88-006296BID
Dickerson Florida, Inc. vs.
Department Of Transportation
Status: Closed
Recommended Order on Friday, February 17, 1989.
Recommended Order on Friday, February 17, 1989.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8DICKERSON FLORIDA, INC., )
12)
13Petitioner, )
15)
16vs. ) CASE NO. 88-6296BID
21)
22DEPARTMENT OF TRANSPORTATION, )
26)
27Respondent. )
29_________________________________)
30RECOMMENDED ORDER
32Pursuant to notice, the Division of Administrative Hearings, by its duly
43designated Hearing Officer, William J. Kendrick, held a formal hearing in the
55above-styled case on January 3, 1989, in Tallahassee, Florida.
64APPEARANCES
65For Petitioner: Robert N. Ervin, Esquire
71Wilfred C. Varn, Esquire
75Ervin, Varn, Jacobs, Odom
79& Ervin
81305 Gadsden Street
84Tallahassee, Florida 32301
87For Respondent: J. Marleen Ahearn, Esquire
93Department of Transportation
96Haydon Burns Building, MS-58
100Tallahassee, Florida 32399-0458
103PRELIMINARY STATEMENT
105These proceedings arose as a result of an invitation to bid (ITB) issued by
119Respondent, Department of Transportation (Department), for road work on SR-76
129(Kanner Highway) in Martin County, Florida (State Project No. 89060-3523). The
140Department proposed to reject the bid of petitioner, Dickerson Florida, Inc.
151(Dickerson), the apparent low bidder, as non-responsive for failure to achieve
162the disadvantaged business enterprise (DBE) goal, and to award the contract to
174Ranger Construction Industries, Inc. (Ranger), the next apparent low bidder.
184Dickerson protested the Department's proposed action.
190At final hearing, Dickerson called as witnesses: James R. Widmann, John
201T. Barfield, and Dennis F. Davis. Dickerson's exhibits 1-17 were received into
213evidence. The Department called as witnesses: Donnie Alford, Brant L.
223Hargrove, Aldric Borders Keith O. Pitchford, and Thomas Kindred. The
233Department's exhibits 1 and 2 were received into evidence.
242The transcript of hearing was filed January 18, 1989, and the parties were
255granted leave until January 30, 1989, to file proposed findings of fact. The
268parties' proposals have been addressed in the appendix to this recommended
279order.
280FINDINGS OF FACT
283Background
2841. In September 1988, Respondent, Department of Transportation
292(Department), issued an invitation to bid (ITB), State Project NO. 89 060-3523,
304for road work on SR-76 (Kanner Highway) in Martin County, Florida. By October
31726, 1988, the bid opening date, four bids had been filed with the Department.
3312. On December 5, 1988, the bid results were posted by the Department.
344The bid results revealed that Petitioner, Dickerson Florida, Inc. (Dickerson),
354was the lowest bidder at $1,057,464.71 and that Ranger Construction Industries,
367Inc. (Ranger) at $1,145,177.61 was the second lowest bidder. The bid results
381further revealed that the bid of Dickerson had been rejected as non-responsive
393because it purportedly did not achieve the disadvantaged business enterprise
403(DBE) goal of 12 percent established by the ITB, and that the Department
416proposed to award the contract to Ranger.
4233. Dickerson timely filed a written notice of protest and formal written
435protest contesting the Department's decision, and the matter was referred to the
447Division of Administrative Hearings for formal hearing.
454The Bid Documents
4574. Pertinent to this case, the ITB contained the following provisions:
468SPECIAL PROVISIONS
470DISADVANTAGED BUSINESS ENTERPRISES
4732-5.3.2 Submittals for Contracts with Goals:
479For all contracts for which DBE contract
486goals have been established, each contractor
492shall meet or exceed or demonstrate that it
500could not meet, despite its good faith
507efforts, the contract goals set by the
514Department. The DBE participation information
519shall be submitted with the Contractor's bid
526proposal. Award of the Contract shall be
533conditioned upon submission of the DBE
539participation information with the bid proposal
545and upon satisfaction of the contract goals or,
553if the goals are not met, upon demonstrating
561that good faith efforts were made to meet the
570goals.
571The Contractor's bid submission shall
576include the following information (Submitted on
582Forms Nos. 275-020-002-DBE Utilization
586Affirmative Action Certification, 275-020-003-
590DBE Utilization Summary and 275-020-004-DBE
595Utilization Form):
597(1) The names and addresses of certified
604DBE firms that will participate in the
611contract. Only DBEs certified by the
617Department at the time the bid is
624submitted may be counted toward DBE goals.
631(2) A description of the work each named
639DBE firm will perform.
643(3) The dollar amount of participation by
650each named DBE firm.
654(4) If the DBE goal is not met, suffi-
663cient information to demonstrate that the
669contractor made good faith efforts to meet
676the goals. (Emphasis added)
6805. Accompanying the ITB were three DBE utilization forms which, pertinent
691to this case, provided the vehicle for complying with the foregoing special
703provisions, and which the bidder was required to complete and include in its
716bid. Among these was form 275-020-004, the DBE Utilization Form, which
727required, consistent with the special provisions, that the bidder provide the
738name, address, and telephone number of the DBE subcontractor, as well as the
751item number and description of the work the subcontractor was to perform. One
764utilization form, signed by the bidder (prime contractor), was to be submitted
776for each DBE utilized on the project. Significantly, the utilization form to be
789signed by the bidder contained the following provision:
797(Signature and submission with the prime
803contractor's bid signifies acceptance of the
809quote and an obligation to subcontract the work
817to the DBE as indicated).
8226. The other two DBE utilization forms that were to be included in the bid
837were form 275-020-003, the DBE Utilization Summary, and form 275-020-002, the
848DBE Utilization Affirmative Action Certification. The DBE Utilization Summary
857provided the vehicle for the bidder to submit the dollar amount of participation
870by each DBE firm, and to derive a DBE percentage participation for the total
884project. It also requested that the bidder provide the following information:
895Number of DBE Utilization Forms attached _____
902NOTE: Sign and attach all Utilization
908Forms which you are using toward the DBE
916goal.
917By submittal of the DBE Utilization Form and the DBE Utilization Summary, the
930bidder could comply with the special provisions of the ITB regarding DBE
942utilization.
9437. The final DBE utilization form that was to be included in the bid, the
958DBE Utilization Affirmative Action Certification, required the bidder to certify
968the existence of an approved DBE Affirmative Action Program Plan or that it was
982submitting a plan for approval with its bid. The certification form, which was
995to be signed by the bidder, contained the following conspicuous notation:
1006The Florida Department of Transportation
1011requires the Disadvantaged Business Enterprise
1016Utilization Form(s) to accompany the bid
1022documents....
1023FAILURE TO SUBMIT THE DISADVANTAGED BUSINESS
1029ENTERPRISE UTILIZATION FORM(S) REFLECTING FULL
1034COMPLIANCE WITH THE CONTRACT GOAL, OR IF THE
1042DISADVANTAGED BUSINESS ENTERPRISE UTILIZATION
1046FORM(S) DO NOT REFLECT FULL COMPLIANCE WITH THE
1054CONTRACT GOAL, FAILURE TO SUBMIT SUFFICIENT
1060DOCUMENTATION TO DEMONSTRATE GOOD FAITH EFFORTS
1066TO MEET THE GOAL WILL BE JUST CAUSE TO CONSIDER
1076THE BID NONRESPONSIVE AND TO REJECT THE BID.
1084THESE DOCUMENTS MUST BE SUBMITTED WITH THE BID
1092PROPOSAL.
1093Dickerson's Bid
10958. The bid submitted by Dickerson included the DBE Utilization Affirmative
1106Action Plan Certification and a DBE Utilization Summary evidencing a DBE
1117percentage participation for the total project of 13.39 percent. As submitted,
1128the utiliza- tion summary listed Dickerson's DBE subcontractors and the amount
1139of their participation as follows:
1144A. Highway Valets, Inc. -- $ 6,473.35
1152B. Temple's Heavy Hauling -- $44,536.25
1159C. Highway Valets, Inc. -- $ 6,730.00
1167D. Pary, Inc. -- $ 5,264.00
1174E. Siboney Contracting Co. -- $45,938.55
1181F. Advance Barricades and
1185Signing, Inc. -- $32,599.80
11909. Accompanying Dickerson's bid were DBE Utilization Forms for Highway
1200Valets, Inc. and Temple's Heavy Hauling, signed by the DBE subcontractor and
1212Dickerson, which contained the item number and description of the work to be
1225performed by those subcontractors, as well as a DBE Utilization Form for Siboney
1238Contracting Company, signed only by Dickerson, which contained the item number
1249and description of the work to be performed by that subcontractor. No DBE
1262Utilization Form was submitted for Pary, Inc. or Advance Barricades and Signing,
1274Inc., and Dickerson's bid contained no information to demonstrate the item
1285number or work those firms were to perform on the project.
129610. Upon noting the absence of any DBE Utilization Forms for Pary or
1309Advance Barricades, or any other documentation from which the item numbers and
1321work description for these DBE's could be ascertained, the Department reduced
1332the dollar value of Dickerson's DBE participation by the amount allocated to
1344these firms, and recalculated a DBE percentage for Dickerson of 9.8 percent,
1356well below the DBE goal of 12 percent. Thereafter, upon concluding that
1368Dickerson's failure to include the item number and description of the work to be
1382performed by the DBE's was not a minor irregularity that could be waived,
1395discussed infra, and that Dickerson had submitted no documentation with its bid
1407to demonstrate that it could not in good faith achieve the goal, the Department
1421proposed to reject Dickerson's bid as non-responsive for its failure to achieve
1433the DBE goal of 12 percent established by the ITB. 1/
144411. On December 12, 1988, some seven days after the Department posted the
1457bid result, Dickerson submitted to the Department a DBE Utilization Form for
1469Pary and Advance Barricades which contained the item number and description of
1481the work to be performed by those firms. Notably, neither form was signed by
1495Dickerson, as required by the ITB, and the quotation of Advance Barricades was
1508for $53,208, some $20,618.20 more than the participation allotted to that firm
1522in the utilization summary submitted with Dickerson's bid.
1530A Minor Irregularity?
153312. Minor irregularity is defined by Rule 13A-1.002(10), Florida
1542Administrative Code, as:
1545... a variation from the invitation to bid
1553... which does not affect the price of the bid
1563or give the bidder ... an advantage or
1571benefit not enjoyed by other bidders ..., or
1579does not adversely impact the interests of the
1587agency. Variations which are not minor can not
1595be waived.
1597In the instant case, the proof demonstrated that Dickerson's failure to include
1609a description of the work Pary and Advance Barricades were to perform on the
1623project would adversely affect the interests of the agency.
163213. The Department has experienced significant problems in the past in its
1644administration of the DBE program, particularly in the reliability of the DBE
1656participations contained in bid documents. The purpose of the special
1666provisions of the ITB, which parrot Rule 14-78.003(2)(b)3, Florida
1675Administrative Code, relating to the name, amount of participation, and work to
1687be performed by the DBE subcontractors are designed to assist the Department in
1700achieving the goals established by the DBE program by increasing the reliability
1712of the bid documents.
171614. Historically, bids have been submitted to the Department with inflated
1727DBE participations and with the names of DBE's who had never been contacted by
1741the prime contractor to perform any work on the project. Absent a description
1754of the work the DBE subcontractor had agreed to perform, the Department has been
1768frustrated in its efforts to confirm, post bid, that the DBE subcontractor is
1781doing the type and amount of work for which it contracted. Consequently, DBE
1794participation on a project has frequently differed significantly from that
1804stated in the bid documents, and as contemplated by the Department
181515. By requiring compliance with the special provisions of the ITB, and
1827its rule, the Department essentially forces the solidification of a contract
1838between the prime contractor and the DBE subcontractor, and gains reliability in
1850the DBE participation specified in the bid documents, and achieves a binding
1862commitment that can be verified post bid. Under such circumstances, a bid's
1874failure to include a description of the work a DBE subcontractor is to perform
1888on the project is a variation that would adversely impact the interests of the
1902agency and cannot be waived.
1907CONCLUSIONS OF LAW
191016. The Division of Administrative Hearings has jurisdiction over the
1920parties to, and the subject matter of, these proceedings.
192917. Section 120.53(5), Florida Statutes, and Rule 14- 25.024(1), Florida
1939Administrative Code, establish specific procedures to protest a bid solicitation
1949requirement. The proper procedure for contesting the special provisions of the
1960ITB that required the bidder to include a description of the work each named DBE
1975firm was to perform on the project as part of its bid, as well as the provision
1992that failure to include such a description would result in disqualification of
2004the bid, was by filing a bid solicitation protest prior to the date the bids
2019were to be received. Rule 14-25.024(1), Florida Administrative Code. Since
2029Dickerson did not file a timely protest of the ITB, it has waived its right to a
2046Chapter 120 proceeding to contest the propriety of these provisions. Section
2057120.53(5), Florida Statutes, and Capeletti Bros., Inc. v. Department of
2067Transportation, 499 So.2d 855 (Fla. 1st DCA 1986). 2/
207618. Notwithstanding its waiver of any right to protest the propriety of
2088these provisions, Dickerson contended at hearing that its bid was responsive to
2100the ITB even though it did not include a description of the work to be performed
2116by Pary and Advance Barricades. The gravamen of Dickerson's contention is that
2128by naming Pary and Advance Barricades on its Utilization Summary, along with the
2141dollar amount of their participation, it had submitted a "quotation" to the
2153Department that conformed with existing law, and that any rule or ITB
2165requirement that its bid include a description of the work these subcontractors
2177were to perform was unenforceable.
218219. Pertinent to this case are the provisions of Section 337.125, Florida
2194Statutes, and Rule 14-78.003(2)(b)3, Florida Administrative Code. Section
2202337.125 provides:
2204(1) Any form documenting the utilization
2210of certified socially and economically
2215disadvantaged business enterprises by a prime
2221contractor shall be signed by the socially and
2229economically disadvantaged business enterprise
2233and the prime contractor. In lieu thereof, the
2241prime contractor shall submit the written or
2248oral quotation of the socially and economically
2255disadvantaged business enterprise, and the
2260department shall confirm the contents of the
2267submission by contacting the socially and
2273economically disadvantaged enterprise.
2276(4) The department shall promulgate rules
2282for implementing the directives contained in
2288this section.
2290Implementing section 337.125 is Rule 14-78.003(2)(b)3, Florida Administrative
2298Code. That rule provides:
2302For all contracts for which DBE contract
2309goals have been established, each bidder shall
2316meet or exceed or demonstrate that it could not
2325meet, despite its good faith efforts, the
2332contract goals set by the Department. The DBE
2340participation information shall be submitted
2345with the contractor's bid proposal. Award of
2352the contract shall be conditioned upon
2358submission of the DBE participation information
2364with the bid proposal and upon satisfaction of
2372the contract goals or, if the goals are not
2381met, upon demonstrating that good faith efforts
2388were made to meet the goals. Failure to
2396satisfy these requirements shall result in a
2403contractor's bid being deemed nonresponsive and
2409the bid being rejected.
2413a. The contractor's bid submission shall
2419include the following information:
2423i. The current names, telephone numbers,
2429and addresses of certified DBE firms that will
2437participate in the contract;
2441ii. A description of the work each named
2449DBE firm will perform;
2453iii. The dollar amount or participation by
2460each named DBE firm;
2464iv. Any documentation required by the
2470contract or applicable rules as evidence of DBE
2478participation.
2479v. If the DBE goal is not met, suffi-
2488cient information to demonstrate that the
2494contractor made good faith efforts to meet the
2502goals.
2503b. In order to count the DBE subcontract
2511amount toward the DBE goal, the documents
2518confirming utilization shall be signed by both
2525a representative of the DBE firm and the prime
2534contractor. In lieu thereof, the prime
2540contractor shall submit the quotation and the
2547Department will attempt to confirm the contents
2554of the submission by contacting the DBE firm by
2563telephone or by certified letter, return
2569receipt requested, within two workdays after
2575the date of the letting. (Emphasis added)
258220. Dickerson contends that its inclusion of the names of Pary and Advance
2595Barricades, along with the dollar amount of their participation, on its
2606Utilization Summary constituted the submission of an "oral quotation" of a DBE
2618which, pursuant to section 337.125, Florida Statutes, the Department was
2628obligated to confirm. So reasoning, Dickerson contends it was not obligated to
2640submit a description of the work the subcontractors were to perform, and that
2653any ITB requirement or rule to the contrary is unenforceable. Dickerson's
2664contention is unpersuasive.
266721. Contrary to Dickerson's contention, there are no inconsistencies
2676between the statute and the rule. The term "quotation" is not defined by
2689section 337.125, and is therefore to be accorded its commonly accepted meaning.
2701See e.g. Gardner v. Johnson, 451 So.2d 477 (Fla. 1984). In commerce, a
"2714quotation" or "quote" is to state the price of something. Webster's New
2726Twentieth Century Dictionary, Unabridged, Second Edition, 1979. By requiring
2735the bidder to submit with its bid a description of the work each DBE
2749subcontractor is to perform and the dollar amount of participation by each DBE
2762subcontractor, the rule is therefore consistent with the statute it implements
2773because it requires the submittal of a "quotation."
278122. Dickerson's failure to include a description of the work Pary and
2793Advanced Barricades were to perform on the project, an essential element of any
2806quotation, compels the conclusion that it failed to submit a "quotation". Under
2819the circumstances, the Department had no "quotation" to confirm, and it properly
2831excluded Pary and Advanced Barricades when computing Dickerson's DBE
2840participation. Rule 14-78.003(2)(b)3, Florida Administrative Code.
284623. In reaching this conclusion I have not overlooked the fact that the
2859Department could have called the subcontractors and, perhaps, ascertained from
2869them what work they had agreed to perform on the project for the stated price.
2884It is not, however, the Department's obligation to compile quotations, but to
2896confirm them. It is the bidder's obligation to submit a binding quotation that
2909is capable of verification.
291324. Dickerson further contends that its failure to include a description
2924of the work the subcontractors were to perform was a minor irregularity that
2937should be waived by the Department. Again, Dickerson's contentions are not
2948persuasive.
294925. Rule 13A-1.002(10), Florida Administrative Code, addresses the issue
2958of minor irregularities in a bid as follows:
2966The agency shall reserve the right to
2973waive any minor irregularities in an otherwise
2980valid bid ... A minor irregularity is a
2988variation from the invitation to bid ... which
2996does not affect the price of the bid ..., or
3006give the bidder ... an advantage or benefit not
3015enjoyed by other bidders ..., or does not
3023adversely impact the interests of the agency.
3030Variations which are not minor cannot be
3037waived.
303826. Since Dickerson's failure to include a description of the work to be
3051performed by the DBE subcontractors was a variation from the ITB that could, for
3065the reasons set forth in the findings of fact, adversely impact the interests of
3079the agency, such failure is not a minor irregularity and is not subject to
3093waiver.
309427. Dickerson's attempt to "supplement" its bid after the bid opening did
3106not and cannot cure its failure to comply with the ITB. Rule 13A-1.001(13),
3119Florida Administrative Code, provides:
3123Valid Bid/Proposal - a responsive offer in
3130full compliance with the bid/proposal
3135specifications and conditions by a
3140responsible person or firm. The
3145responsiveness of the bid ... will be
3152determined as of the time the
3158bids/proposals are made public. (Emphasis
3163added).
3164See: Palm Beach Group v. Department of Insurance and Treasurer, 10 FALR 5627
3177(1988)
3178RECOMMENDATION
3179Based on the foregoing findings of fact and conclusions of law, it is
3192RECOMMENDED that a final order be entered dismissing the formal protest
3203filed by Dickerson Florida, Inc.
3208DONE and ENTERED in Tallahassee, Leon County, Florida, this 17th day of
3220February, 1989.
3222___________________________________
3223WILLIAM J. KENDRICK
3226Hearing Officer
3228Division of Administrative Hearings
3232The DeSoto Building
32351230 Apalachee Parkway
3238Tallahassee, Florida 32399-1550
3241(904) 488-9675
3243Filed with the Clerk of the
3249Division of Administrative Hearings
3253this 17th day of February, 1989.
3259ENDNOTES
32601/ The Department has in place a multi-stage review process to evaluate the
3273responsiveness of bids. After the bids are opened, the DBE certification
3284coordinator determines whether the DBE goal has been obtained. To ascertain
3295whether the DBE goal has been met, the coordinator reviews the Utilization
3307Summary to ascertain the dollar participation of each DBE subcontractor and the
3319relationship the total DBE participation bears to the bid price. The coordinator
3331then reviews the DBE Utilization Form or equivalent documentation to assure that
3343the prime contractor and the DBE subcontractor have agreed to the work to be
3357performed for the price indicated on the Utilization Summary. If any of the DBE
3371utilization forms have not been signed by the DBE, the coordinator will contact
3384the DBE to confirm that it has agreed to perform the work indicated at the
3399stated price. Where, as here, the bid contains no utilization form or
3411equivalent documentation to delineate the work the subcontractor is to perform,
3422the coordinator does not contact the DBE because there is no quotation or
3435agreement accompanying the bid which can be confirmed, recalculates the DBE
3446participation without such DBE firms and ascertains whether the bid then meets
3458the DBE goal. If it does not meet the DBE goal, as recalculated, the
3472coordinator refers the matter to the Good Faith Efforts Review Committee to
3484ascertain whether the bid contains documentation to excuse the bidder's failure
3495to meet the DBE goal. Here that committee found no such documentation,
3507recommended that the bid be declared non- responsive, and referred the matter to
3520the Technical Review Committee to ascertain whether Dickerson's failure to
3530include the DBE utilization forms or equivalent documentation for Pary and
3541Advance Barricades was a minor irregularity that could be waived. The Technical
3553Review Committee concluded, for reasons discussed in further findings of fact,
3564that such failure was not a minor irregularity and could not be waived. On
3578review of the work performed by the Good Faith Efforts Committee, the Contract
3591Award Committee agreed with their conclusions and declared the bid of Dickerson
3603to be non-responsive for failure to meet the DBE goal.
36132/ Although Dickerson's formal protest did not raise the issue, it did raise at
3627hearing the constitutionality of those portions of Chapter 337, Florida
3637Statutes, relating to DBE participation goals or quotas. Since jurisdiction to
3648determine the validity of a state statute under either the United States
3660Constitution or the Constitution of the State of Florida is not vested in the
3674Division of Administrative Hearings, that issue will not be resolved by this
3686order, nor will the timeliness of Dickerson's contention be addressed.
3696APPENDIX
3697Dickerson's proposed findings of fact are addressed as follows:
37061-3. Addressed in paragraph 1.
37114-5. Addressed in paragraph 2.
37166-9. Addressed in paragraph 10 and footnote 1.
372410. Addressed in paragraph 2.
372911. To the extent necessary, addressed in paragraph 3.
373812 Addressed in paragraph 8.
374313. Addressed in paragraphs 8 and 9.
375014. Addressed in paragraph 10 and footnote 1.
375815. Addressed in paragraph 11.
376316. To the extent necessary, addressed in paragraphs
37711 and 10.
377417. Accepted, but not necessary to result reached.
378218. Not relevant.
378519. Not relevant.
378820. Addressed in footnote 1.
379321. Not relevant. Dickerson was accorded a Section
3801120.57(1), Florida Statutes, hearing.
380522. To the extent pertinent, addressed in paragraphs
38134-7, and 12-15.
381623. To the extent pertinent, addressed in paragraph
38247. Otherwise rejected as not relevant.
383024. Addressed in paragraph 3.
3835The Department's proposed findings of fact are addressed as follows:
38451-3. Addressed in paragraphs 1 and 2.
38524-7. Addressed in paragraph 10 and footnote 1.
38608. Addressed in paragraph 9.
38659. Addressed in paragraph 5.
387010. To the extent pertinent, addressed in paragraphs
38784-9.
387911. Addressed in paragraphs 12-15.
388412-13. Addressed in paragraphs 4-7.
388914-15. Addressed in paragraph 10.
389416. Addressed in paragraphs 10, 12-15 and footnote 1.
390317. Not necessary to result reached or not relevant.
391218. Not relevant.
3915COPIES FURNISHED:
3917ROBERT M. ERVIN, ESQUIRE
3921WILFRED C. VARN, ESQUIRE
3925ERVIN, VARN, JACOBS, ODOM
3929& ERVIN
3931305 GADSDEN STREET
3934TALLAHASSEE, FLORIDA 32301
3937J. MARLEEN AHEARN, ESQUIRE
3941DEPARTMENT OF TRANSPORTATION
3944HAYDON BURNS BUILDING, M.S. 58
3949605 SUWANNEE STREET
3952TALLAHASSEE, FLORIDA 32399-0458
3955KAYE N. HENDERSON, SECRETARY
3959DEPARTMENT OF TRANSPORTATION
3962HAYDON BURNS BUILDING, M.S. 58
3967605 SUWANNEE STREET
3970TALLAHASSEE, FLORIDA 32399-0458
3973THOMAS H. BATEMAN, III, ESQUIRE
3978GENERAL COUNSEL
3980DEPARTMENT OF TRANSPORTATION
3983HAYDON BURNS BUILDING, M.S. 58
3988605 SUWANNEE STREET
3991TALLAHASSEE, FLORIDA 32399-0458