94-002353BID North Florida Construction vs. Department Of Transportation And Pro-Steel Buildings
 Status: Closed
Recommended Order on Monday, June 13, 1994.


View Dockets  
Summary: Petitioner proved that DOT was arbitrary in not finding low bidder non- responsive when Minority Business Enterprise was not qualified for type work as of award date.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8NORTH FLORIDA CONSTRUCTION, )

12)

13Petitioner, )

15)

16vs. ) CASE NO. 94-2353BID

21)

22DEPARTMENT OF TRANSPORTATION, )

26)

27Respondent, )

29and )

31)

32PRO-STEEL BUILDERS, INC., )

36)

37Intervenor. )

39___________________________________)

40RECOMMENDED ORDER

42Pursuant to written notice a formal hearing was held in this case before

55Larry J. Sartin, a duly designated Hearing Officer of the Division of

67Administrative Hearings, on May 12, 1994, in Tallahassee, Florida.

76APPEARANCES

77For Petitioner: Tommy Strickland, pro se

83North Florida Construction, Inc.

87Post Office Box 129

91Clarksville, Florida 32430

94For Respondent: Thomas H. Duffy

99Assistant General Counsel

102Department of Transportation

105Haydon Burns Building

108605 Suwannee Street, Mail Station 58

114Tallahassee, Florida 32399-0458

117For Intervenor: Stephen J. Kubik, Esquire

123155 Office Plaza Drive

127Tallahassee, Florida 32301

130STATEMENT OF THE ISSUE

134Whether the Respondent acted fraudulently, arbitrarily, illegally or

142dishonestly in proposing to award a contract for State Project No. 99003-3501 to

155the Intervenor.

157PRELIMINARY STATEMENT

159After review of bids submitted to the Respondent in response to an

171Invitation to Bid issued by the Respondent, the Respondent proposed to award a

184contract for the project to the Intervenor. By letter dated April 5, 1994, the

198Petitioner challenged the Respondent's proposed award and requested a formal

208administrative hearing.

210By letter dated April 28, 1994, the Respondent requested assignment of a

222Hearing Officer of the Division of Administrative Hearings to this matter. The

234request was designated case number 94-2353BID and was assigned to the

245undersigned.

246The final hearing was scheduled for May 12, 1994, by Notice of Hearing

259entered May 3, 1994.

263On May 3, 1994, a Motion to Intervene was filed by Pro-Steel Buildings,

276Inc. The motion was granted without objection at the commencement of the final

289hearing.

290At the final hearing the Petitioner presented the testimony of Eddie

301Gallon, Sr., and Thomas Strickland. No exhibits were offered by the Petitioner.

313The Respondent presented the testimony of Mike Melvin. Three exhibits were

324offered by the Respondent and were accepted into evidence.

333The Intervenor presented the testimony of Jacqueline Watts, Thomas Trapane

343and Stephen Warren. The Intervenor offered four exhibits which were accepted

354into evidence.

356One "joint exhibit" was offered and accepted into evidence.

365A transcript of the final hearing was filed May 18, 1994. The parties

378agreed to file proposed recommended orders on or before May 31, 1994. All of

392the parties filed proposed recommended orders.

398A ruling on each proposed finding of fact contained in the proposed orders

411filed by the parties has been made either directly or indirectly in this

424Recommended Order, or the proposed finding of fact has been accepted or rejected

437in the Appendix which is attached hereto.

444FINDINGS OF FACT

447A. The Parties.

4501. The Respondent, the Department of Transportation (hereinafter referred

459to as the "Department"), is an agency of the State of Florida. The Department

474sought bidders for a construction project by invitation to bid.

4842. The Petitioner, North Florida Construction, Inc. (hereinafter referred

493to as "North Florida"), submitted a bid on the Department's construction

505project.

5063. The Intervenor, Pro-Steel Buildings, Inc. (hereinafter referred to as

"516Pro-Steel"), also submitted a bid on the Department's construction project.

527B. The Subject Invitation to Bid.

5334. The Department issued an Invitation to Bid for State Project Number

54599003-3501 (hereinafter referred to as the "ITB").

5535. The ITB solicited bids on a construction contract for the relocation of

566the Department's maintenance yard facility in Tallahassee, Florida.

5746. The ITB required that each prime contractor either subcontract at least

58625 percent of the total contract price to a Certified Minority Business

598Enterprises (hereinafter referred to as a "CMBE"), or show a good-faith effort

611to meet the 25 percent goal. Pages 78-81, Joint Exhibit 1.

6227. Included in the Instructions to Bidders, at Section B-14, are

633instructions concerning "Listing of Subcontractors." Page 15, Joint Exhibit 1.

643Section B-14 of the ITB provides:

649In order that the Owner may be assured that

658only qualified and competent subcontractors

663will be employed on the project, each Bidder

671shall submit in triplicate with his proposal

678a list of the subcontractors who will perform

686the work for each Division of the

693Specifications utilizing the "List of

698Subcontractors" form enclosed as Exhibit 5.

704The Bidder shall have determined to his own

712complete satisfaction that a listed

717subcontractor has been successfully engaged

722in this particular type of business for a

730reasonable length of time, has successfully

736completed installations comparable to that

741which is required by this Agreement and is

749qualified both technically and financially

754to perform that pertinent phase of this work

762for which he is listed. . . .

770Any bidder who lists a subcontractor not

777certified and/or registered by the State to

784perform the work of his trade if, such

792certification or registration is required

797for the trade by Florida Laws, will be

805rejected as non-responsive.

808No change shall be made in the list of

817subcontractors, before or after the award

823of a contract, unless agreed to in writing

831by the Owner. [Emphasis added].

8368. Exhibit 5, List of Subcontractors, provides, in part, the following:

847THE UNDERSIGNED, HEREINAFTER CALLED "BIDDER",

852LISTS BELOW THE NAME OF EACH SUBCONTRACTOR

859WHO WILL PERFORM THE PHASES OF THE WORK

867INDICATED. FAILURE OF THE BIDDER TO SUPPLY

874SUFFICIENT INFORMATION TO ALLOW VERIFICATION

879OF THE CORPORATE, AND DISCIPLINE LICENSE

885STATUS OF THE SUBCONTRACTOR MAY DEEM THE BID

893AS BEING NON-RESPONSIVE.

896Page 55, Joint Exhibit 1. Exhibit 5 was required to be completed and submitted

910with all bids pursuant to Section B-14 of the ITB.

9209. From the technical specifications for Heating, Ventilation and Air

930Conditioning work (hereinafter referred to as "HVAC"), for the project at issue,

943it could be inferred that two 30-ton air conditioning units were required.

955C. The Bids Submitted by Pro-Steel and North Florida.

96410. Bids on the ITB were submitted and opened on March 24, 1994.

97711. North Florida submitted a bid in response to the ITB:

988a. On the envelope containing the sealed bid of North Florida, North

1000Florida requested that $14,000.00 be deducted from its proposed contract price.

1012b. North Florida submitted a bid of $2,997,007.00. North Florida was the

1026apparent second low bidder.

1030c. North Florida listed Gallon & Sons as the subcontractor responsible for

1042HVAC work.

1044d. North Florida also listed Gallon & Sons as a CMBE. Gallon & Sons was

1059listed on Exhibit 5, the Minority Business Enterprise Utilization Summary,

1069submitted with North Florida's bid.

1074e. North Florida proposed to install two 30-ton air conditioning units.

108512. Pro-Steel also submitted a bid in response to the ITB.

109613. Pro-Steel submitted a bid of $2,993,000.00. Pro-Steel was the

1108apparent low bidder.

111114. Pro-Steel listed "Watts Mechanical" as the subcontractor responsible

1120for the HVAC work required by the ITB.

112815. Pro-Steel also listed Watts as one of two CMBE subcontractors. "Watts

1140Mechanical" was listed on Exhibit 5, the Minority Business Enterprise

1150Utilization Summary, submitted with Pro-Steel's bid.

115616. Pro-Steel's bid submittal proposed the installation of two 30-ton air

1167conditioning units.

1169D. The Department's Decision.

117317. It is the policy of the Department to waive minor irregularities in

1186bid submittals.

118818. Irregularities with North Florida's bid were correctly determined to

1198be minor by the Department and were waived.

120619. The bid tabulation sheet and the bids indicated that Pro-Steel

1217submitted the lowest, responsive bid. The Department proposed to award the

1228contract under the ITB to Pro-Steel.

123420. Without Watts as a CMBE, Pro-Steel would not meet the 25 percent CMBE

1248participation goal of the ITB.

125321. The Department's project manager for the ITB determined that Watts was

1265a CMBE in evaluating the bid submittals.

1272E. Qualification of CMBE's to Perform Work Proposed.

128022. Gallon & Sons was at all times relevant to this proceeding, registered

1293as a CMBE in hearing and air conditioning.

130123. Eddie Gallon, Sr., was at all times relevant to this proceeding, the

1314registered qualified agent for Gallon & Sons. Mr. Gallon holds a Class A

1327license in heating and air conditioning.

133324. The stock of Watts Mechanical, Inc. (hereinafter referred to as

"1344Watts"), is owned 100 percent by Jacqueline Watts. Ms. Watts is also the

1358President of Watts.

136125. Ms. Watts held and still holds a Class B HVAC license from the

1375Department of Business and Professional Regulation. Ms. Watts was registered

1385with the Department of Business and Professional Regulation as the qualifying

1396agent for Watts.

139926. Watts was registered with the Department of Management Services as a

1411CMBE under the category of heating and air conditioning contractors.

142127. On January 1, 1994, Watts acquired the assets of Energy Systems of

1434Tallahassee (hereinafter referred to as "Energy Systems"). Energy Systems was

1445then owned by Thomas Trapane.

145028. As of January 1, 1994, it was intended that Watts be renamed "Watts

1464Mechanical and Energy Systems, Inc."

146929. Mrapane held and still holds a Class A HVAC license from the

1482Department of Business and Professional Regulation.

148830. Mrapane was registered with the Department of Business and

1498Professional Regulation as the qualifying agent for Energy Systems.

150731. As of January 1, 1994, Mrapane became an employee of Watts.

151932. As of March 24, 1994, when bids were submitted on the ITB:

1532a. Watts had not filed an amendment to its Articles of Incorporation

1544reflecting the change in name to Watts Mechanical and Energy Systems, Inc.

1556(hereinafter referred to as "Watts Mechanical and Energy"). The amendment was

1568not filed until April 26, 1994.

1574b. Mrapane had not registered with the Department of Business and

1585Professional Regulation as the qualifying agent for Watts or Watts Mechanical

1596and Energy. It was not until May 2, 1994, that the Department of Business and

1611Professional Regulation issued a letter indicating that Mrapane was a

1621secondary qualifying agent for Watts Mechanical and Energy.

1629c. Watts had not notified the Department of Management Services of its

1641name change with regard to its CMBE certification.

164933. Based upon the foregoing, at the date of the submittal of bids and the

1664proposed award of contract pursuant to the ITB, Watts did not hold the license

1678required in order for it to complete the work Pro-Steel had represented to the

1692Department Watts would perform.

1696F. Substitution of Subcontractors.

170034. It is the policy of the Department to allow contractors to substitute

1713subcontractors for good cause if proper documentation is submitted. The

1723evidence, however, failed to prove the Department's policy concerning

1732substitution of subcontractors applies in this matter.

173935. The evidence also failed to prove that the Department's policy

1750concerning substitution of contractors allows the Department to accept as

1760meeting part of the CMBE requirement of the ITB a CMBE that was not qualified to

1776perform the required work as of the date of bid award.

1787G. Alternative Proposals.

179036. The ITB allows substitutions for specified systems or products

1800contained in the ITB. Page 28, Joint Exhibit 1.

180937. Substitutions, however, must be requested of the Architect-Engineer

1818and written approval from the Architect-Engineer must be obtained.

1827Substitutions must be submitted within 45 days after award of the contract.

183938. No substitutions were submitted by Pro-Steel or Watts at the time of

1852bid submittal.

185439. As of the date of the final hearing of this case, Watts had decided to

1870suggest that the configuration of the HVAC of the project be changed in a manner

1885that would not require a Class A license for the work to be performed. The

1900evidence failed to prove that the Department was aware of this proposal at the

1914time of its initial decision.

1919CONCLUSIONS OF LAW

1922A. Jurisdiction.

192440. The Division of Administrative Hearings has jurisdiction of the

1934parties to and the subject matter of this proceeding. Section 120.53(5),

1945Florida Statutes (1993).

1948B. Burden of Proof.

195241. The burden of proof, absent a statutory directive to the contrary, is

1965on the party asserting the affirmative of the issue of the proceeding. Antel v.

1979Department of Professional Regulation, 522 So.2d 1056 (Fla. 5th DCA 1988);

1990Department of Transportation v. J.W.C. Co., Inc., 396 So.2d 778 (Fla. 1st DCA

20031981); and Balino v. Department of Health and Rehabilitative Services, 348 So.2d

2015249 (Fla. 1st DCA 1977).

202042. In this proceeding it is North Florida that is asserting the

2032affirmative and, therefore, has the ultimate burden of proof.

2041C. The Department's Proposed Award to Pro-Steel is

2049Arbitrary.

205043. There is not dispute about the fact that Watts did not hold a license

2065to complete the HVAC work called for in the ITB as of the date of the proposed

2082award of contract in this case. Section 489.113, Florida Statutes, requires

2093that, in order for a person (including a corporation) to perform air

2105conditioning contracting, that person must hold required the necessary air

2115conditioning contracting license. To perform the work required in this matter

2126required a Class A license.

213144. At the time of the bid submittal and proposed award in this case, no

2146person holding a Class A license had registered with the Department of Business

2159and Professional Regulation as the qualifying agent for Watts. Watts,

2169therefore, was not qualified to perform the work for which it's name was

2182submitted by Pro-Steel at the time of bid submittal and award.

219345. The issue which must be decided is whether this irregularity in Pro-

2206Steel's submitted bid constituted a minor irregularity that could be waived by

2218the Department.

222046. Not all irregularities in bids or deviations from an invitation to bid

2233are materialopabest Foods, Inc. v. Department of General Services, 493

2243So.2d 50 (Fla. 1st DCA). See also Rule 60A-1.002(13), Florida Administrative

2254Code. A deviation from an invitation to bid "is only material if it gives the

2269bidder a substantial advantage over the other bidders and thereby restricts or

2281stifles competition." Tropabest Foods at 52.

228747. In determining whether the deviation from the ITB in this case is

2300material, North Florida was required to prove that the Department acted

2311fraudulently, arbitrarily, illegally or dishonestly in deciding to award the

2321contract to the apparent low bidder, Pro-Steel. See Overstreet Paving Company

2332v. Department of Transportation, 608 So.2d 851 (Fla. 2d DCA 1992), citing

2344Department of Transportation v. Groves-Watkins Construction, Co., 530 So.2d 912

2354(Fla. 1988).

235648. The Department and Pro-Steel argue, in part, that in light of the fact

2370that Watts Mechanical and Engineer, held all necessary licenses and

2380qualifications as of the date of the final hearing, that Pro-Steel did not gain

2394any competitive advantage. Therefore, it is argued, the Department did not act

2406fraudulently, arbitrarily, illegally or dishonestly. This argument must be

2415rejected.

241649. Pursuant to the clear terms of the ITB, the Department was required at

2430the time of bid submittal to reject Pro-Steel's submittal.

243950. Section B-14 provides that the names of subcontractors are to be

2451included, after determining that each listed subcontractor is "qualified both

2461technically and financially to perform that pertinent phase of this work for

2473which he is listed", so that the Department:

2481. . . may be assured that only qualified and competent subcontractors will

2494be employed on the project, . . . . [Emphasis added].

250551. The ITB contemplates that these assurances are to be given at the time

2519of bid submittal.

252252. Section B-14 goes on to also unequivocally require rejection of a

2534bidder who lists a subcontractor that is not "registered by the State to perform

2548the work specified:

2551Any bidder who lists a subcontractor not certified and/or registered by the

2563State to perform the work of his trade if, such certification or registration is

2577required for the trade by Florida Laws, will be rejected as non-responsive.

2589[Emphasis added].

2591This requirement of the ITB is not discretionary.

259953. Based upon the terms of the ITB itself, the Department eliminated its

2612discretion to treat as a minor irregularity the requirement that subcontractors

2623listed in bids be registered by the State of Florida to perform the work

2637specified and informed all bidders that any bid which failed to list a

2650registered subcontractor "[would] be rejected as non-responsive."

265754. To ignore these provisions of the ITB is arbitrary.

266755. The irregularity in Pro-Steel's bid may have given Pro-Steel a

2678substantial advantage over the other bidders in this case. In effect Pro-Steel

2690was allowed to submit the name of a subcontractor necessary to meet the CMBE

2704requirement of the ITB which was not qualified at the time of bid submittal to

2719perform the work specified but which took steps after bid submittal to become

2732qualified. There may have been other potential bidders who would have submitted

2744bids had they known that subcontractors included on their bid could become

2756qualified after submittal of the bid but were dissuaded by the terms of Section

2770B-14 of the ITB.

277456. The language contained in Exhibit 5, quoted in finding of fact 8,

2787gives the Department discretion to reject a bid as non-responsive with regard to

2800subcontractors, but only if a bidder fails to "supply sufficient information to

2812allow verification of the corporate, and discipline license status of the

2823subcontractor . . . ." The evidence failed to prove that the irregularity with

2837Pro-Steel's bid involved such a failure. The irregularity here goes beyond the

2849failure to supply information. The irregularity here involves the failure of a

2861subcontractor, at the date of bid award, to qualify for the work it was to

2876perform. That irregularity could not have been rectified at the time of bid

2889submittal with additional information from Pro-Steel.

289557. The Department's argument concerning its ability to allow the

2905substitution of subcontractors or substituted proposals must be rejected. The

2915crucial point of time in this matter is the time of bid submittal and the

2930proposed award of contract. The winning bidder must be responsive and the

2942apparent winner at that time based upon the bid submittal at that time. For the

2957Department to take into account what may happen in the future in making that

2971determination would give bidders an unfair advantage. It would not, therefore,

2982be appropriate to take into account these potential corrective steps as a result

2995of this proceeding.

299858. At the time of bid submittal and proposed award of contract, Pro-Steel

3011was not responsive and the Department's proposed decision to award the contract

3023to Pro-Steel is arbitrary.

3027RECOMMENDATION

3028Based upon the foregoing Findings of Fact and Conclusions of Law, it is

3041RECOMMENDED that the Department of Transportation enter a Final Order

3051declaring the bid submitted by Pro-Steel Builders, Inc., to be non-responsive.

3062DONE AND ENTERED this 13th day of June, 1994, in Tallahassee, Florida.

3074___________________________________

3075LARRY J. SARTIN

3078Hearing Officer

3080Division of Administrative Hearings

3084The DeSoto Building

30871230 Apalachee Parkway

3090Tallahassee, Florida 32399-1550

3093(904) 488-9675

3095Filed with the Clerk of the

3101Division of Administrative Hearings

3105this 13th day of June, 1994

3111APPENDIX

3112Case Number 94-2353BID

3115The parties have submitted proposed findings of fact. It has been noted

3127below which proposed findings of fact have been generally accepted and the

3139paragraph number(s) in the Recommended Order where they have been accepted, if

3151any. Those proposed findings of fact which have been rejected and the reason

3164for their rejection have also been noted.

3171North Florida's Proposed Findings of Fact

31771 Accepted in 2 and hereby accepted.

31842 Accepted in 1.

31883 Accepted in 3 and hereby accepted.

31954 Accepted in 4 and 10.

32015 Accepted in 10-11 and 13.

32076 Accepted in 6-8.

32117 Accepted in 14.

32158 Accepted in 15.

32199 Accepted in 7.

322310 Accepted in 25 and 32.

322911 Conclusion of law.

323312 Accepted in 9.

323713 Conclusion of law.

324114 See 27 and 32.

324615 Accepted in 32.

325016 Accepted in 15.

325417 Accepted in 20.

325818 Accepted in 7-8.

326219 See 33.

3265The Department's Proposed Findings of Fact

32711 Accepted in 4.

32752 Accepted in 2-3 and 11-12.

32813 Accepted in 6.

32854 Accepted in 10-11.

32895 Accepted in 11 and 13.

32956 Accepted in 11 and 15.

33017 See 26, 28 and 32. Watts Mechanical, Inc. was a CMBE at the time of

3317bid submittal. Watts Mechanical & Energy Systems, Inc., did not exist at the

3330time of bid submittal.

33348 Accepted in 22.

33389 Accepted in 9.

33429 Accepted in 24.

334610-11 Accepted in 25.

335012 Accepted in 31.

335413 Accepted in 29.

335814 Accepted in 32.

336215 Accepted in 23.

336616 Hereby accepted.

336917 Accepted in 20.

337318 Accepted in 21.

337719 Accepted in 36. But see 37-38.

338420 Not relevant.

338721 See 7.

339022 Accepted in 8.

339423 See 36-38.

339724 Not relevant.

340025 Accepted in 17.

3404Pro-Steel's Proposed Findings of Fact

34091 Accepted in 4.

34132 Accepted in 7-8

34173 Accepted in 8.

34214 Not supported by the weight of the evidence.

34305 Accepted in 34. See 35.

34366 Accepted in 17.

34407 Accepted in 2-3, 10-11 and 18-19.

34478 Accepted in 14.

34519 Accepted in 9 and 36.

345710 See 25-26. But see 32.

346311 Accepted in 27, 29 and 31. The last sentence is not relevant.

347612 Accepted in 32.

348013 Not supported by the weight of the evidence.

348914 See 34-35.

349215 See 36-39

3495COPIES FURNISHED:

3497Ben G. Watts, Secretary

3501Attn: Eleanor F. Turner, M.S. 58

3507Haydon Burns Building

3510605 Suwannee Street

3513Tallahassee, FL 32399-0450

3516Thornton J. Williams

3519General Counsel

3521562 Haydon Burns Building

3525605 Suwannee Street

3528Tallahassee, FL 32399-0450

3531Thomas H. Duffy

3534Assistant General Counsel

3537Department of Transportation

3540Haydon Burns Building, M.S. 58

3545605 Suwannee Street

3548Tallahassee, FL 32399-0458

3551Tommy Strickland

3553North Florida Construction, Inc.

3557Post Office Box 129

3561Clarksville, Florida 32430

3564Stephen J. Kubik, Esquire

3568155 Office Plaza Drive

3572Tallahassee, Florida 32301

3575NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

3581All parties have the right to submit written exceptions to this Recommended

3593Order. All agencies allow each party at least 10 days in which to submit

3607written exceptions. Some agencies allow a larger period within which to submit

3619written exceptions. You should contact the agency that will issue the final

3631order in this case concerning agency rules on the deadline for filing exceptions

3644to this Recommended Order. Any exceptions to this Recommended Order should be

3656filed with the agency that will issue the final order in this case

3669=================================================================

3670AGENCY FINAL ORDER

3673=================================================================

3674STATE OF FLORIDA

3677DEPARTMENT OF TRANSPORTATION

3680NORTH FLORIDA CONSTRUCTION, INC.,

3684Petitioner,

3685vs. DOAH CASE NO.: 94-2353BID

3690DOT CASE NO.: 94-0158 DEPARTMENT OF

3696TRANSPORTATION,

3697Respondent,

3698and

3699PRO-STEEL BUILDINGS, INC.,

3702Intervenor.

3703____________________________________/

3704FINAL ORDER

3706This matter was heard pursuant to written notice before Larry J. Sartin, a

3719duly designated Hearing Officer of the Division of Administrative Hearings on

3730May 12, 1994, in Tallahassee, Florida. Appearances for the parties were as

3742follows:

3743For Petitioner: Tommy Strickland, pro se

3749North Florida Construction, Inc.

3753Post Office Box 129

3757Clarksville, Florida 32430

3760For Respondent: Thomas H. Duffy

3765Assistant General Counsel

3768Department of Transportation

3771605 Suwannee Street, Mail Sation 58

3777Tallahassee, Florida 32399-0458

3780For Intervenor: Stephen J. Kubik

3785155 Office Plaza Drive

3789Tallahassee, Florida 32301

3792STATEMENT OF THE ISSUE

3796Whether the Respondent, DEPARTMENT OF TRANSPORTATION (hereinafter

3803DEPARTMENT), acted fraudulently, arbitrarily, illegally or dishonestly in

3811proposing to award a contract for State Project No. 99003-3501 to Intervenor,

3823PRO-STEEL BUILDINGS, INC., (hereinafter PRO-STEEL) for relocation of the

3832District Three Tallahassee Maintenance Yard.

3837BACKGROUND

3838Pursuant to a protest of the DEPARTMENT'S intent to award the contract for

3851State Project No. 99003-3501 to PRO-STEEL, timely filed by Petitioner, NORTH

3862FLORIDA CONSTRUCTION, INC. (hereinafter NORTH FLORIDA), the matter was referred

3872to the Division of Administrative Hearings for assignment of a hearing officer.

3884A hearing was scheduled and held on May 12, 1994, at which time PRO-STEEL'S

3898Motion to Intervene was granted.

3903NORTH FLORIDA offered no exhibits into evidence and presented the testimony

3914of two witnesses: Eddie Gallon, Sr. and Thomas Strickland. The DEPARTMENT

3925presented the testimony of Mike Melvin and offered and entered into evidence

3937three exhibits. PRO- STEEL offered and entered into evidence four exhibits and

3949presented the testimony of three witnesses: Jacqueline Watts, Thomas Trapane,

3959and Stephen Warren.

3962The Hearing Officer entered his Recommended Order on June 13, 1994, and

3974Exceptions to the Recommended Order were filed by both the DEPARTMENT and PRO-

3987STEEL.

3988Rulings On Exceptions

3991References to the Transcript in this proceeding will be denoted by the page

4004and line numbers as (Tr. p.__, 1.__). The DEPARTMENT'S exceptions are addressed

4016as follows:

4018Exception 1 is rejected as legal argument, not going to factual

4029determinations made by the Hearing Officer and are addressed in the Conclusions

4041of Law below.

4044Exception 2 is rejected as legal argument, not going to factual

4055determinations made by the Hearing Officer and are generally addressed in the

4067Conclusions of Law below.

4071Exception 3 is rejected as legal argument, not going to factual

4082determinations made by the Hearing Officer and are generally addressed in the

4094Conclusions of Law below.

4098Exception 4 is rejected as legal argument, not going to factual

4109determinations made by the Hearing Officer and are generally addressed in the

4121Conclusions of Law below.

4125PRO-STEEL'S exceptions are addressed as follows:

4131Exception 1 is accepted to the extent that the Hearing Officer incorrectly

4143referred to Exhibit 20 to the Department of Transportation Specifications for

4154Tallahassee Maintenance Yard Relocation State Project No. 99003-3501 (PP. 77-82

4164of Joint Exhibit 1) as Exhibit 5 to those specifications.

4174Exception 2 is accepted for the reason noted in the preceding paragraph.

4186Exception 3 is rejected. The Hearing Officer's Finding of Fact No. 20 is

4199supported by competent substantial evidence and PRO-STEEL cites not contrary

4209record evidence. Moreover, this exception is more in the nature of legal

4221argument which is addressed generally in the Conclusions of Law below.

4232Exception 4 is rejected. The Hearing Officer's Finding of Fact No. 33 is

4245supported by competent substantial evidence and PRO-STEEL cites no contrary

4255record evidence in its exception. Moreover, this exception is more in the

4267nature of legal argument which is addressed generally in the Conclusions of Law

4280below.

4281Exception 5 is accepted to the extent that the DEPARTMENT'S evidence did

4293not distinguish this contract from others concerning substitution of

4302subcontractors. (Tr. p. 106, 1. 11-19). However, that testimony dealt with

4313substitution after award of a contract for good cause such as an inability to

4327perform. The DEPARTMENT'S testimony did not address the policy of substitution

4338of subcontractors under circumstances such as those at issue here were the bid

4351documents contain a provision such as that found in paragraph B-14 of the

4364project specifications. (Joint Exhibit #1, p. 15)

4371Exception 6 is rejected. The Hearing Officer's Finding of Fact No. 35 is

4384supported by competent substantial evidence and PRO-STEEL cites no contrary

4394record evidence in its exception. Moreover, this exception is in the nature of

4407legal argument which is addressed generally in the Conclusions of Law below.

4419Exception 7 is rejected for the reason noted in the preceding paragraph.

4431Exception 8 is rejected as legal argument which will be generally addressed

4443in the Conclusions of Law below.

4449Exception 9 is rejected as legal argument which will be generally addressed

4461in the Conclusions of Law below. However, NORTH FLORIDA'S use of Exhibit 5 to

4475the Specifications (Joint Exhibit #1) in support of its position is misplaced.

4487Any discretion left to the DEPARTMENT in Exhibit 5 to Joint Exhibit 1 has only

4502to do with the DEPARTMENT'S ability to verify information supplied by the bidder

4515on its subcontractors. It has nothing to do with the provisions of paragraph B-

452914 relating to the required state licensure of subcontractors.

4538Exception 10 is rejected for the same reasons set out in paragraph 9 above.

4552Exception 11 is rejected for the same reasons set out in paragraph 9 above.

4566Exception 12 is rejected as legal argument which is more generally

4577addressed in the Conclusions of Law below. The analysis as to whether waiver of

4591a particular bid requirement affords a bidder a competitive advantage is not at

4604issue until there is first a determination that the bid requirement is not

4617material. In this instance the DEPARTMENT through the terms of its Invitation

4629to Bid determined the materiality of this requirement up front when it advised

4642bidders that bids would be rejected as non-responsive where the subcontractor

4653listed does not possess the requisite state licensure to do the denoted work.

4666Exception 13 is rejected for the reasons set out in paragraph 9 above.

4679Exception 14 is rejected as legal argument generally addressed in the

4690Conclusions of Law below. Moreover, the DEPARTMENT'S past practices and

4700policies cannot take precedence over the clear language of the Invitation to

4712Bid.

4713Exception 15 is rejected as legal argument more generally addressed in the

4725Conclusions of Law below. The specific language of the Invitation to Bid rather

4738than any ruling the Hearing Officer in this matter has removed discretion from

4751the DEPARTMENT to waive the exact licensure requirement or to allow PRO-STEEL to

4764complete the ministerial act of upgrading its licensure with the Department of

4776Business and Professional Regulation. This ruling in no way abrogates existing

4787case law which allows broad discretion in the public body engaged in competitive

4800acquisition of goods and services where that body does not by the terms of the

4815bid documents specifically limit that broad discretion.

4822FINDINGS OF FACT

4825The Hearing Officer's Findings of Fact are found to be correct and

4837supported by competent substantial evidence except for Finding of Fact 11. d,

4849which was addressed above in PRO-STEEL'S first exception. Finding of Fact 11. d

4862is amended to correctly reflect the appropriate reference to Exhibit 20 to Joint

4875Exhibit 1 rather than Exhibit 5 as pointed out by PRO-STEEL.

4886It is also noted that there was no finding by the Hearing Officer that the

4901employees of the DEPARTMENT acted fraudulently, illegally or dishonestly.

4910Nothing in the record appears to support such a finding and in fact no such

4925contention has been made.

4929CONCLUSIONS OF LAW

49321. The DEPARTMENT has jurisdiction over the subject matter of the parties

4944to this proceeding pursuant to Chapters 287 and 120, Florida Statutes.

49552. Based on the foregoing Findings of Fact and a review of the record in

4970its entirety, the Hearing Officer's Conclusions of Law are found to be correct

4983and are adopted and incorporated herein. Under different facts the result might

4995be different. However, in this case the clear language of the Invitation to Bid

5009requires that the bid submitted by PRO- STEEL be declared nonresponsive pursuant

5021to paragraph B-14 of Joint Exhibit 1.

5028ORDER

5029Based on the foregoing Findings of Fact and Conclusions of Law, it is

5042therefore

5043ORDERED that the bid protest submitted by PRO-STEEL is hereby declared not

5055responsive.

5056DONE AND ORDERED this 12th day of September, 1994.

5065____________________________

5066BEN G. WATTS, P.E.

5070Secretary

5071Department of Transportation

5074Haydon Burns Building

5077605 Suwannee Street

5080Tallahassee, Florida 32399

5083NOTICE OF RIGHT TO APPEAL

5088THIS ORDER CONSTITUTES FINAL AGENCY ACTION AND MAY BE APPEALED BY PETITIONER

5100PURSUANT TO SECTION 120.68, FLORIDA STATUTES, AND RULE 9.110, FLORIDA RULES OF

5112APPELLATE PROCEDURE, BY FILING A NOTICE OF APPEAL CONFORMING TO THE REQUIREMENTS

5124OF RULE 9.110(D), FLORIDA RULES OF APPELLATE PROCEDURE, BOTH WITH THE

5135APPROPRIATE DISTRICT COURT OF APPEAL, ACCOMPANIED BY THE APPROPRIATE FILING FEE,

5146AND WITH THE DEPARTMENT'S CLERK OF AGENCY PROCEEDINGS, HAYDON BURNS BUILDING,

5157605 SUWANNEE STREET, M.S. 58, TALLAHASSEE, FLORIDA 32399-0458, WITHIN THIRTY

5167(30) DAYS OF RENDITION OF THIS ORDER.

5174COPIES FURNISHED:

5176Larry J. Sartin

5179Hearing Officer

5181Division of Administrative Hearings

5185The Desoto Building

51881230 Apalachee Parkway

5191Tallahassee, Florida 32399-1550

5194Thomas H. Duffy

5197Assistant General Counsel

5200Department of Transportation

5203605 Suwannee Street, M.S. 58

5208Tallahassee, Florida 32399-0458

5211Tommy Strickland, pro se

5215North Florida Construction, Inc.

5219Post Office Box 129

5223Clarksville, Florida 32430

5226Stephen J. Kubik

5229155 Office Plaza Drive

5233Tallahassee, Florida 32301

Select the PDF icon to view the document.
PDF
Date
Proceedings
Date: 09/15/1994
Proceedings: Final Order filed.
PDF:
Date: 09/12/1994
Proceedings: Agency Final Order
Date: 07/01/1994
Proceedings: Department's Exceptions to Recommended Order filed.
PDF:
Date: 06/13/1994
Proceedings: Recommended Order
PDF:
Date: 06/13/1994
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 5-12-94.
Date: 06/12/1994
Proceedings: Intervenor`s Pre-Hearing Statement; Department`s Statement of Notification filed.
Date: 05/31/1994
Proceedings: (Petitioner) Notice of Filing; Proposed Recommended Order (unsigned);Cover Letter filed.
Date: 05/31/1994
Proceedings: Proposed Recommended Order of Intervenor Pro-Steel Buildings, Inc. filed.
Date: 05/31/1994
Proceedings: Department of Transportation's Proposed Recommended Order filed.
Date: 05/18/1994
Proceedings: Transcript filed.
Date: 05/12/1994
Proceedings: Letter to LJS from E. Chamblis (RE: certification of J. Watts) filed.
Date: 05/12/1994
Proceedings: CASE STATUS: Hearing Held.
Date: 05/11/1994
Proceedings: Department's Prehearing Statement filed.
Date: 05/09/1994
Proceedings: Letter to LJS from Clifford Newsome (re: statement) filed.
Date: 05/05/1994
Proceedings: CC Motion to Intervene and Request for Notification and Receipt of All Pleadings w/cover ltr filed. (From Thomas H. Duffy)
Date: 05/03/1994
Proceedings: (Respondent) Motion To Intervene filed.
Date: 05/03/1994
Proceedings: Notice of Hearing sent out. (hearing set for 5/12/94; at 9:00am; in Tallahassee)
Date: 05/03/1994
Proceedings: Prehearing Order sent out. (prehearing stipulation shall be file no later than 2 days before the hearing)
Date: 04/28/1994
Proceedings: Agency Referral letter; Letter to DOT from C. Newsome (re: protest); Letter to DOT from E. Gallon (re: protest); Supportive documents filed.

Case Information

Judge:
LARRY J. SARTIN
Date Filed:
04/28/1994
Date Assignment:
04/29/1994
Last Docket Entry:
09/15/1994
Location:
Tallahassee, Florida
District:
Northern
Agency:
ADOPTED IN PART OR MODIFIED
Suffix:
BID
 

Related DOAH Cases(s) (1):

Related Florida Statute(s) (3):

Related Florida Rule(s) (1):