92-005465BID Harrell Roofing, Inc. vs. Florida State University
 Status: Closed
Recommended Order on Friday, October 30, 1992.


View Dockets  
Summary: BID delivered 4 minutes late and lack of acknowledgement of change addendum held to be minor irregularities which agency could waive.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8HARRELL ROOFING, INC, )

12)

13Petitioner, )

15)

16v. )

18)

19FLORIDA STATE UNIVERSITY, )

23) CASE NO. 92-5465BID

27Respondent. )

29)

30ALLSTATE CONSTRUCTION, INC., )

34)

35and )

37)

38SOUTHEAST ROOFING, )

41)

42Intervenors. )

44______________________________________)

45RECOMMENDED ORDER

47The final hearing in the above-styled matter was heard pursuant to notice

59by Stephen F. Dean, assigned Hearing Officer of the Division of Administrative

71Hearings, on September 21, 1992, in Tallahassee, Florida.

79APPEARANCES

80For Petitioner: Wendell Parker

84Mike Harrell

86Harrell Roofing, Inc.

89P.O. Box 20421

92Tallahassee, Florida 32316

95For Respondent: Sonja Mathews

99Florida State University

102540 W. Jefferson Street

106Tallahassee, Florida 32306-4038

109For Intervenor: Davisson F. Dunlap, Jr.

1153375-A Capital Circle, N.E.

119Tallahassee, Florida 32308

122Counsel for Allstate Construction

126Mr. Jeff Miller

129Route 16, Box 1307

133Tallahassee, Florida 32310

136Representing Southeast Roofing

139STATEMENT OF ISSUES

1421. Whether Allstate Construction's (Allstate) bid was delivered in time.

1522. Whether Florida State University (FSU) had the authority to waive the

164lateness of Allstate's bid if it was late.

1723. Whether the failure by Allstate to acknowledge receipt of Addendum No.

1842 was a bidding irregularity.

1894. Whether Allstate's failure to acknowledge receipt of Addendum No. 2

200could be waived by FSU.

205PRELIMINARY STATEMENT

207Florida State University requested bids for repairs to the roof and walls

219of Thagard Student Health Center on July 2, 1992. Thereafter, two addenda were

232issued. The first addendum was issued on July 27, 1992, and the second on July

24728, 1992. Bids were received from several contractors to include the Petitioner

259and Intervenor in this case. The bids were opened and posted on August 6, 1992,

274and the bid tabulation sheet posted on the same day.

284Prior to the end of the posting period, the Petitioner notified FSU of

297Petitioner's intent to protest the bid. Subsequently, the Petitioner filed a

308timely formal protest petition. Attempts between the parties to resolve the

319dispute failed, and the matter was forwarded to the Division of Administrative

331Hearings for formal hearing pursuant to Section 120.53(5)(d), Florida Statutes.

341Allstate Construction, Inc. and Southeast Roofing, Inc. (Southeast) filed

350petitions to intervene which were granted; however, at hearing Southeast did not

362actively participate.

364At the hearing, the parties presented witnesses regarding the events of

375August 6, 1992; and concerning the nature of the changes called for in Addendum

389No. 2. The parties submitted documentary exhibits. Copies of several of the

401key exhibits are attached to this order for ease of reference. Subsequently,

413FSU and Allstate filed proposed findings which were read and considered.

424Appendix A states which of the proposed findings were adopted, and which were

437rejected and why. Harrell submitted a letter which was also read and

449considered.

450FINDINGS OF FACT

4531. Florida State University requested bids for repairs to the roof and

465walls of Thagard Student Health Center on July 2, 1992. Thereafter, two addenda

478were issued. The first addendum was issued on July 27, 1992, and the second on

493July 28, 1992.

4962. Item #1 of Specifications in Addendum No. 1, which is attached, changed

509the date the bids were to be presented to August 6, 1992 at 2:00 p.m. in Room

526124-D of Mendenhall Maintenance Building at FSU.

5333. Item #1 to Specifications in Addendum No. 2, which is attached, changed

546the specifications of ringlets and counterflashings published in Item #4 to

557Specifications in Addendum No. 1; and Item #2 in Addendum No. 2 changed the

571specifications of the materials in the cants published in the original

582specifications.

5834. On August 6, 1992, representatives of Harrell, Southeast, and FSU were

595present in Room 124-D, Mendenhall Maintenance Building prior to 2:00 p.m.

606Harrell and Southeast had already presented their bids to Sallie Dixon, FSU's

618representative. One of the persons present had called upon Ms. Dixon to call

631time and open the bids, but she had not done so when Dot Mathews and Joe O'Neil

648entered the room.

6515. Mr. O'Neil announced to those present that Ms. Mathews was late because

664he had misdirected her to another part of the building when Ms. Mathews's had

678entered the office he was in, Room 124, and had asked directions. Ms. Mathews

692immediately handed Allstate's bid to Ms. Dixon, and Ms. Dixon received it.

7046. Immediately, Ms. Dixon opened, tabulated, and posted the bids.

714Allstate had the lowest responsible bid. Allstate's bid did not acknowledge

725receipt of Addendum No. 2.

7307. FSU's rules on bidding provide that the official time will be that of

744the clock in the reception area of the Purchasing Department; however, the

756opening was held in Mendenhall Maintenance Building because of repairs to the

768Purchasing Department, and the university's officials were uncertain whether the

778reception area and clock existed at the time of the opening.

7898. It was the clear impression of all present, except Ms. Mathews, that

802the bid presented by Ms. Mathews was after 2:00 p.m. The estimates of the time

817varied, but none placed the time beyond 2:04 p.m.

8269. FSU generally sent an acknowledgment form with an addendum which

837required the bidders to acknowledge receipt of the addendum; however, in this

849instance, the addendum was sent by the supervising engineer, and an

860acknowledgment form was not sent with the addendum. The specifications did not

872require acknowledgment of addenda.

87610. The essence of the substantial amount of testimony received on the

888impact of the changes was (1) that the change in thickness of materials had a

903negligible impact, and (2) the real change in costs was the result of the

917requirement that the paint finish be by the manufacturer.

92611. The requirement that the materials be painted by the manufacturer was

938part of Addendum No.1. Further, the bidders are deemed manufacturers, and the

950finish that they put on the manufactured items is "by the manufacturer".

96312. Although testimony was received that Petitioner would have

972manufactured the items and then had them coated thereby increasing their total

984costs, an alternative method of manufacture was described by Allstate's

994representative in which the painted raw materials are retouched after being cut

1006and welded into the finished structures. Petitioner's choice of the first

1017method was explained by its representative to be its effort to comply with the

1031bid requirement that the winning contractor guarantee the finish for twenty

1042years. Intervenor's choice was to use the second method.

105113. To the extent that one method may have been more expensive that the

1065other, there was no prohibition of the Petitioner to adopt the less expensive

1078method; and, therefore, there was no economic advantage to Allstate.

108814. In the absence of an economic advantage to Allstate, Allstate's

1099failure to acknowledge Addendum No. 2 was a minor irregularity. FSU waived the

1112lateness of Allstate's bid and Allstate's failure to acknowledge Addendum No. 2,

1124and awarded the bid to Allstate.

1130CONCLUSIONS OF LAW

113315. The Division of Administrative Hearings has jurisdiction over the

1143subject matter and the parties to this action in accordance with Section 120.53,

1156Florida Statutes.

115816. Rule 6C2-2.015(7)(d), Florida Administrative Code, provides in

1166pertinent part:

1168(d) Receipt of Bids. Bids shall be delivered

1176to the Purchasing Department, or as otherwise

1183directed, at or prior to the date and time

1192specified in the Invitation to Bid for the bid

1201opening. Bids which are not delivered to this

1209location and only this location, no matter

1216what reason, shall not be considered. It is

1224the bidder's responsibility to assure that

1230their bid is delivered at the proper time and

1239place for the bid opening[.] . . . . . . The

1251clock in the Reception area of the Purchasing

1259Department is designated as the official time

1266piece for purposes of determining whether a

1273bid or proposal was received by the appointed

1281hour.

128217. The facts are clear that the bid was delivered late as measured by the

1297time pieces in the room where the bids were opened. The university's official

1310did not synchronize her watch with the "official time piece" prior to the

1323opening. The facts reveal that the university's representatives did not know

1334whether the "official time piece" existed on the day of the opening. However,

1347the persons present testified that the bid was no more than four (4) minutes

1361late.

136218. The only Florida case addressing late bids is Hewitt Contracting

1373Company, Inc., v. Melbourne Regional Airport Authority, 528 So.2d 122 (Fla. 5th

1385DCA, 1988), which involves remarkably similar facts. In Hewitt, supra, the

1396Authority had advertised for bids to be received at 11:00 a.m. local time on a

1411given date. Hewitt submitted a bid prior to 11:00 a.m., and Hubbard submitted a

1425bid between 11:00 and 11:10 a.m. After 11:10 a.m., the Authority's director

1437entered the room, announced the bidding was closed, opened and tabulated the

1449bids. Hubbard had the low bid and was awarded the contract. Hewitt objected to

1463Hubbard's bid being considered because it was filed late. The court held that

1476the Authority had discretion to waive the irregularity of Hubbard's filing under

1488the facts in the case.

149319. The facts reveal that Allstate failed to acknowledge receipt of

1504Addendum No. 2.; that an acknowledgment form was not provided in this instance;

1517and that the bid documents did not call for disqualification if the addenda were

1531not acknowledged as some invitation to bid provide. Credible evidence was

1542received that change in the thickness of the materials was inconsequential to

1554the costs of the project. Credible evidence was received that the requirement

1566for manufacturer's paint on the items was potentially an issue; however, two

1578things impact consideration of this issue. First, this requirement repeats a

1589requirement in Addendum No. 1, and really was not a change. Second, there were

1603two methods to paint the items, and the bidders were free to use either method.

161820. A minor irregularity is defined as:

1625. . . [A] variation from the Invitation to Bid

1635terms and condition, which does not affect

1642price offered, or give the bidder an advantage

1650or benefit not enjoyed by the other bidders or

1659does not adversely impact the interest of the

1667University[.] . . .

167121. Because all the bidders were free to use either method, the failure to

1685acknowledge Addendum No. 2 was a minor irregularity because there was no

1697economic advantage to Allstate which was not enjoyed by the other bidders, and

1710no adverse impact to the University.

171622. FSU could elect to waive minor irregularities. Being four minutes

1727late when the bidding had not been closed and none of the other bids opened is a

1744minor irregularity, as was failing to acknowledge Addendum No. 2. FSU waived

1756these irregularities. An agency has great discretion in this regard, and one

1768attacking the decision must show that the decision was arbitrary and capricious.

1780See Liberty County v. Baxter's Asphalt & Concrete, Inc., 421 So.2d 50 (Fla.

17931982) and Florida Department of Transportation v. J.W.C. Co., 396 So.2d 778

1805(Fla. 1st DCA 1981). Although it is an article of faith among contractors that

1819being late is fatal, this is no longer the law in all cases in Florida.

183423. The Petitioner had the burden to show that FSU's waiver of these

1847irregularities was arbitrary and capricious. Petitioner failed to meet this

1857difficult burden.

1859RECOMMENDATION

1860Based upon the consideration of the facts found and the conclusions of law

1873reached, it is,

1876RECOMMENDED:

1877That the Petitioner's Petition be dismissed, and the bid be awarded to

1889Allstate Construction, Inc.

1892DONE and ENTERED this 30th day of October, 1992, in Tallahassee, Florida.

1904___________________________________

1905STEPHEN F. DEAN, Hearing Officer

1910Division of Administrative Hearings

1914The DeSoto Building

19171230 Apalachee Parkway

1920Tallahassee, Florida 32399-1550

1923(904) 488-9675

1925Filed with the Clerk of the

1931Division of Administrative Hearings

1935this 30th day of October, 1992.

1941APPENDIX CASE NO. 92-5465BID

1945Florida State University and Allstate Construction, Inc. submitted proposed

1954findings which were read and considered. The following states which findings

1965were adopted and which were rejected and why:

1973Florida State University's Proposed Findings:

1978Para 1-4 Adopted.

1981Para 5-7 Not necessary/irrelevant.

1985Para 8 Adopted.

1988Para 9-11 Not necessary/irrelevant.

1992Para 12-24 Adopted.

1995Para 25 Not necessary/irrelevant.

1999Allstate Construction's Proposed Findings:

2003Para 1,2 Adopted.

2007Para 3 Not necessary/irrelevant.

2011Para 4-8 Adopted.

2014Para 9 Not necessary/irrelevant.

2018Para 10-15 Adopted.

2021COPIES FURNISHED:

2023Wendell Parker

2025Mike Harrell

2027Harrell Roofing, Inc.

2030P.O. Box 20421

2033Tallahassee, FL 32316

2036Sonja Mathews

2038Florida State University

2041540 W. Jefferson Street

2045Tallahassee, FL 32306-4038

2048Davisson F. Dunlap, Jr.

20523375-A Capital Circle, N.E.

2056Tallahassee, FL 32308

2059Jeff Miller

2061Route 16, Box 1307

2065Tallahassee, FL 32310

2068Dale W. Lick, President

2072Florida State University

2075211 Westcott Building

2078Tallahassee, FL 32306-1037

2081Gerold B. Jaski, General Counsel

2086Florida State University

2089540 West Jefferson Street

2093Tallahassee, FL 32306

2096NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

2102All parties have the right to submit written exceptions to this Recommended

2114Order. All agencies allow each party at least 10 days in which to submit

2128written exceptions. Some agencies allow a larger period within which to submit

2140written exceptions. You should contact the agency that will issue the final

2152order in this case concerning agency rules on the deadline for filing exceptions

2165to this Recommended Order. Any exceptions to this Recommended Order should be

2177filed with the agency that will issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
Date: 12/02/1992
Proceedings: Amended Final Order filed.
Date: 11/25/1992
Proceedings: Final Order filed.
PDF:
Date: 11/23/1992
Proceedings: Agency Final Order
PDF:
Date: 11/23/1992
Proceedings: Recommended Order
PDF:
Date: 10/30/1992
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 9/21/92
Date: 10/02/1992
Proceedings: (Allstate Construction`s Unsigned Proposed) Recommended Order filed.
Date: 10/02/1992
Proceedings: (Respondent) Proposed Findings of Fact and Conclusions of Law w/(TAGGED) Appendix filed.
Date: 10/01/1992
Proceedings: Letter to SFD from Harrell Roofing, Inc. (re: late bid proposal) filed.
Date: 09/18/1992
Proceedings: Allstate Construction's Supplemental Witness List filed.
Date: 09/17/1992
Proceedings: (Petitioner & Respondent) Prehearing Stipulation filed.
Date: 09/15/1992
Proceedings: (Respondent) Motion to View Premises filed.
Date: 09/15/1992
Proceedings: Notice of Depositions filed. (From Sonja P. Mathews)
Date: 09/15/1992
Proceedings: Letter to DOAH from Dorothy "Dot" Mathews (re: Participating in proceedings); Letter to Whom It May Concern from Jeffrey C. Miller (re: Participating in proceedings) filed.
Date: 09/11/1992
Proceedings: Notice of Appearance; Allstate Construction's Motion to Intervene filed.
Date: 09/10/1992
Proceedings: Prehearing Order sent out.
Date: 09/10/1992
Proceedings: Notice of Hearing And Order sent out. (hearing set for 9-21-92; 10:00am; Tallahassee)
Date: 09/09/1992
Proceedings: Letter to Mr. Walter Parramore (FSU) from Wendell R. Parker (Harrell Roofing, Inc.) stating Notice of Protest filed.
Date: 09/08/1992
Proceedings: Agency referral letter; Request for Administrative Hearing, letter form; Agency Action letter filed.

Case Information

Judge:
STEPHEN F. DEAN
Date Filed:
09/09/1992
Date Assignment:
09/09/1992
Last Docket Entry:
12/02/1992
Location:
Tallahassee, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Related DOAH Cases(s) (1):

Related Florida Statute(s) (1):

Related Florida Rule(s) (1):