95-000727BID
Deloitte And Touche, L.L.P. vs.
Department Of Health And Rehabilitative Services
Status: Closed
Recommended Order on Friday, May 12, 1995.
Recommended Order on Friday, May 12, 1995.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8DELOITTE & TOUCHE LLP, )
13)
14Petitioner, )
16)
17vs. ) CASE NO. 95-0727BID
22)
23STATE OF FLORIDA, DEPARTMENT )
28OF HEALTH AND REHABILITATIVE )
33SERVICES, )
35)
36Respondent. )
38and )
40)
41UNISYS CORPORATION, )
44)
45Intervenors. )
47_________________________________)
48RECOMMENDED ORDER
50After notice to all parties, Don W. Davis, a hearing officer of the
63Division of Administrative Hearings, held a formal hearing in this case on March
769 and 10, 1995, in Tallahassee, Florida.
83APPEARANCES
84For Petitioner: William E. Williams
89Rex D. Ware
92Huey, Guilday, & Tucker, P.A.
97106 East College Avenue, Suite 900
103Tallahassee, Florida 32301
106For Respondent: William A. Frieder
111Assistant General Counsel
114Florida Department of Health and
119Rehabilitative Services
1211323 Winewood Boulevard
124Tallahassee, Florida 32399-0700
127For Intervenor: W. Robert Vezina, III
133Cummings, Lawrence & Vezina, P.A.
1381004 DeSoto Park Drive
142Post Office Box 589
146Tallahassee, Florida 32302-0589
149Steven A. Blaske
152Unisys Corporation
1544151 Ashford Dunwoody Road
158Atlanta, Georgia 30319
161STATEMENT OF THE ISSUE
165Whether Respondent Florida Department of Health and Rehabilitative Services
174(HRS), acted illegally, dishonestly, fraudulently, arbitrarily or/and
181capriciously in determining to award the contract for RFP 95-142CM-FAP to
192Unisys Corporation (Unisys).
195PRELIMINARY STATEMENT
197On or about February 1, 1995, HRS posted a Notice of Award indicating
210intent to award the contract contemplated by the request for proposals (RFP) to
223Unisys.
224The matter was transferred to the Division of Administrative Hearings by
235HRS after Petitioner Deloitte & Touche, LLP (Deloitte), filed a notice of
247protest and a formal petition protesting the award of the contract under RFP 95-
261142CM-FAP to Unisys.
264By order dated February 23, 1995, the petition of Unisys to intervene in
277the proceeding, was granted.
281At final hearing, Deloitte presented testimony of five witnesses and 27
292exhibits. The witnesses were: HRS Secretary H. James Towey; HRS Deputy
303Secretary Lowell R. Clary; HRS Chief Information Officer Bill Belleville; HRS
314Staff Director John M. Holland, Jr.; and Elton Scott, Ph.D., an associate
326professor of finance at Florida State University. HRS presented testimony of
337one witness, Karin L. Morris, the Systems Programming Administrator charged with
348preparing the RFP, and nine exhibits. Unisys called no witnesses, but presented
36015 exhibits.
362The transcript of the final hearing was filed on April 10, 1995. Proposed
375findings of fact submitted by the parties are addressed in the appendix attached
388to this recommended order.
392FINDINGS OF FACT
3951. On November 14, 1994, HRS's Office of Information Systems distributed
406the RFP, entitled "FLORIDA System --Applications Programming Services." The RFP
416was designed to procure the programming services required by HRS to complete the
429software programming of, among other things, the state's federally mandated
439Child Support Enforcement System, and to maintain and enhance the system upon
451its completion.
4532. Upon selection of the winning proposal, HRS intended to enter into the
466contract for thirty-six months, renewable upon agreement of the parties for an
478additional 12 months. The cost proposal rates for the initial three-year term
490would be binding for any subsequent work on the project. HRS also reserved the
504right to acquire additional consulting services from the contractor for related
515activities for up to one year after the termination of the Contract.
5273. HRS began developing this RFP in the late spring or early summer of
5411994 in anticipation of the expiration of the current contract with Deloitte
553for provision of applications programming services. Before release to
562prospective proposers, the RFP was approved by HRS' Office of Contract Services
574and the Information Technology Resources Procurement Advisory Commission
582(ITRPAC), a body consisting of various state officials including the head of the
595Division of Purchasing, which ensures that the RFP complies with state rules.
607In addition, various federal agencies approved the RFP before its release to
619prospective proposers.
6214. The RFP provided that 60 percent of the proposal scoring would be based
635on the technical proposals contained in the responses to the RFP, and that the
649remaining 40 percent of the score would be assigned to the costs as submitted in
664the proposals. After scoring and weighting of the scores, the weighted scores
676were to be combined to determine the winning proposal.
6855. The breakdown of scoring between technical and cost components is based
697upon HRS' standard practice and its experience with the format required by other
710state and federal agencies with whom HRS works. The division of the scores was
724also intended to ensure that an unqualified vendor did not secure the bid solely
738on the basis of low cost.
7446. The selection of the evaluation criteria and weighting of evaluation
755points for this RFP were subject to the discretion of the Department at the time
770the RFP was prepared.
7747. On December 12, 1994, HRS held a bidders' conference at which
786representatives of Deloitte and Unisys were in attendance.
794EVALUATION OF RESPONSES
7978. On January 6, 1995, Deloitte and Unisys submitted the only two
809proposals in response to the RFP. Both proposals were deemed responsive to the
822requirements of the RFP.
8269. HRS appointed a five member Evaluation Committee to review and evaluate
838the proposals. HRS provided training to the Evaluation Committee members
848specifically directed to the proper method for reviewing and scoring proposals
859submitted in response to the RFP.
86510. Each member of the Evaluation Committee was qualified by training,
876education and experience to review and evaluate the technical merits of each
888proposal.
88911. The RFP defined the criteria by which the proposals would be reviewed,
902scored and ranked by the Evaluation Committee, and the contract awarded.
91312. Included in the RFP were blank cost proposal forms which the proposers
926were to complete. Those forms did not include any blank spaces to be filled in
941referencing costs associated with any "renewal" periods or otherwise provide for
952including information about proposed costs for any renewal periods.
96113. The Evaluation Committee members each independently reviewed the
970technical proposals submitted in response to the RFP over a period of
982approximately two weeks. Committee members submitted the raw scores from their
993technical evaluations to Karin Morris, the HRS System Program Administrator.
1003The cost proposals were opened and scored on January 20, 1995 by Ms. Morris.
101714. The RFP provided, in Section 6.0, that a comprehensive, fair, and
1029impartial evaluation would be conducted of all proposals received. The RFP also
1041provided for the grouping of evaluation criteria into six categories with points
1053assigned as follows:
10561 - Mandatory Requirements 0 points
10622 - Management Summary 0 points
10683 - Corporate Capabilities 200 points
10744 - Project Staff 200 points
10805 - Technical Approach 100 points
10866 - Project Workplan 100 points
10927 - Cost 400 points
109715. Section 6.0 of the RFP also contained the following language:
1108Selection of the successful proposer will be
1115based on the proposal that is determined to
1123be in the best interest of the department,
1131taking into consideration cost and other
1137criteria set forth in the RFP.
114316. Further, the RFP provided, in Section 6.1, that:
1152An Evaluation Committee will be established to
1159assist the department in selection of the winning
1167contractor(s). All proposals not meeting the
1173mandatory requirements will be rejected. The
1179committee will evaluate the technical approach,
1185corporate capabilities and project staff of all
1192responsive proposals. The committee will
1197rank proposers by the resulting scores and make
1205a recommended award. The committee will summarize
1212their findings and prepare an evaluation report
1219to the Deputy Secretary for Administration. The
1226report will then be presented to the Secretary
1234of HRS.
1236The Secretary will review the final report,
1243pertinent supporting materials and make the
1249determination of the final award, taking into
1256consideration cost and other evaluation criteria
1262set forth in the RFP. The Secretary reserves
1270the right to take any additional administrative
1277steps deemed necessary in determining the final
1284award. (Emphasis added).
128717. Most importantly, Section 6.3(D) of the RFP dealing with the
1298evaluation of the cost proposals stated:
1304The points awarded for the three cost evaluation
1312categories will be totaled and added to the
1320points awarded for technical evaluation cate-
1326gories 3 through 6 to determine the winning
1334proposer. (Emphasis added).
133718. After reviewing and comparing the weighted scores of both proposals,
1348the Evaluation Committee issued a "Final Report," with recommendations, on
1358January 30, 1995.
136119. The weighted technical scores reflected in the Evaluation Committee's
1371Final Report are as follows:
1376DELOITTE UNISYS
1378Corporate Capabilities 200 186.36
1382Project Staff 200 159.07
1386Technical Approach 100 76.62
1390Project Workplan 100 76.73
1394TOTAL 600 499
139720. The weighted cost scores were:
1403DELOITTE UNISYS
1405Fixed Price Tasks 10.0 2.27
1410Monthly Price 357.90 380.0
1414Hourly Price 7.77 10.0
1418TOTAL 375.67 392.2
142121. Totaling all categories as required by paragraph 6.3(D) of the RFP,
1433the Department's Evaluation Committee arrived at the following final ranking:
1443DELOITTE UNISYS
1445Technical Proposal 600 499
1449Business Proposal 376 392
1453TOTAL 976 891
145622. Based upon the Evaluation Committee's scores, Deloitte's demonstrated
1465technical capability is 20 percent higher than that of Unisys.
147523. Under the terms of the RFP, there was no discretion involved in
1488scoring the cost portion of the proposals, including the weight to be accorded
1501costs in the final overall scoring to determine the winning bidder. Based upon
1514HRS' inclusion of the specific criteria in the RFP, the cost portion scoring was
1528merely a mechanical calculation.
153224. Both of the proposers' cost proposals fall within the agency's
1543budgetary limits for the current year for accomplishing the work requested by
1555the RFP.
155725. Four of the five members of the HRS Evaluation Committee recommended
1569award of the contract to Deloitte, in the following language:
1579Deloitte & Touche scored higher in all areas
1587including recommendations. Deloitte and Touche
1592is the incumbent contractor and therefore there
1599are no risks associated with the transition.
1606Deloitte understood the requirements of the
1612RFP and addressed them more completely in their
1620proposal. Therefore, it is our recommendation
1626that the contract should be awarded to Deloitte
1634& Touche. (Emphasis added).
1638One member of the Evaluation Committee recommended the decision be left to the
1651Secretary of HRS. None of the members of the HRS Evaluation Committee
1663recommended award of the contract to Unisys.
1670HRS SECRETARY'S DECISION TO AWARD TO UNISYS
167726. On January 27, 1995, prior to preparation of the recommendations
1688contained in, or the issuance of, the Evaluation Committee's Final Report, HRS
1700Secretary James Towey convened a meeting with Deputy Secretary Lowell Clary,
1711John Holland, Bill Belleville and the department's legal counsel to discuss the
1723contract award process, a draft of the Evaluation Committee's Final Report and
1735other matters the Secretary felt relevant to HRS' ultimate decision on the RFP.
174827. At the meeting, Towey was informed by Bill Belleville that Deloitte's
1760proposal was the "best." Towey was also informed by John Holland and Bill
1773Belleville that both companies could perform under the contract. However,
1783neither Holland's nor Belleville's assessments were based on responses to the
1794RFP, but rather upon their own experience with the two vendors outside of this
1808RFP process. Belleville conceded that he believed that a proposer was qualified
1820to perform the contract by merely meeting the "mandatory" requirements of the
1832RFP, a category that was accorded zero points in the scoring criteria.
184428. Informed that both companies could perform under the contract, Towey
"1855zeroed in" on costs as the major consideration for the award of the contract.
1869At the meeting, he considered a present-value calculation of the payments that
1881the State would make over the course of a contract, if the contract had been for
1897a 48 month term. The calculation had been prepared by Dean Modling, an HRS
1911senior management analyst supervisor, although the RFP had been approved by the
1923Department of Management Services without provision for such an analysis.
193329. The RFP not inform proposers that a present-value analysis would be
1945performed and provision for the present-value of a contract was not included in
1958the scoring criteria for the proposals. Present value calculation became an
1969issue when it was raised and discussed at the January 27, 1995 meeting, and
1983subsequently used in the Secretary's decision to award the contract to Unisys.
199530. Towey also considered, in deciding to award the contract to Unisys, a
2008calculation of "raw costs," provided after the January 27, 1995 meeting. These
"2020raw costs" were presented on two charts. Both added up the amounts submitted
2033by each proposer for fixed price tasks and monthly costs, over 36 months.
2046Although the RFP did not request, and neither proposer submitted costs for a 48
2060month contract, the two charts included a calculation for a hypothetical 48
2072month contract using the same monthly payments submitted for the 36 month
2084contract. In addition, one of the two charts included a 5.8 percent factor for
2098overtime, which was also not addressed by the RFP or by the proposals submitted
2112in response to the RFP. There was no evaluation criteria contained in the RFP
2126which dealt with the issue of "raw costs" over the term of the contract.
214031. Prior to the decision to award to Unisys, HRS never performed and
2153Towey never considered a present value analysis for the 36 month contract period
2166provided for in the RFP.
217132. Finally, as a result of concern expressed at the January 27, 1995
2184meeting regarding whether Unisys could handle the immediate tasks required by
2195the contract, including requirements of the Child Support Enforcement and
2205federal certification programs, Towey considered whether there would be any risk
2216of transition if Unisys were unable to hire some of Deloitte's employees and
2229subcontractors should he decide to award the contract to Unisys. Towey
2240specifically requested Deputy Secretary Clary to research this issue. In order
2251to obtain information, Clary had HRS personnel directly contact Deloitte's
2261subcontractors. Clary responded to Towey three days later on January 30, 1995,
2273the day before the decision by Towey to award the contract to Unisys, that
2287Deloitte's subcontractors would not be prohibited from working for Unisys.
229733. Consideration of overtime and risk of transition were not criteria
2308contained in the RFP, nor were these elements evaluated and scored by the HRS
2322Evaluation Committee.
232434. By way of a January 31, 1995 memorandum to Clary announcing the award
2338of the contract to Unisys, Towey stated:
2345I have now had an opportunity to review the
2354report of the evaluators of this RFP, the
2362recommendations contained therein, the raw
2367data submitted with the proposals, and the
2374RFP. I understand the nature of the project
2382and its importance to the agency. Based upon
2390my review of the information presented to me
2398and my understanding of similar projects in
2405the past, my decision is to award the contract
2414to Unisys as the proposal most advantageous to
2422the state of Florida, taking into consideration
2429the price and other criteria set forth in the RFP.
2439Although I have considered the risk of transition
2447to a new contractor, I find that I am unable to
2458ignore the dollar savings which will result in
2466awarding the contract to Unisys. Since you and
2474your staff have assured me that both companies
2482are technically competent to perform the work,
2489I believe the monetary savings outweigh any risk
2497that might exist in the transition of contractors.
2505Therefore, I have determined that it is in the
2514state's best interest to award the contract to
2522Unisys.
2523Please take whatever steps are necessary to
2530implement this decision. (Emphasis added).
253535. By his actions, Towey exercised more than the prerogative conferred by
2547the RFP to "take any additional administrative steps deemed necessary in
2558determining the final award" and actually evaluated criteria other than that
2569contained in the RFP in reaching his decision to award the contract to Unisys.
2583Further, in awarding the contract to Unisys, Towey effectively altered the
2594relative weight of the criteria as specified in the RFP.
260436. Towey relied upon the advice of Clary. Illustrative of Clary's
2615perspective is his testimony at the final hearing that he believed the 60/40
2628weighting contained in the RFP to be inapplicable to decision making by the
2641Secretary of HRS.
264437. Neither Bill Belleville nor John Holland reviewed, in detail, the
2655proposals submitted in response to the RFP. Neither performed their own
2666independent analysis of the responses. Further, Clary never reviewed the RFP
2677nor the proposals submitted in response to the RFP.
268638. In the course of his decision making process with regard to award of
2700the contract to Unisys, Towey relied on the advice of Clary, Belleville and
2713Holland, referred to by Towey as his "top managers", despite their undisputed
2725lack of familiarity with the Deloitte and Unisys proposals.
273439. While his memorandum dated January 31, 1995, states he reviewed the
2746RFP, Towey admitted in his testimony at the final hearing that he had not
2760personally reviewed the document. Further, he never reviewed or performed his
2771own analysis of the two proposals submitted in response to the RFP.
278340. The members of the Evaluation Committee members were the only persons
2795to fully and carefully evaluate the two proposals and score them under the
2808criteria contained in the RFP. Since that time, no one else from HRS has
2822attempted to reevaluate or re-score the proposals. Neither Towey nor anyone
2833else involved in the January 27, 1995 meeting disagrees with the analysis and
2846scoring of the proposals by the Evaluation Committee.
2854PRESENT-VALUE ANALYSIS
285641. Section 1.2 of the RFP, states, in part:
2865This RFP will result in a thirty-six month
2873contract.
287442. Further, Section 4.12(C) of the RFP states, in part:
2884Upon selection of the winning proposal, the
2891department shall enter into a contract for
2898thirty-six (36) months.
290143. Although the possibility of renewal of the contract for a maximum of a
2915single, one year term is contained in the RFP, there is no provision in the RFP
2931which requires that HRS renew the contract after 36 months or that the
2944contractor accept a renewal after 36 months for any specific term.
295544. By the terms of the RFP, any renewal of the contract for a period
2970beyond the 36 month term is subject to negotiation between the contractor and
2983the department. While proposals submitted by Unisys and Deloitte commit to
2994maintaining the same costs in the event of renewal, negotiation as to the
3007length, price and staffing for any renewal period less than a year, is not
3021excluded by the terms of the RFP. Neither HRS nor the contractor is bound,
3035under the terms of the RFP, to any extension of the contract.
304745. HRS' own manual, HRSP 75-3, entitled "Developing a Request for
3058Proposal," states, in the section on contract renewals:
3066If Contract Renewals have been provided for
3073in this RFP, include the following recommended
3080language in the Special Provisions subsection
3086of the RFP:
3089This contract may be renewed on a yearly basis
3098not to exceed two (2) years beyond the initial
3107contract or for a period no longer than the term
3117of the original contract whichever period is
3124longer. Such renewals shall be contingent upon
3131satisfactory performance evaluations as determined
3136by the department and shall be subject to the
3145availability of funds. As specified in the
3152provider's response to the RFP/ITB, the total
3159cost for the contract under the' first year
3167renewal will not exceed $ ______ and the second
3176year renewal will not exceed $ _______. Each
3184renewal shall be confirmed in writing and shall
3192be subject to the same terms and conditions set
3201forth in the initial contract. (Emphasis added).
320846. Another in-house document at HRS is HRS manual, HRSM 75-2 (May 1, 1994
3222update), entitled "Contract Management System for Contractual Services".
3231Chapter 5 of that document, entitled "Contractual Procurement Requirements,"
3240states, in pertinent part:
3244The dollar amount and the manner in which the
3253costs for the . . . renewals will be calculated
3263must be specified in the response to the RFP and
3273in the resulting contract document.
327847. By contrast, the RFP contains none of the language specified in either
3291HRS manual regarding renewal. Section 4.12(c) of the RFP merely states:
3302This contract term shall be renewable for a max-
3311imum of a one year term upon the mutual agreement
3321in writing of the contractor and the department.
3329(Emphasis added).
333148. Terms of the RFP did not invite proposers to submit a specific cost or
3346any other information for a renewal period or explain how costs for a renewal
3360period would be calculated. Neither did the RFP contain any language that
3372renewals would be conditioned on satisfactory performance by the contractor.
338249. Proposers, on blank cost forms, were requested in the RFP to provide
3395HRS with their proposed prices for fixed price items, monthly costs and hourly
3408costs. The forms, contrary to the requirements of HRS manuals applicable in
3420situations where information for a renewal term is requested, did not provide a
3433place for proposers to indicate costs for any renewal term or to demonstrate how
3447those costs were calculated.
345150. Both contractors understood that any renewal would be subject to
3462negotiation. The "Standard Contract" contained in the RFP provides only for a
3474term of 36 months and a cost for that specific contract term.
348651. Consistent with the terms of the RFP that the contract was for a 36
3501month term, HRS submitted, on more than one occasion, materials to ITRPAC. In
3514those materials, HRS represented that the proposed budget amounts of $25 million
3526and $28 million for the project were for a three year term contract.
353952. The Notice of Award which HRS issued stated that a three year contract
3553was to be awarded.
355753. Although the RFP addressed staffing at a maximum of 107 persons, HRS
3570was aware that 100 percent staffing might not always occur. Section 2.l(B)(5)
3582of the RFP permits 90 percent of the maximum staffing level at a given time
3597without the vendor incurring a penalty.
360354. At one point in the RFP preparation, a draft of the RFP required 95
3618percent staffing. Even that level was considered by HRS to be too restrictive
3631and anti-competitive and was amended to 90 percent out of fear that a 95 percent
3646staffing level would discourage submission of competitive proposals.
365455. The 90 percent figure was also used in the RFP to account, in part,
3669for projected attrition of contractor employees that HRS had historically
3679experienced on this project. From the standpoint of budgetary allowances by HRS
3691for the project, it is realistic to believe that the job will be staffed at
3706somewhere between 90 percent and 95 percent rather than at the maximum staffing
3719level of 107 employees.
372356. Although Section 4.15(D)(5) of the RFP states that the State is not
3736responsible for paying contractor's employees for leave or vacation time, the
3747testimony of Petitioner's financial expert, Dr. Elton Scott, establishes that a
3758reasonable assumption is to assume that each employee is entitled to, and would
3771take, at least two weeks vacation. Such an assumption should also be included
3784when performing a present value analysis, particularly when assuming 100 percent
3795staffing.
379657. Depending on budget allocations for this project, it is possible that
3808HRS would only require that the contractor provide as few as 46 employees.
382158. The present value calculation performed by HRS indicated that, over 48
3833months, at 100 percent staffing (107 employees), the monetary cost of awarding
3845the contract to Unisys would be approximately $500,000 less than the cost of
3859awarding the contract to Deloitte, a savings of approximately 1.5 percent over
3871the term of the contract.
387659. As demonstrated by HRS' subsequent present value calculation performed
3886at final hearing in this cause, for the 36 month actual contract period, at
3900maximum staffing, HRS would realize a savings of no more than $39,802 by
3914awarding the contract to Unisys, a savings of less than 2/10ths of 1 percent.
392860. None of HRS' present value calculations accounted for leave/vacation
3938time or for any staffing levels under 100 percent for any other reasons.
395161. Based upon the terms of the RFP, the language of HRS' procurement
3964manuals, and the expert testimony of Dr. Scott, any valid present-value analysis
3976should have included a 36 month term contract. Any such analysis should also
3989have taken into account varying levels of staffing, leave/vacation time, and
4000overtime if staffed at the minimum required.
400762. A properly performed present-value analysis indicates that Deloitte's
4016proposal is less expensive than the Unisys proposal in the following amounts
4028over a 36 month contract term, at the staffing levels indicated:
4039Employees Leave/Vacation Time Overtime Deloitte Savings
4045107 2 weeks none $12,791
405196 none none $109,062
405696 none 5.8 percent $ 18,327
406346 none none $844,473
4068(Pet. Exh. 15)
407163. The only scenario in which the Unisys proposal is less costly than the
4085Deloitte proposal, using the proper present value analysis, would be at 107
4097employees, with no accounting for leave time. This unlikely future scenario
4108would result in a savings of no more than $47,378, or less than 2/10ths of l
4125percent of the contract amount over 36 months.
413364. Because it requires an up-front payment of more than $1,600,000 (as
4147compared to $78,000 for Deloitte), the Unisys proposal places the State of
4160Florida at substantially more financial risk than the Deloitte proposal in the
4172event of nonperformance by Unisys.
417765. On February 1, 1995, HRS posted its notice of intent to award the
4191Contract to Unisys. Deloitte filed its timely notice of intent to protest on
4204February 3, 1995, and filed its timely formal protest and request for hearing on
4218February 13, 1995.
4221CONCLUSIONS OF LAW
422466. The Division of Administrative Proceedings has jurisdiction over the
4234parties and the subject matter of this proceeding. Sections 120.53(5) and
4245120.57(1), Florida Statutes.
424867. Deloitte has standing to challenge the actions of HRS in this
4260proceeding and to seek award of the contract at issue.
427068. Unisys has standing to intervene in this proceeding.
427969. In Wester v. Belote, 138 So. 721, 724 (Fla. 1931), the Court held that
4294competitive bidding requirements:
4297. . . serve the object of protecting the public
4307against collusive contracts and prevent favoritism
4313toward contractors by public officials and tend
4320to secure fair competition upon equal terms to
4328all bidders, they remove temptation on the part
4336of public officers to seek private gain at the
4345taxpayer's expense, are of highly remedial
4351character, and should receive a construction
4357always which will fully effectuate and advance
4364their true intent and purpose and which will
4372avoid the likelihood of same being circumvented,
4379evaded, or defeated. Emphasis added).
438470. Petitioner's burden in this proceeding is to prove that the actions of
4397the agency were either illegal, dishonest, fraudulent, arbitrary and/or
4406capricious. Department of Transportation v. Groves-Watkins Constructors, 530
4414So. 2d 912 (Fla. 1988). "[I]ntervention to prevent the rejection of a bid
4427should occur only when the purpose or effect of the rejection is to defeat the
4442object and integrity of competitive bidding." Id. at 913.
445171. The discretion afforded state agencies in soliciting and accepting
4461bids is not unbridled and can be overturned when the purpose of competitive
4474bidding has been subverted. Wood Hopkins Contracting Co. v. Roger Au and Son,
4487Inc., 354 So. 2d 446 (Fla. 1st DCA 1978); Caber Systems v. Department of General
4502Services, 530 So. 2d 325 (Fla. 1st DCA 1988).
451172. An agency's actions are considered to be arbitrary and capricious when
4523they are not supported by facts or logic, or are despotic. Aqrico Chemical
4536Company v. Department of Environmental Regulation, 365 So. 2d 759 (Fla. 1st DCA
45491979).
455073. An arbitrary agency action includes "one which is decisive but not
4562governed by fixed rule or standard." Youth Crime Watch of America v. Department
4575of Health and Rehabilitative Services, 619 So. 2d 405 (Fla. 3rd DCA 1993).
458874. As found by the Hearing Officer in Courtney v. Department of Health
4601and Rehabilitative Services, 12 F.A.L.R. 2226 (Final Order - 1990), in
4612determining that HRS had subverted the competitive procurement process and
4622improperly awarded a contract:
4626Part of the reciprocity achieved under the
4633competitive bidding process is achieved in
4639the bid specifications and weighted bid
4645evaluation criteria. Potential bidders are
4650advised in advance of the requirements to be
4658met in order to receive the contract award,
4666as well as the standards by which each bid
4675will be evaluated by the agency and each
4683standard's relative importance to the agency.
4689In essence, this advance notice enables a
4696potential bidder to gauge the agency's notions
4703of the type of bid best suited to its purpose
4713for the money involved. A potential bidder can
4721then determine whether he can meet the bid
4729specifications and criteria and thereby determine
4735whether he wishes to go to the time, expense
4744and trouble of preparing and submitting a fairly
4752lengthy and detailed bid proposal. Therefore,
4758central to the integrity and reciprocity of the
4766competitive bidding process is the requirement
4772that an agency's action on a bid can be expressed
4782within the bid specifications and evaluation
4788criteria which it created. In other words,
4795should an agency reject a bid for reasons not
4804given weight in the bid evaluation criteria,
4811that action would go to the integrity of the
4820competitive bidding process and would be
4826arbitrary and capricious. (Emphasis added).
4831[See also: Adlee Developers v. HRS, 14 F.A.L.R. 4938 (Final Order - July 28,
48451992), citing Aurora Pump v. Gould Pumps, 424 So. 2d 70 (Fla. 1st DCA 1982)
4860("An agency issuing an ITB must evaluate the bids received thereunder solely on
4874the criteria stated in the ITB."); and Bay Plaza I v. HRS, 11 F.A.L.R. 2854
4890(Final Order - April 13, 1989) ("However, the agency issuing the invitation must
4904evaluate bids received solely on the criteria stated in the invitation to bid
4917and prospective bidders are entitled to rely upon the completeness of the terms
4930stated therein.") (also citing Aurora Pump)].
4937EVALUATION OF PROPOSALS
494075. Section 287.057(2), Florida Statutes, states, in part, that if an
4951agency chooses to procure contractual services through an RFP, it must include:
4963. . . a statement of the . . . contractual
4974services sought and all contractual terms
4980and conditions applicable to the procurement
4986of contractual services, including the criteria,
4992which shall include, but need not be limited to,
5001price, to be used in determining acceptability
5008of the proposal . . . (Emphasis added).
501676. Section 287.057(2), Florida Statutes, also provides:
5023The award shall be made to the responsible
5031offeror whose proposal is determined in writing
5038to be the most advantageous to the state, taking
5047into consideration the price and the other
5054evaluation criteria set forth in the request
5061for proposals. . . (Emphasis added).
506777. Further, Section 287.012(16), Florida Statutes, states, in part:
5076Requests for proposals shall state the relative
5083importance of price and any other evaluation
5090criteria. (Emphasis added).
509378. As noted in System Development Corporation v. HRS, 423 So. 2d 433
5106(Fla. 1st DCA 1982), an Invitation To Bid (ITB) must be considered on the basis
5121of cost, i.e. the lowest and best bid, whereas a response to an RFP should be
5137considered on the basis of technical excellence as well as cost.
514879. In this case, HRS determined that it was advisable to use the request
5162for proposal process to select the appropriate contractor for the services
5173sought in the RFP. The RFP provided that the winning proposer would be chosen
5187based on the evaluation criteria contained in the RFP, assigning 60 percent of
5200possible points to technical excellence and 40 percent to cost.
521080. In the initial stages of the process of evaluating the responses, HRS
5223adhered to correct procedures in selecting a qualified evaluation committee,
5233training its members and having the members independently score each proposer's
5244technical capability. Subsequently, in accordance with the RFP, the cost
5254proposals were opened and mechanically assigned the weighted cost scores across
5265the three subcategories described in the RFP. Finally, the weighted technical
5276scores and weighted cost scores were combined to reveal that Deloitte was the
"5289winning proposer." The evaluation committee thus recommended award to
5298Deloitte.
529981. HRS departed, however, from the evaluation and scoring methodology set
5310forth in the RFP commencing with the meeting of January 27, 1995. It is clear
5325that HRS, prior to Secretary Towey's announced decision, considered factors
5335outside the evaluation criteria contained in the RFP, and more importantly,
5346reweighted the relative importance of those criteria so that cost became the
5358major consideration, contrary to the terms of the RFP.
536782. Alternatively stated, the scoring process was ignored contrary to
5377dictates of the RFP that the scoring process would determine the winning
5389proposal and that Towey would only utilize "administrative steps" to perfect an
5401award. In actuality, the HRS Secretary went far beyond mere administrative,
5412clerical steps in his discard of the scoring process. On the advice of managers
5426operating without benefit of personal review of the substantive data, he
5437considered both proposers as equals and determined the award totally by a cost
5450estimate resulting from a flawed analysis.
545683. In reality, had the requirements of the RFP governed the selection
5468process, cost considerations would have been considered secondary to technical
5478superiority. If the HRS Secretary had determined the results of the initial
5490scoring process with regard to technical ability (weighted at 60 percent) to be
5503flawed, it is conceivable that justification would have existed sufficient for
5514him to have ordered that the proposals be rescored. But such was not the case
5529in the instant matter. Notably, the correctness of the original evaluators or
5541scoring was not questioned or challenged by management.
554984. Bidders justifiably rely on the criteria set forth in an RFP. To
5562allow HRS to alter the evaluation criteria set forth in the RFP, and/or the
5576relative weight placed on those criteria, contrary to the terms contained in the
5589RFP, serves to completely compromise the purpose of the competitive bidding
5600process. If such a procedure were permissible, an agency could set forth
5612seemingly fair evaluation criteria in an RFP, inducing the submission of
5623proposals, and then alter the importance of the announced criteria to improperly
5635select a favored contractor.
563985. It is not only the actual presence of favoritism or impropriety, but
5652the appearance of favoritism or other impropriety which the law seeks to
5664eliminate. In the present case, because HRS clearly considered factors in a
5676manner contrary to that announced in the RFP and required under applicable law,
5689i.e. overtime, risk of transition, and a reweighting of the relative importance
5701of cost, the acts of HRS were illegal, arbitrary and capricious and therefore
5714impermissible.
571586. As noted in Courtney, supra, it is arbitrary and capricious for HRS to
5729propose award in the instant case to Unisys based upon what must be labeled
"5743improper award factors" and "incorrect weighting of the criteria."
575287. Although this procurement was an RFP, the matter has essentially been
5764treated by HRS as an Invitation To Bid (ITB) by the determination to make the
5779proposed award to Unisys. HRS chose to issue an RFP in which price accounted
5793for only 40 percent of the scoring. Subsequently, Secretary Towey ultimately
5804decided that if the proposers each met the minimum mandatory technical
5815requirements of the RFP (which was accorded zero points in category 1 of the
5829scoring criteria), price would be the determining factor. An agency cannot
5840invite a proposal on an RFP to be evaluated as was proposed here, and ultimately
5855award the contract as if it were an ITB.
586488. The facts in Latecoere International, Inc. v. Department of Navy, l9
5876F.3rd 1342 (11th Cir. 1994), are also similar to the present case. There,
5889although the solicitation documents indicated that cost was not the most
5900important factor and the challenger was determined to have submitted the
5911technically superior proposal, the Navy improperly applied the solicitation
5920criteria to award the contract to another company whose cost was 7.8 percent
5933lower than that of the challenger. The Court noted:
5942. . . it is improper to induce an offer repre-
5953senting the highest quality and then reject it
5961in favor of a materially inferior offer on the
5970basis of a relatively insignificant price
5976difference. [citation omitted] In awarding a
5982contract, a selection authority is required to
"5989use the factors established in the solicitation
5996. . . consider any rankings and ratings, and if
6006requested, any recommendations prepared by
6011evaluation and advisory groups" and to provide
6018supporting documentation . . . showing the
6025relative differences.
6027Where cost is secondary to technical consider-
6034ations under [a solicitation] evaluation scheme
6040. . . selection of a lower priced proposal over
6050a proposal with higher technical [ratings]
6056requires adequate justification, i.e., some
6061showing the [selection authority] reasonably
6066concluded that, notwithstanding the point
6071differential between the two proposals, they
6077were essentially equal. [citation omitted]
6082When a source selection authority's documentation
6088contains an inadequate rationale to support "a
6095decision to make an award to a lower priced
6104offeror with a lower technical ranking," the
6111selection authority's decision can be said to
6118have no rational basis. 19 F.3rd at 1360, 1361
6127(Emphasis added).
612989. In this case, the only technical evaluation performed demonstrated
6139that Deloitte's proposal scored 20 percent higher than that of Unisys. Although
6151Secretary Towey was told informally by HRS personnel, who had neither evaluated
6163nor scored the proposals, that both proposers could perform the work, there was
6176no factual basis from which HRS could have determined that the two proposals
6189were technically equal. In fact, the only credible evidence in the record
6201demonstrated that Deloitte's technical proposal was significantly superior to
6210that of Unisys.
621390. The Court in Latecoere perhaps best summarized the general standards
6224that must apply to competitive solicitations:
6230An executive agency shall evaluate sealed bids
6237and competitive proposals based solely on the
6244factors specified in the solicitation. [citation
6250omitted] Agencies do not have the discretion to
6258announce in the solicitation that they will use
6266one evaluation plan, and then follow another;
6273once offerors are informed of the criteria
6280against which their proposals will be evaluated,
6287the agency must adhere to those criteria . . .
629719 F.3rd at 1359.
630191. In this case, HRS exercised its discretion when selecting the
6312evaluation criteria to be included in the RFP. In determining that 60 percent
6325of the overall scores would be assigned for technical capabilities and 40
6337percent for costs, HRS recognized the importance of technical qualifications
6347over cost savings. HRS cannot again exercise its discretion, after the fact, to
6360change those criteria.
636392. In light of Deloitte's score with regard to technical superiority and
6375the absence of any discretion to change the scoring criteria for the cost
6388proposals, Deloitte's total score entitled it to award of the contract under the
6401terms of the RFP.
640593. In reaching his decision to award the contract to Unisys, Secretary
6417Towey specifically stated that he was doing so because the Unisys proposal was
6430the "most advantageous to the State of Florida." Based on scoring criteria
6442contained in the RFP, the only way he could reach that determination was if the
6457cost savings of the Unisys proposal were so great as to overcome the technical
6471superiority of Deloitte's proposal as set forth in the Evaluation Committee's
6482Final Report. The record clearly reflects, however, that selection of the
6493Unisys' proposal results in either an insignificant cost savings to the State or
6506no savings at all.
651094. In this case, HRS acted in an illegal, arbitrary and capricious manner
6523in proposing to award the contract for the RFP to Unisys. The evaluation and
6537scoring criteria of the RFP were clear, the Evaluation Committee performed the
6549only fair and adequate analysis of the proposals, and the Secretary of HRS was
6563not free to alter the relative weight of the scoring criteria in making his
6577final decision to award the contract.
658395. As established by the proof presented in this proceeding, Respondent's
6594determination of an intended award to Unisys is legally flawed and clearly
6606arbitrary.
6607RECOMMENDATION
6608Based on the foregoing findings of fact and conclusions of law, it is
6621RECOMMENDED that a final order be entered which declines the award to
6633Unisys and takes into account the foregoing findings of fact and conclusions of
6646law when deciding the future course of contracting for the services sought by
6659the RFP.
6661DONE and ENTERED this 12th day of May, 1995.
6670___________________________________
6671DON W. DAVIS, Hearing Officer
6676Division of Administrative Hearings
6680The DeSoto Building
66831230 Apalachee Parkway
6686Tallahassee, Florida 32399-1550
6689(904) 488-9675
6691Filed with the Clerk of the
6697Division of Administrative Hearings
6701this 12th day of May, 1995.
6707APPENDIX
6708In accordance with provisions of Section 120.59, Florida Statutes, the
6718following rulings are made with regard to purposed findings of fact submitted by
6731the parties.
6733Intervenor's Proposed Findings:
67361. Adopted.
67382. Adopted as to 1st sentence. Remainder not relevant
6747with exception of last sentence which is adopted.
67553. Rejected, subordinate to HO findings.
67614. Accepted.
67635. Rejected, subordinate to HO findings.
67696.-7. Rejected, cumulative.
67728. Accepted.
67749.-10. Rejected, subordinate to HO findings.
678011. Accepted.
678212. Rejected, subordinate to HO findings.
678813. Accepted.
679014. Rejected, cumulative.
679315.-17. Rejected, subordinate.
679618.-20. Rejected, relevance.
679921.-22. Accepted.
680123. Rejected, subordinate to HO findings.
680724.-25. Accepted.
680926.-29. Rejected, subordinate to HO findings.
681530. Accepted.
681731.-36. Rejected, subordinate.
682037. Rejected, weight of the evidence.
682638. Rejected, opinion, weight of the evidence.
683339.-41. Rejected, subordinate.
6836Respondent's Proposed Findings:
68391.-3. Adopted, not verbatim.
68431.-6. Adopted by reference.
68477. Rejected, relevance.
68508.-9. Rejected, cumulative, unnecessary.
685410.-12. Accepted.
685613. Rejected, cumulative.
685914.-16. Accepted.
686117. Rejected, weight of the evidence.
686718. Rejected, relevance.
687019. Rejected, weight of the evidence.
687620.-21. Rejected, argument.
687922.-23. Rejected, subordinate to HO findings.
688524. Rejected, argument.
688825.-27. Rejected, subordinate, weight of the evidence.
689528.-29. Rejected, relevance.
689830.-31. Rejected, subordinate.
690132. Rejected, weight of the evidence.
690733. Rejected, subordinate, weight of the evidence.
691434. Rejected, relevance.
691735.-36. Rejected, cumulative.
692037. Rejected, weight of the evidence.
692638. Accepted.
692839. Rejected, argument, weight of the evidence.
693540. Rejected, relevance, argument.
693941.-42. Rejected, argument.
694243. Rejected, subordinate.
694544. Rejected, 20 percent difference, improper
6951characterization.
695245. Rejected, relevance, argument.
695646. Rejected, argument, subordinate.
696047. Rejected, redundant, subordinate.
696448. Rejected, legal conclusion.
696849. Rejected, relevance, argument, lack of credible
6975evidence.
697650. Rejected, weight of the evidence.
698251. Rejected, subordinate.
698552. Rejected, weight of the evidence.
699153. Rejected, relevance.
699454. Rejected, argumentative, legal conclusion.
699955. Rejected, legal conclusion, argument.
700456. Rejected, legal conclusion.
7008Petitioner's Proposed Findings Of Fact:
70131.-43. Accepted, though not verbatim in some instances.
702144. Subordinate to HO findings.
702645.-48. Accepted.
702849. Subordinate.
703050. Accepted.
703251. Subordinate.
703452.-70. Accepted.
7036COPIES FURNISHED:
7038William E. Williams, Esq.
7042Red D. Ware, Esq.
7046Huey, Guilday & Tucker, P.A.
7051106 E. College Ave., Ste. 900
7057Tallahassee, FL 32301
7060William A. Frieder, Esq.
7064Department of Health and
7068Rehabilitative Services
70701323 Winewood Blvd.
7073Tallahassee, FL 32399-0700
7076W. Robert Vezina, III
7080Cummings, Lawrence & Vezina, P.A.
70851004 DeSoto Park Dr.
7089Tallahassee, FL 32302
7092Steven A. Blaske
7095Unisys Corporation
70974151 Ashford Dunwoody Rd.
7101Atlanta, GA 30319
7104Robert L. Powell, Agency Clerk
7109Department of Health and
7113Rehabilitative Services
71151323 Winewood Blvd.
7118Tallahassee, FL 32399-0700
7121Kim Tucker, Esq.
7124Department of Health and
7128Rehabilitative Services
71301323 Winewood Blvd.
7133Tallahassee, FL 32399-0700
7136NOTICE OF RIGHT TO SUBMIT EXCEPTION
7142All parties have the right to submit written exceptions to this Recommended
7154Order. All agencies allow each party at least 10 days in which to submit
7168written exceptions. Some agencies allow a larger period within which to submit
7180written exceptions. You should contact the agency that will issue the final
7192order in this case concerning agency rules on the deadline for filing exceptions
7205to this Recommended Order. Any exceptions to this Recommended Order should be
7217filed with the agency that will issue the final order in this case.
7230=================================================================
7231AGENCY FINAL ORDER
7234=================================================================
7235STATE OF FLORIDA
7238DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES
7244DELOITTE & TOUCHE LLP,
7248Petitioner,
7249HRS Case No.
7252v. DOAH Case No. 95-727-BID
7257STATE OF FLORIDA, DEPARTMENT
7261OF HEALTH AND REHABILITATIVE
7265SERVICES,
7266Respondent,
7267v.
7268UNISYS CORPORATION,
7270Intervenor.
7271_______________________________/
7272FINAL ORDER
7274This cause came on before me for the purpose of determining final agency
7287action in the above styled cause. After referral to the Division of
7299Administrative Hearings, a Recommended Order was issued by the Honorable Don
7310Davis on May 12, 1995.
7315The undersigned was appointed by Governor Lawton Chiles on May 24, 1995, as
7328substitute Secretary of the Department of Health and Rehabilitative Services
7338pursuant to Section 120.71, Florida Statutes. That appointment is evidenced by
7349a certification by Secretary of State Sandra Mortham attached as Appendix "A".
7362A copy of the Hearing Officer's Recommended Order is also attached hereto
7374as Appendix "B". The Hearing Officer made extensive Findings of Fact, which are
7388accepted and made a part of this Final Order as if specifically stated herein.
7402Additionally, the Recommended Order contains several conclusions of law which,
7412according to the Hearing Officer, result in a finding that Secretary Towey acted
7425in an illegal, dishonest, fraudulent, arbitrary and/or capricious manner by
7435awarding the contract at issue here to Unisys. The conclusions of law relied on
7449by the hearing officer to reach that result are specifically rejected, and this
7462order is entered determining that the award to Unisys is within that measure of
7476discretion allowed to the Agency Secretary.
7482FACTUAL SETTING
7484In November of 1994, the Department of Health and Rehabilitative Services,
7495("HRS"), distributed an RFP entitled "FLORIDA System-- Applications Programming
7506Services." On December 12, 1994, HRS conducted a bidders conference at which
7518representatives of Deloitte & Touche and Unisys were present. In early January
7530of 1995, Deloitte & Touche and Unisys submitted the only two proposals in
7543response to the RFP. HRS considered both to be responsive to the RFP. An
7557evaluation Committee was selected and trained to analyze the proposals. The
7568members of that team individually evaluated the proposals and scored Deloitte &
7580Touche higher than Unisys. The weighted technical scores submitted by the
7591evaluation team were: Deloitte & Touche- 600; Unisys- 499. Cost scores were
7603evaluated separately and resulted in the following scores: Deloitte & Touche-
7614375.67; Unisys-392.2. The combined, (technical and cost) scores: Deloitte &
7624Touche- 976; Unisys- 891. Of the five members of the evaluation team, four
7637recommended award to Deloitte & Touche and one recommended that the decision be
7650left to Secretary Towey.
7654Assessment of Vendors
7657Secretary Towey called a meeting of his top managers to discuss the
7669recommendations from the evaluation team. That meeting was recorded and a
7680transcript was available at the hearing held before DOAH. The discussion of the
7693relative merits of the two proposals first involved questions regarding the
7704capability of each vendor to perform the contract. The Secretary asked
7715questions of his managers respecting the point difference between the two
7726vendors. At one point he specifically asked if the differential was similar to
7739the distinction between a Cadillac and a Corolla, "both can get you from point A
7754to point B, so the issue is the technical competence and meritoriousness."
7766(See: Exhibit 19, page 10). After much discussion, the managers at HRS
7778responded that both vendors could do the job.
7786Present Value Assessment
7789The discussion then turned to other factors including the transition that
7800would be required if a contractor other than the incumbent was picked, the
7813start-up costs associated with the proposals, and finally, the present value of
7825both proposals over the three year contract and the expected renewal of one
7838year. Such a present value analysis was provided and it showed that the State
7852would save approximately $500,000 if Unisys was selected.
7861The Hearing Officer considered testimony at the hearing from an expert in
7873present value analysis who drew different conclusions, primarily because he drew
7884different assumptions from which his present value analysis was provided. 1/
7895The expert admitted that the HRS present value analysis, drawn from the
7907assumptions made by HRS, showed a substantial savings to the state if Unisys was
7921awarded the contract. 2/ Secretary Towey decided to award the contract to
7933Unisys. A timely protest was filed by Deloitte & Touche, and Unisys was allowed
7947intervenor status.
7949LEGAL DETERMINATIONS
7951Florida Statutes provide guidance respecting the evaluation and award of
7961contractual proposals through the RFP process. Section 287.057(2), Florida
7970Statutes, states:
7972(2) When an agency determines in writing that the use
7982of competitive sealed bidding is not practicable,
7989commodities or contractual services shall be procured
7996by competitive sealed proposals.
8000If the agency contemplates renewal of the commodities
8008or contractual services contract, it shall be so stated
8017in the request for proposals. The proposal shall
8025include the price for each year for which the contract
8035may be renewed. Evaluation of proposals shall include
8043consideration of the total cost for each year as quoted
8053by the offeror.
8056The award shall be made to the responsible offeror
8065whose proposal is determined in writing to be the most
8075advantageous to the state, taking into consideration
8082the price and the other criteria set forth in the
8092reguest for proposals.
8095Additionally, the Secretary's determination of cost had to be based on a present
8108value analysis. Section 287.0572, Florida Statutes, provides:
8115(1) The cost of bids or proposals for state contracts
8125which require the payment of money for more than 1 year
8136and which include provisions for unequal payment
8143streams or unequal time payment periods shall be
8151evaluated using present-value methodology.
8155Thus, the Secretary was compelled to look at cost for the three year contract
8169including the cost provisions for the one year extension and was also compelled
8182to analyze those costs using a present value methodology. Both parties were
8194required by law and by the RFP to provide cost information for the three year
8209contract and the one year renewal. (See: Finding of Fact #44 in the Recommended
8223Order.) Both proposals were found to be responsive to the RFP.
8234The Nature of the RFP Process
8240Aside from the statutory list of requirements that the agency head must
8252consider, are those considerations which the RFP process allows the agency head
8264to consider within the discretion allowed a public officer. The RFP process is
8277different from the Invitation to Bid process because it allows the agency head
8290to use his or her common sense to determine which proposal is most advantageous
8304to the state. The Invitation for Bid process, on the other hand, is limited to
8319an analysis of price. (See generally: System Development Corp. v. HRS, 423
8331So.2d 433 (Fla. 1st DCA 1982). The RFP process seeks information respecting the
8344offeror's employees, technical skill, reliability and cost. Those factors are
8354then evaluated by a team consisting of employees who have the skill to analyze
8368the technical criteria. The team submits a recommendation to the agency head.
8380This method of procurement does not require the agency head to decide the best
8394interest of the state in a vacuum. The Hearing Officer found that the agency
8408head is limited to factors stated in the RFP and would therefore be bound to
8423accept the proposal which scored the highest. That conclusion of law is in
8436error.
8437Secretary Towey received an accounting degree with high honors. The RFP
8448process does not require that he ignore his training and experience. With
8460respect to the scoring process, it is axiomatic to statistical analysis that a
8473proposal with a score 20 percent higher than another, may not be 20 percent
8487better than the other.
8491Agency secretaries are public officers, commissioned by the Governor and
8501subject to Senate confirmation. A public officer, by definition, is one who has
8514the authority to exercise a portion of the sovereign power of the state. State
8528ex rel. Holloway v. Sheats, 83 So. 508, 509 (Fla. 1919). That empowerment to
8542decide what is in the best interest of the agency, or as here, most advantageous
8557to the state, is at the heart of this case.
8567Petitioner's Burden of Proof
8571Petitioner was required to demonstrate that the Secretary, by awarding the
8582contract to Unisys, participated in a process that was illegal, dishonest,
8593fraudulent, arbitrary and/or capricious. Department of Transportation v.
8601Groves-Watkins Constructors, 530 So.2d 912 (Fla. 1988). The conclusion of law
8612found in the recommended order that the evidence demonstrated illegality,
8622dishonesty, fraud, and arbitrary and/or capricious conduct, is in error. Wide
8633discretion is allowed to the agency in the selection of proposals, and the
8646exercise of discretion will be upheld even if it may appear erroneous or if
8660reasonable persons may disagree. Liberty County v. Baxter's Asphalt & Concrete,
8671Inc., 421 So.2d 505 (Fla. 1982). No dishonesty was found; no illegality or
8684fraud was demonstrated. The evidence instead indicates a process where every
8695factor was carefully considered and where the Secretary used his best judgment
8707to find the proposal which was most advantageous to the state. No factual
8720finding by the Hearing Officer indicates that the petitioner met the standard
8732established by Groves-Watkins, sura.
8736Interpreting the Secretary's Duty to Assess the Proposal
"8744Most Advantageous to the State"
8749There are no Florida cases which directly address the issue presented here.
8761A case decided by the Comptroller General in In re Grey Advertising, Inc., 55
8775Comp. Gen. 1111 (1976)(1976 WL 13172), however, provides guidance in a very
8787similar situation. (The case has been attached as Appendix "C") Grey has been
8801recognized as authoritative in several other decisions such as Delta Data
8812Systems Corp v. Webster, 744 F.2d 197 (D.C. Cir. 1984), decided by then Judge
8826Scalia. In Grey, the RFP in question established a 1000 point evaluation
8838process, listing seven technical criteria and one criterion based on cost. The
8850cost factor accounted for only five points of the 1000 total. After an
8863evaluation panel considered the technical factors, the incumbent contractor Grey
8873was the high scorer with 924.99 points. A second proposer, Bates, received
8885872.63 points. The panel recommended that the award go to Grey. The Navy
8898Material Command, ("NAVMAT"), reviewed the recommendation and rejected it,
8909determining that the two proposals were relatively equal technically and cost
8920should be the determining factor. The Bates proposal offered substantial
8930savings to the government. The Comptroller General upheld the award finding
8941that NAVMAT may use its judgment and discretion to determine the significance of
8954the difference in scores. There as here, cost became the deciding factor.
8966Further, Grey stands for the principle that great deference is to be allowed to
8980the agency when deciding which is the most advantageous proposal. The
8991Comptroller General's reasoning fits squarely with the concept in this case that
9003the process of awarding a contract pursuant to an RFP is flexible, and allows
9017the Secretary to exercise judgment which will be given great deference on
9029appeal.
9030Legal Analysis of the
9034Present-Value Evaluation Performed by HRS
9039The Petitioner produced evidence at the hearing in an attempt to prove that
9052the present-value assessment used by HRS was incorrect. Petitioner's expert
9062testified that certain assumptions made by HRS were improper, and provided his
9074analysis which demonstrated different cost factors than those determined by HRS.
9085The law does not require that the agency use set assumptions in a present value
9100analysis. The Secretary and his managers can use their judgment to determine
9112reasonable assumptions upon which that analysis will be conducted. If either
9123vendor wished to be heard on the issue of present-value analysis, there was time
9137for that to be discussed at the bidders conference. Neither proposer asked that
9150their assumptions be drawn in any present value analysis to be done by HRS.
9164They were on constructive notice of Section 287.052(1), Florida Statutes, which
9175required such an evaluation. To challenge that analysis now is to second guess
9188the agency when the time for clarification has passed. The Hearing Officer drew
9201his own conclusions from the expert and determined that the HRS evaluation was
9214not the "better" present-value assessment. The Hearing Officer may not
9224substitute his judgment for that of the agency. Further, as a matter of law the
9239Hearing Officer's assessment would not require the finding that the process was
9251flawed. Under Liberty County, supra, the HRS assessment will be upheld even if
9264it may appear erroneous or if reasonable people may disagree with the agency.
9277The Exceptions to the Recommended Order
9283Both HRS and Unisys filed numerous exceptions to the recommended order
9294challenging the findings of fact and the conclusions of law drawn by the Hearing
9308Officer. Findings of fact are cloaked with the presumption that they are
9320correct absent a demonstration from the record that they are not based on
9333substantial competent evidence. Tuveson v. Florida Governor's Council on Indian
9343Affairs, 495 So.2d 790 (Fla. 1st DCA 1986). Those exceptions respecting the
9355findings of fact found in the recommended order are hereby denied since the
9368record contains evidence from which the findings could be drawn. The exceptions
9380of the parties respecting the conclusions of law drawn by the hearing officer
9393are hereby granted upon the grounds stated more particularly within this final
9405order.
9406Unisys filed a Motion to Strike Petitioner's Memorandum of Law in Response
9418to Exceptions and its Proposed Final Order filed with the substitute Secretary
9430on June 12, 1995. That motion is denied. Petitioner's Memorandum was
9441considered in the determination made within this final order.
9450CONCLUSION
9451The Department adopts the findings of fact found in the Recommended Order
9463and rejects those conclusions of law which lead to the conclusion that the
9476Department illegally, fraudulently, dishonestly, or in an arbitrary and/or
9485capricious manner awarded Unisys the contract for RFP 95-142CM-FAP.
9494This order constitutes a final agency action. A party who is adversely
9506affected by this Final Order is entitled to judicial review which must be
9519instituted by filing one copy of a Notice of Appeal with the agency clerk of HRS
9535and a second copy along with a filing fee as prescribed by law with the District
9551Court of Appeal in the appellate district where the agency maintains its
9563headquarters or where a party resides. Review proceedings will be conducted in
9575accordance with the Florida appellate rule. The Notice of Appeal must be filed
9588within thirty (30) days of rendition of the order to be reviewed.
9600ADJUDGED, that the award to Unisys is affirmed.
9608DONE and ORDERED this 10th day of August, 1995, in Tallahassee, Florida.
9620_________________________
9621GREGORY C. SMITH
9624Substitute Secretary
9626Department of Health and
9630Rehabilitative Services
9632Filed with the Clerk of HRS on August 11, 1995.
9642ENDNOTES
96431/ The testimony of Dr. Elton Scott was provided on the issue of present value
9658analysis. Dr. Scott admitted that the present value calculation he provided was
9670based on his own assumptions and that the present value analysis run by HRS was
9685based on its assumptions.
96892/ The hearing officer concluded, as a factual determination, that the expert's
9701present value analysis was the better reasoned approach. That finding of fact
9713has been accepted, as have all the factual determinations found in the
9725recommended order. However, as will be demonstrated, the legal conclusion that
9736the Hearing Officer may substitute his evaluation for that of the agency head,
9749is rejected.
9751COPIES FURNISHED:
9753William E. Williams, Esquire
9757Rex D. Ware, Esquire
9761Huey, Guilday & Tucker, P.A.
9766106 East College Avenue, Suite 900
9772Tallahassee, Florida 32301
9775William A. Frieder, Esquire
9779Assistant General Counsel
9782Department of HRS
9785Building E, Suite 200
97891323 Winewood Blvd.
9792Tallahassee, Florida 32399-0700
9795W. Robert Vezina, 111, Esquire
9800Mary M. Piccard, Esquire
9804Cummings, Lawrence & Vezina, P.A.
98091004 DeSoto Park Drive
9813P. O. Box 589
9817Tallahassee, Florida 32302-0589
9820Steven A. Blaske, Esquire
9824Unisys Corporation
98264151 Ashford Dunwoody Road
9830Atlanta, GA 30319
9833Hearing Officer Don W. Davis
9838Division of Administrative Hearings
9842The DeSoto Building
98451230 Apalachee Parkway
9848Tallahassee, Florida 32399-1550
9851CERTIFICATE OF SERVICE
9854I HEREBY CERTIFY that a true copy of the foregoing FINAL ORDER has been
9868furnished to each of the above-named persons by U.S. Mail or hand delivery this
988211 day of August, 1995.
9887________________________________
9888ROBERT L. POWELL, SR.
9892Agency Clerk
9894Department of Health and
9898Rehabilitative Services
9900Building E, Suite 200
99041323 Winewood Blvd.
9907Tallahassee, Florida 32399-0700
9910(904) 488-2381
9912FAX: (904) 922-3947
- Date
- Proceedings
- Date: 08/23/1995
- Proceedings: Replacement page (1) of Final Order previously filed filed.
- Date: 08/11/1995
- Proceedings: Final Order filed.
- PDF:
- Date: 05/12/1995
- Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held March 9 and 10, 1995.
- Date: 04/27/1995
- Proceedings: Proposed Recommended Order (ON Disk from Bill Williams) filed.
- Date: 04/20/1995
- Proceedings: (Intervenor) Notice of Filing Proposed Recommended Order (For HO Signature); Unisys Corporation`s Recommended Order Disk ; Respondent`s Proposed Findings of Fact and Conclusions of Law; Respondent`s Proposed Recommended Order Disk filed.
- Date: 04/20/1995
- Proceedings: Petitioner`s Proposed Recommended Order W/tagged attachments; Cover Letter filed.
- Date: 04/10/1995
- Proceedings: Transcript (4 volumes, tagged) filed.
- Date: 03/13/1995
- Proceedings: Unisys`s notice of filing Deposition Transcripts; Deposition of William Brattain; Deposition of Victor Kumar; Deposition of Elijah Williams; Deposition of Shelia Williams filed.
- Date: 03/09/1995
- Proceedings: CASE STATUS: Hearing Held.
- Date: 03/08/1995
- Proceedings: Unisys`s Notice of Serving an Amended Answer to Petitioner`s First Interrogatories filed.
- Date: 03/08/1995
- Proceedings: (8) Subpoena Duces Tecum; (8) Affidavit filed.
- Date: 03/06/1995
- Proceedings: Petitioner`s Motion to Compel filed.
- Date: 03/03/1995
- Proceedings: Order Continuing Final Hearing to Date Certain sent out. (hearing rescheduled for 3/9/95; 9:30am)
- Date: 03/01/1995
- Proceedings: Petitioner`s Response to Unisys Corporation`s First Request for Production of Documents filed.
- Date: 03/01/1995
- Proceedings: Unisys Corporation`s Response to First Request for Production of Documents By Deloitte & Touche Lip; Unisys Corporation`s Notice of Serving Answers to First Interrogatories of Deloitte & Touche Lip; Petitioner`s First Set of Interrogatories to Intervenor;
- Date: 03/01/1995
- Proceedings: Notice of taking depositions duces tecum filed.
- Date: 02/28/1995
- Proceedings: Petitioner`s notice of serving answers to Respondent`s first set of interrogatories filed.
- Date: 02/24/1995
- Proceedings: Petitioner`s First Request for Production of Documents to Intervenor, Unisys Corporation; Notice of Serving Interrogatories; Petitioner`s First Request for Production of Documents to Respondent, Department of Health And Rehabilitative Service filed.
- Date: 02/24/1995
- Proceedings: (Respondent) Notice of Propounding Interrogatories; Respondent`s First Interrogatories to Petitioner filed.
- Date: 02/24/1995
- Proceedings: Notice of taking Deloitte & Touche LLP Corporate deposition filed.
- Date: 02/23/1995
- Proceedings: Order Granting Petition to Intervene sent out. (by: Unisys Corp)
- Date: 02/22/1995
- Proceedings: Notice of Hearing sent out. (hearing set for 3/6/95; 9:30am; Talla)
- Date: 02/22/1995
- Proceedings: Prehearing Order sent out.
- Date: 02/21/1995
- Proceedings: Notice; Formal Written Protest and Petition for Formal Administrative Proceeding (& exhibit A-D) & Cover Letter From W. Williams; Petition to Intervene by Unisys filed.