish. Construction off

1833the notch will eliminate approximately 800' of this small fish habitat, with a

1846resulting loss of a food source to the predator fish in the area.

185918. While the Applicant suggests that construction of the running notch

1870will improve navigation, the proof does not support its conclusion. The ships

1882using the turning notch will range in size from 800' to approximately 1,000'.

1896To successfully and safely turn ships of such magnitude would require an area of

1910at least 800' by 1400'. Consequently, the Applicant will be using a minimum of

1924500' of the ICW as part of its turning notch, and during the course of such

1940maneuver will impede navigation on the ICW. While ships using the Applicant's

1952new facility may find the turning notch an improvement to navigation, it is at

1966the expense of other traffic on the ICW.

197419. While the proposed project will not adversely affect the public

1985health, safety or welfare or the property of others, and will not adversely

1998affect significant historical and archaeological sites, a balancing of the

2008statutory criteria establishes that construction of the turning notch is

2018contrary to the public interest. 2/

2024Alternative Site Location for the New Terminal

203120. Prior to selecting south port as the site for its new container

2044facility, the Applicant evaluated its other land holdings to determine whether

2055an alternative site existed. In addition to south port, the Applicant

2066identified two other sites that could conceivably accommodate the new terminal.

2077These alternative sites would obviate the necessity of a turning notch in the

2090forest area. 3/

209321. The first alternative to the south port site, was to locate the

2106terminal in the northern section of the port along berths 11, 16, 17, and 18,

2121and to excavate from the area of berth 19 a 300' by 300' area. As envisioned,

2137this alternative would provide a berthing area of 2,700', but would require that

2151Slip No. 3 be filled, and a consequent loss of berths 12-15. Slip No. 3, and

2167berths 12-15, are part of the Applicant's petroleum facility. Since it is

2179extremely unlikely that there will be any reduction in the Applicant's petroleum

2191business, the elimination of that capability to install a new container facility

2203is not a viable alternative to the south port site.

221322. The second alternative to the south port site, was to locate the

2226terminal along the west side of the ICW, with a bulkhead line running north from

2241the FP&L discharge canal a distance of 2,700'. Adoption of this alternative

2254would require, however, that the port's dry dock and shipyard be closed and

2267filled, and a loss of about 600 shipyard jobs to the community. This is not a

2283viable alternative to the south port site.

229023. The alternatives considered , the proof establishes that the selection

2300of south port as the site for construction of the new container terminal was

2314appropriate. The vacant lands existent at south port will accommodate the new

2326facility without disrupting or curtailing the port's current petroleum, shipyard

2336or other activities.

2339The Need for the Turning Notch

234524. The new container facility will be located approximately 1 1/2 miles

2357south of the Port Everglades turning basin, and on the western shore of the ICW.

2372To accommodate the expected traffic, the Applicant has dredged the ICW from the

2385ship channel, which provides access to the port from the Atlantic Ocean, to the

2399terminal to a depth of 44' MLW and to a minimum bottom width of 500'. At such

2416depth and width, the ICW will accommodate the container ships in their passage

2429to and from the new terminal, but will not allow them the space needed to turn

2445around. Consequently, absent a turning notch, the ships would be required to

2457move astern on their inbound or outbound passage. This movement would require

2469that the ships move astern under their own power or with the assistance of tugs.

248425. The proof establishes that ships could not, within the confines of the

2497ICW, safely or effectively back to or from the new facility solely under their

2511own power. Ships are designed to travel through the water moving ahead. When a

2525ship goes astern, there is no steering capability.

253326. In addition to the loss of steerage, there are physical limitations on

2546both steam turbine vessels and motor ships (diesel-powered ships) which prevent

2557them from backing 1 1/2 miles, within the confines of the ICW under their own

2572power. In the case of a steam turbine vessel, the portion of the engine which

2587drives the ship astern is relatively small compared to the head turbine. That

2600small turbine would overheat within 8 minutes of operation, and require that the

2613ship's engine be put on dead slow ahead to cool the turbine. This maneuver

2627would slow, if not stop, the backward momentum of the ship. A motor ship, while

2642not possessed of the cooling problems of a steam turbine, generates so much

2655torque that the engine would have to be started and stopped continuously to keep

2669the ship's momentum astern, and at the same time not generate so much torque

2683that the ship will turn sideways in the channel. To restart a diesel requires

2697compressed air, and a motor ship does not have the compressed air capacity to

2711restart her engine a sufficient number of times to traverse the ICW in one

2725movement.

272627. Use of tugs to either assist the ships or to tow the ship's dead

2741(without using their engines) is the only viable alternative to a turning notch.

2754The Applicant asserts, however, that such alternatives are not acceptable from a

2766safety or economic view point, and that construction of a turning notch is

2779essential. The proof does not support the Applicant's assertion.

278828. The maneuver of piloting a ship of up to 1,000' between the ship

2803channel and the new facility, if the ship could move ahead using her own power,

2818would normally require the assistance of two tugs of at least 4,000 shp each.

2833The same two tugs could turn the vessel in a turning notch next to the terminal,

2849under average conditions of wind and current. Under conditions of stronger than

2861average wind and current, a third tug would have to be called out to insure that

2877the maneuver could be safely completed. 4/ Assuming the ship were turned on

2890the inbound leg of her trip, it would take approximately 1 1/2 hours to move her

2906from the sea buoy, turn her and berth her. The outbound leg would take

2920approximately 1 hour and 10 minutes.

292629. At the present time, there are three tugs based at Port Everglades.

2939One tug has 4,200 shp, and the other two have 2,000 shp. Since the two smaller

2957tugs have 2,000 shp each, a vessel of the size contemplated would need to use

2973all three existing tugs, under average conditions of wind and current, even if

2986it moved ahead under its own power while transiting the ICW and maneuvering in a

3001turning notch. To effect such a maneuver under most conditions would require

3013that at least one additional tug be added to the fleet based at Port Everglades.

30285/

302930. If there were no turning notch available, the ships could be backed

3042either to or from the new terminal. This maneuver would be accomplished by

3055either using tugs to tow a dead ship or using tugs to assist a ship backing

3071under its own power.

307531. A dead ship maneuver would require a combination of tugs having a

3088total of at least 15,000 shp under average conditions of wind and tide. Under

3103less than average conditions (i.e. : an incoming tide when the vessel wishes to

3117proceed outbound, or vice versa), a dead ship might have to await a slack tide

3132and, thereby, be delayed up to 5 hours in making her movement. This is, of

3147course, a worst case scenario, which assumes that the ship is positioned such

3160that it is necessary to back her, as opposed to having her move ahead. It is,

3176however, reasonable to design the facility so that ship movements can be

3188accomplished under most conditions without unnecessary delays. Consequently,

3196backing a dead ship to or from the terminal is not a viable alternative to a

3212turning notch.

321432. The use of tugs to counteract a motor vessel's torque and to assist

3228her in backing under her own power to or from the terminal, however, appears to

3243be a viable alternative to construction of the turning notch. Using such a

3256maneuver, a ship could be backed to the new terminal under average conditions in

3270approximately 2 hours, and her outbound transit time would be the same as with a

3285turning notch (1 hour and 10 minutes). The Applicant offered no proof that

3298under less than average conditions the time of transit, using this maneuver,

3310would be substantially increased or that this maneuver would require tugs of any

3323greater horsepower than would be required were a turning notch built.

3334Interestingly, if a turning notch were built as proposed by the Applicant, ships

3347would still have to be backed up to 2,800' between the notch and the terminal

3363under the same conditions they would have to endure were they backed the whole

3377way to the facility. Consequently, not only is the Applicant's assertion that

3389such maneuver is not safe or economical contrary to the proof, it is also not

3404credible.

340533. While motor vessels could be safely and effectively backed to or from

3418the new terminal with tug assist, the same does not hold true for steam turbine

3433vessels. The small turbine which drives the ship as term would quickly overheat

3446even with a tug assist, and inordinately protract the time necessary to transit

3459the ICW. The proof fails , however, to establish that the new terminal will have

3473to accommodate steam turbine vessels, as opposed to diesel powered vessels.

348434. The Applicant is proposing the new terminal to meet a perceived need

3497for additional container capacity, and has purportedly designed it to

3507accommodate the new generation (fifth generation) of container vessels. These

3517vessels will be 983' long, with a beam of 105' and a draft of 39' and will carry

35354,000 TEU's (ten foot equivalent units) at 20 knots. The Applicant offered,

3548however, no proof concerning the power mode of these new vessels. Consequently,

3560there being no proof to the contrary, it is reasonable to conclude that they, as

3575with the preceding two generations, will be diesel powered and that the new

3588terminal will have no need to accommodate steam turbine vessels. 6/

359935. The Applicant's assertion that ship owners, absent a turning notch,

3610would reject the new terminal as unsafe and uneconomical is not credited. The

3623proof establishes that the ships reasonably expected to use the terminal can be

3636safely backed to or from it with the assistance of tugs, and with no apparent

3651increase in cost over that which would be incurred if a turning notch is

3665utilized. Even if additional tugs were needed, that cost would only add $1,200-

3679$1,500 for each additional tug. The Applicant offered no evidence of the cost

3693of utilizing the facility, with or without the notch, and did no marketing

3706studies. Consequently, the Applicant's conclusion that ship owners would find

3716the new terminal uneconomical absent a turning notch is unpersuasive.

3726Other Considerations

372836. In view of the finding that the Applicant failed to demonstrate any

3741need for a turning notch, it is unnecessary to address the issue of alternative

3755placement of the notch or the Applicant's mitigation proposal.

3764CONCLUSIONS OF LAW

376737. The Division of Administrative Hearings has jurisdiction over the

3777parties to, and the subject matter of, these proceedings.

378638. The Department's review of the application at issue in this case is

3799governed by Sections 403.91-403.929, the "Warren S. Henderson Wetlands

3808Protection Act of 1984" (The Henderson Act). Pertinent to this case Section

3820403. 918, Florida Statutes, provides:

3825403.918 Criteria for granting or

3830denying permits. -

3833(1) A permit may not be issued

3840under ss. 403.91-403.929 unless the

3845applicant provides the department

3849with reasonable assurance that

3853water quality standards will not be

3859violated. The department, by rule,

3864shall establish water quality

3868criteria for wetlands within its

3873jurisdiction, which criteria give

3877appropriate recognition to the

3881water quality of such wetlands in

3887their natural state.

3890(2) A permit may not be issued

3897under ss. 403.91-403.929 unless the

3902applicant provides the department

3906with reasonable assurance that the

3911project is not contrary to the

3917public interest....

3919(a) In determining whether a

3924project is not contrary to the

3930public interest ... the department

3935shall consider and balance the

3940following criteria:

39421. Whether the project will

3947adversely affect the public health,

3952safety or welfare or the property

3958of others;

39602. Whether the project will

3965adversely affect the conservation

3969of fish and wildlife, including

3974endangered or threatened species,

3978or their habitats;

39813. Whether the project will

3986adversely affect navigation or the

3991flow of water or cause harmful

3997erosion or shoaling;

40004. Whether the project will

4005adversely affect the fishing or

4010recreational values or marine

4014productivity in the vicinity of the

4020project;

40215. Whether the project will be

4027of a temporary or permanent nature;

40336. Whether the project will

4038adversely affect or will enhance

4043significant historical and archaeo-

4047logical resources under the pro-

4052visions of s. 267.061; and

40577. The current condition and

4062relative value of functions being

4067performed by areas affected by the

4073proposed activity.

4075(b) If the applicant is unable to

4082otherwise meet the criteria set

4087forth in this subsection, the

4092department, in deciding to grant or

4098deny a permit, shall consider

4103measures proposed by or acceptable

4108to the applicant to mitigate

4113adverse effects which may be caused

4119by the project....

412239. The Henderson Act establishes two criteria which must be satisfied

4133before a dredge and fill project may be permitted. First, the applicant must

4146provide reasonable assurance that water quality standards will not be violated.

4157Section 403.918(1), Florida Statutes. Second, the applicant must provide

4166reasonable assurance that the project is not contrary to the public interest.

4178Section 403.918(2), Florida Statutes. In this case, the Applicant has satisfied

4189the first criteria, but has failed to satisfy the second criteria. 7/

420140. Where, as here, an applicant's project does not satisfy the public

4213interest criteria established by subsection 403.918(2)(a), its project may be

4223permitted if it can establish, pursuant to subsection 403.918(2)(b), that it is

"4235unable to otherwise meet the criteria" set forth in subsection 403.918(2)(a)

4246and proposes an acceptable plan to mitigate the adverse affects of its project.

4259The Intervenors assert that if reasonable alternatives exist to avoid adverse

4270impacts to the environment, the applicant has failed to establish that it is

4283unable to otherwise meet" the requirements of subsection 403. 918(2)(a ), and

4295consideration of any mitigation proposals are inappropriate. I agree with the

4306Intervenors.

430741. In interpreting legislative intent one must look to the plain language

4319of the statute at issue. Furthermore, the legislature must be assumed to know

4332the meaning of the words it has used and to have expressed its intent by the use

4349of the words found in the statute. See: Thayer v. State, 335 So.2d 515 (Fla.

43641976) and Carson v. Miller, 370 So.2d 10 (Fla. 1979).

437442. In construing the meaning of ordinary words used in a statute the

4387courts have routinely turned to dictionary definitions. The dictionary defines

"4397otherwise" to mean "in another manner" or "differently". Webster's New World

4409Dictionary, College Edition. Therefore, I conclude that in construing the plain

4420language of the statute that it requires an applicant to show that it is unable

4435in another manner, i.e. : through alternatives, to meet the criteria set forth

4448in subsection 403.918(2)(a) before the Department has authority to consider

4458mitigative measures. I can find no other reasonable interpretation of the word

"4470otherwise" as used in the statute. I also cannot ignore the word because one

4484should never assume that language in a statute is mere surplusage. One must

4497presume that the legislature has inserted language for a purpose. See: Stein

4509v. Biscayne Kennel Club, 199 So. 364 (Fla. 1940).

451843. As I have noted in my findings of fact, the Applicant has not

4532demonstrated that its new container terminal cannot be operated safely or

4543economically without the construction of the turning notch. Although the

4553Applicant may prefer its design scheme, its "no action alternative" to

4564construction of the notch (the use of tugs) satisfies the mandate of subsection

4577403.918(2)(a) and permits it to realize the development potential of its new

4589terminal.

459044. In reaching this conclusion, I am not unmindful of the fact that the

4604legislature found that Florida's wetlands perform essential economic and

4613recreational functions, that continuation of the past practice of alteration and

4624development of the state's inventory of wetlands will cause extensive damage to

4636the state's economic interests and recreational values, and that the current

4647state policy is to preserve and to protect the state's remaining wetlands to the

4661greatest extent practicable. See: Chapter 84-79, Laws of Florida, 1984.

4671RECOMMENDATION

4672Based on the foregoing Findings of Fact and Conclusions of Law, it is

4685RECOMMENDED:

4686That the application of Port Everglades Authority for a dredge and fill

4698permit be DENIED.

4701DONE AND ORDERED this 20th day of February, 1987, in Tallahassee, Florida.

4713___________________________________

4714WILLIAM J. KENDRICK

4717Hearing Officer

4719Division of Administrative Hearings

4723The Oakland Building

47262009 Apalachee Parkway

4729Tallahassee, Florida 32301

4732(904) 488-9675

4734Filed with the Clerk of the

4740Division of Administrative Hearings

4744this 20th day of February, 1987.

4750ENDNOTES

47511/ The Applicant currently holds a permit from the Department to construct

47632,000' of bulkhead on its existent property. This application to construct a

4776turning notch is a separate application dealing with the same project.

4787Additionally, the Applicant will need a separate permit for the southerly 800'

4799of bulkhead when it acquires the Hollywood, Inc., property, and a ground water

4812discharge permit since excavation of the turning notch would pierce the Biscayne

4824Aquifer. Why this project was allowed to proceed in such a piecemeal fashion is

4838unexplained on this record.

48422/ The Applicant concedes its project is contrary to the public interest. See:

4855Applicant's proposed findings of fact and conclusions of law, page 30.

48663/ At hearing, no party offered any evidence that the new terminal could be

4880accommodated at any site other than those addressed by the Applicant.

48914/ The proof fails to reflect the horsepower rating needed for this third tug.

49055/ The applicant made much ado about the cost of purchasing additional tugs if

4919it were required to back the ships to the new facility. The tugs at Port

4934Everglades are, however, operated by a private company. Notwithstanding a cost

4945of $1,500,000 for a 2 ,000 shp tug, it is reasonable to assume additional tugs

4962would be added to the fleet if there were a demand. It is not the cost of the

4980tugs but, rather, the towing charges that are germane to this proceeding. The

4993impact of those charges on the Applicant's ability to attract business at its

5006new facility are discussed infra. Suffice it to say at this point that, even

5020moving ahead, the port will need at least one additional tug.

50316/ The third generation of container vessels were delivered between the late

50431960's and mid 1970's. These vessels were 800- 950' long , 100' beam, and

5056carried between 1,500-2,000 TEU's. When the price of fuel increased in 1974 and

5071again in 1978 these vessels proved to be uneconomical to operate at standard

5084speeds (27-35 knots) and were slowed to operational speeds of 19-20 knots. Part

5097of these vessels were subsequently converted to diesel and the remainder sold to

5110the U.S. Navy as part of its rapid disployment fleet. The fourth generation of

5124container vessels were constructed in the late 1970's and early 1980's. These

5136vessels were 800'-900' long, with a 105' beam and draft of 41', carried 1,800-

51512,500 TEU's, and were diesel power (Petitioner's exhibit 2, Chapter IV, page 5).

51657/ During the course of the proceedings the Intervenors contended that evidence

5177outside of matters affecting environmental considerations should not be weighed

5187for purposes of determining whether the project will not be contrary to the

5200public interest. At hearing, the Applicant offered proof concerning non-

5210environmental factors such as the creation of jobs by the new facility, and

5223potential economic losses to the community if the facility is not built. I tend

5237to agree with the Intervenors. The construction of any project, whether it be a

5251single family residence or a port facility, will have both short and long term

5265impacts on the demand for goods and services and, therefore, the economy. Such

5278matters would not, however, appear to be appropriate considerations under The

5289Henderson Act. See: Grove Isle, Ltd. v. Department of Environmental

5299Regulation, 454 So.2d 571 (Fla. 1st DCA 1984) and Mandarin Landing Association,

5311Ltd. v. Department of Transportation, 8 FALR 633 (DER 1985). However, it is not

5325necessary to address this issue in the instant case in light of my finding that

5340the Applicant's new container facility does not require a turning notch to prove

5353feasible.

5354APPENDIX TO RECOMMENDED ORDER, CASE NO. 86-0039

5361The Applicant's proposed findings of fact are addressed as follows:

53711. Addressed in paragraph 2.

53762-3. Addressed in paragraph 1.

53814. Addressed in paragraph 3.

53865. Addressed in paragraphs 5 and 7.

53936. Not necessary to result reached.

53997. Addressed in paragraphs 3, 6 and 34.

54078. Addressed in paragraph 24.

54129-12. Addressed in paragraphs 24-35.

541713. Rejected as contrary to the proof.

542414. Addressed in paragraphs 28-29, 31-32.

543015. Addressed in paragraph 31.

543516. Addressed in paragraph 35.

544017. Addressed in paragraphs 32 and 35.

544718-23. Not necessary to result reached.

545324. Not necessary to result reached.

545925. Addressed in paragraph 21.

546426. Addressed in paragraph 22.

546927-28. Not necessary to result reached.

547529. Addressed in paragraphs 7 and 8.

548230. Addressed in paragraph 9.

548731-33. Addressed in paragraph 10.

549234-36. Addressed in paragraphs 8 and 12.

549937. Addressed in paragraph 13.

550438-39. Addressed in paragraph 17.

550940. Addressed in paragraph 14.

551441. Addressed in paragraphs 15-19.

551942-49. Addressed in paragraphs 15 and 16.

552650-70. Not necessary to result reached.

553271. First two sentences addressed in paragraph 19. Third

5541sentence not necessary to result reached.

554772-76. Not necessary to result reached.

555377. First sentence addressed in paragraph 12. Second

5561sentence not necessary to result reached.

556778-86. Not necessary to result reached.

557387. Addressed in paragraphs 12 and 17.

558088-90. Not necessary to result reached.

5586The Department's proposed findings of fact are addressed as follows:

55961. Addressed in paragraphs 1 and 7.

56032. Addressed in paragraphs 24-36.

56083. Addressed in paragraphs 7 and 8.

56154-7. First sentence of paragraph 4 addressed in paragraph 8.

5625Remainder not relevant or not necessary to result

5633reached.

56348-15. Not necessary to result reached.

564016-18. Addressed in paragraph 15-16.

564519. Not necessary to result reached.

565120. Not necessary to result reached.

565721. Rejected. The project, the new terminal facility, may

5666increase economic development but the notch will not.

5674construction of the notch is not essential to the

5683development of the facility.

568722. Not necessary to result reached.

569323. Not relevant and not necessary to result reached.

5702The Intervenor's proposed findings of fact are addressed as follows:

57121-8. Addressed in paragraphs 15-16.

57179. First two sentences rejected as not supported by

5726competent proof. Last sentence not relevant.

573210-19. To the extent necessary addressed in paragraphs 8 and

574212, otherwise not necessary to the result reached.

575020-21. Addressed in paragraph 17.

575522-28. Not necessary to result reached.

576129-42. Not necessary to result reached.

576743. Addressed in paragraph 35.

577244. Addressed in paragraphs 24-35.

577745. Not necessary to result reached.

578346-64. Not necessary to result reached.

578965-66. Addressed in paragraph 13.

579467-69. Not necessary to result reached.

580070. Addressed in paragraph 17.

580571. Not necessary to result reached.

581172-75. Addressed in paragraph 17.

581676. Not necessary to result reached.

582277. Addressed in paragraphs 13, 17 and 19.

583078-79. Not necessary to result reached.

583680-83. Addressed in paragraph 14.

584184-94. Not necessary to result reached.

5847COPIES FURNISHED:

5849David S. Dee, Esquire

5853Martha H. Hall, Esquire

5857Carlton, Fields, Ward, Emmanuel,

5861Smith, Cutler & Kent, P.A.

5866Post Office Drawer 190

5870Tallahassee, Florida 32302

5873Deborah Getzoff, Esquire

5876Karen A. Brodeen, Esquire

5880Department of Environmental

5883Regulation

58842600 Blair Stone Road

5888Tallahassee, Florida 32301

5891Peter B. Belmont, Esquire

5895511 - 31st Avenue North

5900St. Petersburg, Florida 33704

5904Charles Lee, Qualified

5907Representative

59081101 Audubon Way

5911Maitland, Florida 32751

5914Dale Twachtmann, Secretary

5917Department of Environmental Regulation

59212600 Blair Stone Road

5925Tallahassee, Florida 32399-2400

5928Daniel H. Thompson, General Counsel

5933Department of Environmental Regulation

59372600 Blair Stone Road

5941Tallahassee, Florida 32399-2400

5944STATE OF FLORIDA

5947DIVISION OF ADMINISTRATIVE HEARINGS

5951PORT EVERGLADES AUTHORITY , )

5955)

5956Petitioner , )

5958)

5959vs. ) CASE NO. 86-0039

5964)

5965STATE OF FLORIDA, DEPARTMENT )

5970OF ENVIRONMENTAL REGULATION )

5974)

5975Respondent , )

5977and )

5979)

5980FLORIDA CHAPTER SIERRA CLUB , )

5985FLORIDA AUDUBON SOCIETY, and )

5990BROWARD COUNTY AUDUBON SOCIETY , )

5995)

5996Intervenors . )

5999__________________________________)

6000SUPPLEMENTAL RECOMMENDED ORDER

6003By order dated April 6, 1987, the Department of Environmental Regulation

6014(Department) remanded the above-styled case to the under signed Hearing Officer

6025to enter findings of fact addressing the applicant's proposed mitigation plan,

6036and to assess the permittability of the project in light of the applicant's

6049mitigation proposal. The Hearing Officer accepts the Department's remand, and

6059enters the supplemental findings of fact which follow in accordance with the

6071Department's request.

6073SUPPLEMENTAL FINDINGS OF FACT

60771. The applicant has proposed, as part of its project, certain mitigation

6089activities designed to offset the adverse environmental impacts that would be

6100caused by the dredging of the proposed turning notch. These proposals consist

6112of (a) the creation of 23 acres of new mangrove forest in the John U. Lloyd

6128State Recreation Area (Park) which lies across the ICW from the proposed notch;

6141(b) the construction of approximately 7300 linear feet of riprap along the

6153eastern edge of the ICW to protect existing and proposed mangrove areas from

6166excessive tidal or wave action; (c) the enhancement of 16 acres of existing

6179mangrove forest in the Park; (d) the deepening of an existing tidal creek in the

6194Park to create a manatee sanctuary; and (e) the grant of a conservation easement

6208to the Department which would prohibit any future development in the remaining

6220acres of mangrove forest adjacent to the proposed notch.

62292. The 23 acres on which the applicant proposes to create a new mangrove

6243forest are presently vegetated with exotic plants, primarily Australian pine and

6254Brazilian pepper. The applicant proposes to remove the exotics, scrape the area

6266to an appropriate inter tidal elevation, and handplant approximately 165,000 red

6278mangrove seedlings on three foot centers. The new mangroves will be monitored

6290and maintained for seven years, with at least an 80 percent survival rate. 1/

63043. To evaluate its plan for creating new mangrove areas, the applicant

6316planted 3,800 red mangroves in a pilot project along the east side of the, ICW,

6332adjacent to the Park. Following the passage of two years, those mangroves have

6345evidenced a survival rate of approximately 80 percent, and white and black

6357mangrove recruits have established themselves on the site.

63654. The applicant has provided reasonable assurances that its' mangrove

6375project will survive, and that its character will be similar to the well-flushed

6388fringe mangrove forest that will be displaced by the notch. The new mangroves

6401should develop a canopy in four to six years , at which time the production of

6416leaf litter will be maximized. When the canopy develops, the per acre

6428productivity of the new mangrove forest should be similar to the present

6440productivity of the mangroves in the notch.

64475. In addition to creating 23 acres of new mangroves to replace the 18

6461acres lost by construction of the notch, the applicant's project will improve

6473the health and productivity of those mangroves presently growing in the Park.

6485This will be accomplished by the removal of the exotics which currently shade A

6499the existing mangroves and by the improvement of the tidal circulation.

65106. In conjunction with its mangrove planting project, the applicant will

6521install approximately 7,300 feet of riprap along the eastern shore of the ICW,

6535an area subject to severe erosion. The ripap, which will be constructed to a

6549height of feet MLW (mean low water), will protect the shoreline, the existing

6562mangroves, and the newly planted mangroves from erosion, turbulent water and

6573floating debris. 2/

65767. Fish populations and fishing values will directly benefit from the

6587riprap and new mangroves by providing shelter and a food source. While large

6600fish and materials will not generally pass through the interstitial spaces in

6612the riprap, small fish and other marine organisms will. 3/ These small fish

6625will be protected from predators part of the time, but at low tide they will be

6641forced through the riprap and into the ICW where they will provide a food

6655service for larger fish.

66598. The macroinvertebrate population of the area will increase in number

6670and diversity as a result of the mitigation plan. In the long-term, the

6683macroinvertebrate habitat of the mitigation area will be similar to that

6694presently existing in the notch area. Additionally, new macroinvertebrate

6703communities will emerge along the riprap.

67099. The mitigation proposal will also create a net benefit to the local and

6723migratory bird population found in the area. The creation of 23 acres of

6736mangroves, together with the enhancement area, infra, will provide additional

6746habitat and improved food source for the birds.

67541O. The third feature of the applicant's mitigation proposal is the

6765enhancement of approximately 16 acres of mangroves in the interior of the Park.

6778These mangroves are presently stressed and poorly flushed. The applicant

6788proposes to excavate ditches from the enhancement area to Whiskey Creek, a tidal

6801creek running through the interior of the Park, and scrape, certain upland areas

6814to create inter tidal elevations between Whiskey Creek and the enhancement area.

6826As a result of the ditching and the removal of upland areas, there will be

6841improved tidal penetration and circulation within the enhancement ,area. This

6851will translate to increased leaf litter production, and the export of more

6863detritus to the marine environment.

686811. In the fourth part of its mitigation plan, the proposes to construct a

6882manatee refuge in a U-shaped cove in the Park. While manatee should not be

6896adversely impacted by the proposed projet, the proof did establish that boats

6908are the largest cause of manatee injury and mortality. Construction of the

6920proposed refuge outside the active waters of the ICW should, therefore, increase

6932the survival rate of this endangered species.

693912. Finally, the applicant has agreed to grant the Department a

6950conservation easement to the 53 acres of mangrove forest that will remain after

6963construction of the turning notch. The dedication of a permanent conservation

6974easement over the remaining mangrove forest will ensure that future construction

6985projects are not undertaken in this area, and that adverse cumulative impacts do

6998not occur.

700013. At hearing, the Department announced its intention to impose all of

7012the conditions contained in its September 16, 1986, draft permit, except for

7024condition number, 11, which dealt with the removal of exotics within the

7036conservation easement. The Department also added two new conditions designed

7046to provide additional protection for the manatee. The new conditions would

7057require, all work boats to observe idle speed restrictions in the manatee

7069sanctuary at all times during construction. The Department would also require

7080that the applicant receive approval from the Department of Natural Resources

7091before working in open waters during the manatee season. The applicant agreed

7103to accept and comply with all of the Department's proposed conditions.

711414. The proof establishes that the applicant's mitigation plan, built as

7125proposed and subject to the Department's permit conditions, will produce a net

7137benefit for the environment. On balance, this benefit outweighs the negative

7148impact to the environment that would be occasioned by the construction of the

7161turning notch and renders the project not contrary to the public interest.

7173SUPPLEMENTAL RECOMMENDATION

7175Based on the foregoing Supplemental Findings of Fact and the Department's

7186order of remand, dated April 6, 1987, it is

7195RECOMMENDED:

7196That the subject dredge and fill permit be ISSUED, subject to the

7208Department's proposed permit conditions.

7212DONE AND ORDERED this 27th day of May, 1987, in Tallahassee, Florida.

7224___________________________________

7225WILLIAM J. KENDRICK

7228Hearing Officer

7230Division of Administrative Hearings

7234The Oakland Building

72372009 Apalachee Parkway

7240Tallahassee, Florida 32399-1550

7243(904) 488-9675

7245Filed with the Clerk of the

7251Division of Administrative Hearings

7255this 27th day of May, 1987.

7261ENDNOTES

72621/ The applicant has its own mangrove nursery. Consequently, if any of the

7275young trees fail to mature, the applicant can promptly replace it.

72862/ Some sand particles could pass through the riprap and settle on the bottom,

7300but this should not occur to any significant degree because the water in the ICW

7315is relatively sediment-free. Accordingly, there should be no siltation problem

7325which would adversely affect the mangrove plantings.

73323/ The applicant, at the Department's request, has agreed to incorporate larger

7344openings in some areas of the riprap so that larger fish can move through the

7359area.

7360COPIES FURNISHED:

7362Dale Twatchtmann, Secretary

7365Department of Environmental

7368Regulation

73692600 Blair Stone Road

7373Tallahassee, Florida 32399-2400

7376David S. Dee, Esquire

7380Martha H. Hall, Esquire

7384CARLTON, FIELDS, WARD, EMMANUEL,

7388SMITH, CUTLER & KENT, P.A.

7393Post Office Drawer 190

7397Tallahassee, Florida 32301

7400Peter B. Belmont, Esquire

7404511 - 31st Avenue North

7409St. Petersburg, Florida 33704

7413Charles Lee, Qualified

7416Representative

74171101 Audubon Way

7420Maitland, Florida 32751

7423Deborah Getzoff, Esquire

7426Karen a. Brodeen, Esquire

7430Department of Environmental

7433Regulation

74342600 Blair Stone Road

7438Tallahassee, Florida 32399-2400

7441Carol Forthman, Deputy General Counsel

7446Department of Environmental

7449Regulation

74502600 Blair Stone Road

7454Tallahassee, Florida 32399-2400

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 02/20/1987
Proceedings: Recommended Order
PDF:
Date: 02/20/1987
Proceedings: Recommended Order (hearing held , 2013). CASE CLOSED.

Case Information

Judge:
WILLIAM J. KENDRICK
Date Filed:
01/07/1986
Date Assignment:
01/10/1986
Last Docket Entry:
02/20/1987
Location:
Tallahassee, Florida
District:
Northern
Agency:
Department of Environmental Protection
 

Related DOAH Cases(s) (1):

Related Florida Statute(s) (1):