97-001682
Collier Cattle Corporation And Tropical Ranch Properties, Inc. vs.
South Florida Water Management District And Department Of Environmental Protection
Status: Closed
Recommended Order on Thursday, June 25, 1998.
Recommended Order on Thursday, June 25, 1998.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8COLLIER CATTLE CORPORATION, and )
13TROPICAL RANCH PROPERTIES, INC., )
18)
19Petitioners, )
21)
22and )
24)
25WALTER R. SHAW, SR., )
30)
31Intervenor, )
33vs. ) Case No. 97-1682
38)
39SOUTH FLORIDA WATER MANAGEMENT )
44DISTRICT and DEPARTMENT OF )
49ENVIRONMENTAL PROTECTION, )
52)
53Respondents. )
55___________________________________)
56RECOMMENDED ORDER
58Robert E. Meale, Administrative Law Judge of the Division
67of Administrative Hearings, conducted the final hearing in
75Naples, Florida, on August 12, 13, 28, and 29, October 1, 2,
878, and 9, November 13, 14, 17, 18, and 19, 1997, and
99January 6, 7, and 8, 1998.
105APPEARANCES
106For Petitioners: James W. McDonald, Jr.
112McDonald & Associates
115Co mmunity Plaza, Suite 306
12015600 Southwest 288th Street
124Homestead, Florida 33030
127A. Glenn Simpson
130Qualified Representative
1325961 22d Avenue Southwest
136Naples, Florida 34116
139For Respondent South Florida Water Management District:
146Marcy I. LaHart
149Associate Attorney
151South Florida Water Management District
1563301 Gun Club Road
160West Palm Beach, Flo rida 33416-4680
166For Respondent Department of Environmental Protection:
172Francine M. Ffolkes
175Assistant General Counsel
178Department of Environmental Protection
182Mail Station 35
1853900 Commonwealth Boulevard
188Tallahassee, Florida 32399-3000
191For Intervenor Walter R. Shaw, Sr.:
197Walter R. Shaw, Sr., pro se
2031400 Northwest 62nd Avenue
207Sunrise, Florida 33313-6138
210For Intervenor Clifford L. Fort:
215Cliffort L. Fort
2188410 Northwest 16th Street
222Pembroke Pines, Florida 33024
226STATEMENT OF THE ISSUE
230The issue is whether Respondent South Florida Water
238Management District is entitled to an environmental resource
246permit from Respondent Department of Environmental Protection
253to construct a weir in Collier County on the Merritt Canal
264about 3600 feet south of Interstate 75 for the purpose of
275extending the hydroperiod on the Florida Panther Federal
283Wildlife Refuge.
285PRELIMINARY STATEMENT
287Respondent South Florida Water Management District
293applied to Respondent Department of Environmental Protection
300for an environmental resource permit to construct a weir in
310the Merritt Canal to be operated by the water management
320district. On January 29, 1997, Respondent Department of
328Environmental Protection issued a Notice of Intent to Issue
337with several general and specific conditions. During the
345hearing, the department attached new monitoring conditions to
353the draft permit.
356Petitioners timely challenged the intended agency action
363and demanded a formal hearing. The administrative law judge
372granted the petitions to intervene of both Intervenors.
380The court reporter filed the final portion of the
389transcript on February 2, 1998.
394The administrative law judge specifically finds that,
401based on his presentation of Petitioners' case, Mr. Simpson is
411a qualified representative for the purpose of representing
419other parties in administrative hearings before the Division
427of Administrative Hearings. The administrative law judge
434denies Mr. Shaw's post-hearing request for summary relief.
442FINDINGS OF FACT
445I. Proposed Permit
4481. On April 17, 1996, Respondent South Florida Water
457Management District (District) filed with Respondent
463Department of Environmental Protection (DEP) an application
470for the construction of a water-control structure in the
479Merritt Canal. The stated purpose of the structure, which is
489a weir, is to extend the hydroperiod of the Lucky Lake Strand.
5012. The application states that the District is the owner
511of a drainage easement covering the land proposed as the site
522of the weir. According to the application, Collier County, in
532which the Merritt Canal lies, originally held the drainage
541easement. The District later adopted the Merritt Canal as a
"551Works of the District," which transferred operational
558responsibility for the canal from the County to the District.
568(A sub-unit of the District, the Big Cypress Basin Board has
579jurisdiction for District projects of the type involved in
588this case. References to the District shall include the Big
598Cypress Basin Board.)
6013. The application requests a permit to construct an
610adjustable sheet-pile weir within the 80-foot Merritt Canal
618right-of-way. The application accurately describes the
624Merritt Canal as a Class III waterbody that is not an
635Outstanding Florida Water.
6384. By Notice of Intent to Issue Environmental Resource
647Permit dated January 29, 1997 (NOI), DEP proposed to issue an
658environmental resource permit (ERP) to the District for the
667construction of the Lucky Lake Strand Water Control Structure.
676The structure would be an adjustable weir with operating
685levels of 7.0 feet National Geodetic Vertical Datum (NGVD) in
695the wet season and 9.5 feet NGVD in the dry season.
7065. As stated in the NOI, the Merritt Canal is 12 miles
718long and one of four main north-south canals within a larger
729system of 183 miles of canals--all Class III waters--
738constructed in the 1960s by Gulf American Land Corporation to
748drain wetlands for development of the Southern Golden Gate
757Estates area. These four north-south canals drain water south
766through the Faka Union Canal and into Faka Union Bay, which is
778part of the 10,000 Islands/Cape Romano Aquatic Preserve. The
788preserve contains Class II Outstanding Florida Waters.
7956. The NOI notes that the U.S. Fish and Wildlife Service
806(FWS) and District entered into an agreement in September 1994
816to construct two weirs in the Merritt Canal "to partially
826restore historic hydroperiods into two major wetland features
834within the federally owned lands of the USFWS Florida Panther
844National Wildlife Refuge, Lucky Lake Strand and Stumpy Strand
853(Class III Outstanding Florida Waters)." As stated in the
862NOI, these federally owned wetlands constitute over 3000 acres
871of cypress and mixed swamps, wet prairies, marshes, and ponds.
8817. The NOI relates that FWS staff proposed the project
891to counteract "subtle vegetational changes and accelerated
898pond draw-downs [that] were taking place in the strands as a
909result of shortened hydroperiods caused by a three-year
917drought, I-75 widening activities, and subsequent canal
924modifications."
9258. The NOI correctly states that water in the wet season
936historically flowed southerly through Stumpy Strand, Lucky
943Lake Strand, and Picayune Strand, before entering the larger
952Fakahatchee Strand. Lucky Lake Strand narrows to 1000 feet at
962its south end, which is at Interstate 75 (I-75).
9719. The NOI accurately asserts that the construction of
980the Merritt Canal and the I-75 borrow canals combined to draw
991down the upstream wetlands, thus reducing their hydroperiods.
999The effect of the Merritt Canal is reportedly significant
1008because of its confluence with the southern tip of Lucky Lake
1019Strand.
102010. The NOI discloses that the original agreement
1028between the District and FWS called for the construction of
1038two weirs south of I-75, one at the headwaters of the Merritt
1050Canal and another about 1800 feet downstream in the Merritt
1060Canal. However, the proposed permit eliminates one weir,
1068whose function was performed by plugs in the north I-75 borrow
1079canal, and relocates the remaining proposed weir about 3600
1088feet south of I-75, rather than immediately south of I-75,
1098reportedly because of difficulties in accessing the proposed
1106weir at I-75.
110911. The NOI states that the Merritt Canal is within the
112080-foot drainage easement originally acquired by Collier
1127County. The uplands adjacent to the weir are reportedly owned
1137by DEP.
113912. The NOI describes the proposed weir as a sheet pile
1150weir with adjustable partitions. As proposed, during the wet
1159season, the District would start to open the gates at 7 feet
1171NGVD and start to close them at 6.5 feet NGVD. During the dry
1184season, the District would start to open the gates at 9.8 feet
1196NGVD and start to close them at 9.3 feet NGVD. Also, the
1208proposed permit would anticipate that the District would
1216dredge the canal to a trapezoidal cross-section having a
1225bottom elevation of -1.5 feet NGVD and a width of about 49
1237feet at the weir and transitioning to 20-foot bottom widths
1247upstream and downstream of the weir.
125313. According to the NOI, the purpose of the proposed
1263weir is
1265to reduce over-drainage of the upstream
1271wetlands in Lucky Lake and Stumpy Strands
1278by extending the hydroperiod further into
1284the dry season. No increase in water
1291levels during the wet season is expected.
1298Although the historic extended hydroperiod
1303is not expected to be achieved, the weir
1311structure is expected to improve current
1317conditions to the upstream wetlands.
1322Holding back water in these wetlands [is]
1329also expected to improve water quality
1335downstream by removal of excess nutrient,
1341sediments, and chemicals. Wildlife values
1346are expected to be enhanced in preferred
1353waterfowl and wading bird habitat,
1358including areas for the endangered wood
1364stork and threatened bald eagle. Forage
1370areas are also expected to be improved for
1378white-tailed deer and other wildlife
1383species which are essential prey for the
1390endangered Florida panther. Aquifer
1394recharge is also expected as the ground
1401water reserves will be raised by raising
1408the canal water levels, while maintaining
1414the existing level of flood protection for
1421adjacent private landowners.
142414. The NOI states that FWS will monitor post-
1433construction environmental conditions and will recommend to
1440the District adjustments to the weir elevations. The NOI
1449reports that the District will be the "main operator" of the
1460weir to adjust elevations to maintain flood control for
1469adjacent lands. The NOI adds:
1474The project was designed so as not to
1482decrease the peak discharge capacity in
1488the canal or increase flood stages in the
1496Upper Merritt Canal watershed. Hydraulic
1501modeling by the District indicates that
1507there will be no additional surface water
1514flooding to private property as a result
1521of the project, and the current level of
1529service will be maintained.
153315. Based on this analysis, the NOI concludes that the
1543District has provided reasonable assurance that the proposed
1551activity will comply with Part IV, Chapter 373, Florida
1560Statutes, and the underlying rules, including Chapter 62-330
1568and Rules 40E-4.301 and 40E-4.302, Florida Administrative
1575Code. The NOI states that the District has demonstrated that
1585the activity is clearly in the public interest, pursuant to
1595Section 373.414(1)(a), Florida Statutes.
159916. The proposed permit conforms to the NOI's
1607description. Specific Condition 13 sets the fixed crest of
1616the proposed weir at 4.5 feet NGVD and the width of the weir
1629at 48 feet.
163217. Although the proposed permit is nowhere explicitly
1640conditioned on a successful wetland enhancement project,
1647Specific Condition 12 states that "the" wetland enhancement
1655project shall be considered successful if, after five years,
1664Lucky Lake Strand and Stumpy Strand display wetland-
1672appropriate vegetation and the "viability of adjacent upland
1680sites [is] not negatively impacted by increased ground water
1689or surface water levels resulting from the authorized
1697project."
169818. Specific Condition 17 requires the District to
1706document the operation of the gates and notify DEP, within
1716three days, whenever any of the permitted elevations are
1725exceeded. Annually, the District must supply DEP detailed
1733data and analysis of the operational history of the weir,
1743including "reasons for going to nonstandard operation and a
1752narrative description of the effectiveness of initiating the
1760nonstandard operation to include areas not flooded (or
1768flooded, if applicable) and other associated impacts."
177519. During the final hearing, the District proposed, and
1784DEP approved, a modification of Specific Condition 18. As
1793modified, Specific Condition 18 requires the District to
"1801monitor the effects of the operation" of the weir, pursuant
1811to the revised monitoring plan incorporated by reference into
1820this condition.
182220. The revised monitoring plan, which is dated
1830November 12, 1997, alters the original monitoring plan by
1839adding two sites for the installation of water-table wells.
1848One of the new sites (Site A) is 1200 feet north of the weir,
1862and the other new site (Site B) is 1200 feet north and 2000
1875feet west of the weir. These are the only water-table
1885monitoring devices.
188721. Five other sites are surface-water monitoring sites.
1895Three of the these sites are in the Merritt Canal: one
1906immediately upstream of the weir, one immediately downstream
1914of the weir, and one farther upstream at I-75. The other two
1926surface-water monitoring sites are farther upstream. One is
1934in Lucky Lake about 1.75 miles north of the weir, and the
1946other is about three miles northeast of Lucky Lake.
195522. Three other sites are rainfall-monitoring sites.
1962Two rainfall-monitoring sites are north of the weir. The site
1972just north of I-75 is at the Ford Motor Company test track,
1984which is immediately west of Lucky Lake and Stumpy Strands,
1994and the site more directly north of the Merritt Canal is about
2006ten miles north of I-75.
201123. Specific Condition 18 states the frequency with
2019which someone (presumably a District employee or contractor)
2027is to collect the data from these 10 monitoring sites, but
2038contains no performance criteria. The monitoring plan thus
2046commits the District to collecting data, but not to analyzing
2056the data, nor, more importantly, taking specified actions when
2065certain performance parameters are exceeded.
207024. Neither the revised monitoring plan nor the
2078application in any way commits the District to using the data
2089collected from the revised monitoring plan to develop a set of
2100criteria, based on rainfall amounts, groundwater levels, and
2108surface water levels, to fine-tune the operation of the gates
2118so as not to exacerbate present flooding. Nothing in the
2128revised monitoring plan or the application suggests that the
2137District will use the data collected from the revised
2146monitoring plan to identify more clearly the relationships
2154between storm events and water levels to understand better the
2164relationship between flooding, on the one hand, and the
2173existence of the proposed weir and the operation of its gates.
2184II. Faka Union Canal Watershed and
2190Southern Golden Gate Estates
219425. What is now known as the Faka Union Canal Watershed
2205historically covered about 234 square miles. It ran from an
2215area about four miles north of what is now known as Immokalee
2227Road south in a widening expanse that approached 12 miles at
2238what is now U.S. Route 41. It then ran south until it emptied
2251into the Gulf of Mexico at Faka Union Bay in what is now the
2265Cape Romano Ten Thousand Islands State Aquatic Preserve east
2274of Marco Island.
227726. Land alterations due to road and canal construction
2286and urban and agricultural development eventually reduced the
2294Faka Union Canal Watershed to about 189 square miles. Most
2304noticeably, these changes narrowed the drainage area at U. S.
2314Route 41 from almost 12 miles to little more than the width of
2327the Faka Union Canal.
233127. The Faka Union Canal Watershed is characterized by
2340low relief and poorly defined drainage patterns. At the north
2350boundary of the watershed, which now ends at Immokalee Road,
2360the elevation reaches 24 feet NGVD. Twenty-eight miles to the
2370south, at the outlet of the basin, the elevation is two feet
2382NGVD. The water flows generally in a southwest direction.
239128. Historically, water ran slowly through the watershed
2399in sheetflow several miles wide and a few inches to a few feet
2412deep. Drainage concentrated in slightly lower sloughs and
2420strands, which generally dried out in the dry season.
2429Historically, the watershed featured flat, swampy lands
2436containing cypress trees, islands of pine forests, and wet and
2446dry prairies. Prior to development, much of the watershed
2455remained inundated by several feet of water during the five-
2465month wet season (roughly from mid-May through mid-October).
2473In this undisturbed state, the prominent features of the
2482watershed were the storage of runoff in depressional areas,
2491attenuated peak flows, and a longer hydroperiod into the dry
2501season.
250229. In the early 1960s, Gulf American Land Corporation
2511subdivided a 173 square-mile area in Collier County into many
2521thousands of lots as small as 1.25 acres. The development was
2532Golden Gate Estates. The portion of Golden Gate Estates south
2542of I-75 is known as Southern Golden Gate Estates. Golden Gate
2553Estates is west of the Merritt Canal.
256030. Gulf American's purpose in dredging the 183-mile
2568canal system was to allow it to market as land, available for
2580continuous occupation, subdivided lots superimposed over an
2587area that was land during the dry months and water during the
2599wet months. To achieve this objective, Gulf American Land
2608Corporation constructed one group of canals that drains to the
2618west and another group of canals drains to the south into the
2630Faka Union Canal. Gulf American dredged the canals draining
2639to the south, which form the Faka Union Canal System, from
26501968 through 1971.
265331. Four north-south canals spaced two miles apart drain
2662Southern Golden Gate Estates and the portion of the Faka Union
2673Canal Watershed north of I-75. From west to east, the canals
2684are the Miller Canal, Faka Union Canal, Merritt Canal, and
2694Prairie Canal. Only the two westerly canals run north of
2704I -75. The Miller Canal extends almost seven miles north of
2715I -75, and the Faka Union Canal extends about 14 miles north of
2728I-75. The Merritt Canal starts in the immediate vicinity of
2738I-75, and the Prairie Canal starts about two miles south of
2749I -75.
275132. The average excavated depth of the four canals is
2761about ten feet from the top of the bank to the bottom of the
2775channel. Given the relatively close proximity of the water
2784table to the surface in this area, excavation to these depths
2795thus established a direct hydraulic connection with the
2803surficial aquifer. The canals are large, ranging from 45 to
2813over 200 feet wide.
281733. Although unable to convey without flooding the water
2826from even a ten-year storm event, which is the level of
2837service standard set by Collier County for Southern Golden
2846Gate Estates, the Faka Union Canal system has nonetheless
2855severely impacted the water resources of Collier County.
2863According to the Hydrologic Restoration of Southern Golden
2871Gate Estates, prepared in February 1996 by the Big Cypress
2881Basin Board (Southern Golden Gate Estates Restoration Plan):
2889. . . Construction of the canals has led
2898to both increased volumes and rates of
2905runoff from the watershed which has had
2912lasting effects on the area's water
2918supply, vegetation, wildlife, and coastal
2923estuaries.
2924The canals intercept large volumes of
2930surface and subsurface flow and quickly
2936divert them to the Faka Union Bay and the
2945Ten Thousand Island Estuary of the Gulf of
2953Mexico resulting in less surface water
2959available for storage. Since groundwater
2964recharge is achieved primarily through
2969infiltration from surface detention
2973storage, reduced groundwater recharge
2977threatens both groundwater supply for the
2983region and the natural barrier to salt
2990water intrusion. Continued overdrainage
2994has caused an eventual lowering of the
3001groundwater table. This has caused
3006vegetation to change from wetland dominant
3012to transitional and upland systems with
3018invasive exotic species. The extreme dry
3024conditions caused by overdrainage have
3029resulted in more frequent and more intense
3036wildfires with a greater destructive
3041impact on vegetation.
3044The increased runoff rate has had severe
3051effects on the receiving estuaries.
3056Historically, the estuaries would receive
3061broad, slow moving sheets of water that
3068were capable of carrying essential
3073nutrients but not high sediment loads.
3079This has been replaced with point loads of
3087freshwater at the Faka Union Canal outlet
3094that push salinity levels down and result
3101in freshwater discharge shocks throughout
3106the Ten Thousand Island Estuary. The
3112increased runoff rate drains the area
3118quickly and does not allow the
3124hydroperiods necessary to sustain wetland
3129vegetation. . . .
3133Southern Golden Gate Estates Restoration Plan, pages
31408-9.
314134. The major roadway affecting the Faka Union Canal
3150Watershed is State Road 84, which was a two-lane road
3160constructed in 1966. In 1990, construction was completed
3168transforming State Road 84 into four-lane I-75. These road
3177projects have hastened drainage of the lands to the north of
3188I-75 and east of the Faka Union Canal.
319635. The land north of the Merritt Canal is largely
3206undeveloped. If one were to extend the Merritt Canal due
3216north of I-75, it would run through the middle of Lucky Lake
3228Strand and much of Stumpy Strand, which is immediately to the
3239north of Lucky Lake Strand. Agricultural land owned by
3248Collier Enterprises is just north of the Ford Motor Company
3258test track and immediately west of Lucky Lake Strand.
3267Agricultural land owned by Baron Collier Company is
3275immediately north of Stumpy Strand.
328036. This imaginary extension of Merritt Canal would mark
3289the west boundary of the Florida Panther National Wildlife
3298Refuge, which was established in June 1989. The Florida
3307Panther National Wildlife Refuge constitutes 26,000 relatively
3315undisturbed acres immediately north of I-75. Intervenor
3322Clifford Fort owns property south of the refuge on the south
3333side of I-75.
333637. The Florida Panther National Wildlife Refuge
3343features mostly wetlands, oak hammocks, pine flatwoods, and
3351prairies. The refuge receives runoff from stormwater and
3359possibly agricultural pumping of the water table from the
3368adjacent farmland. In addition to draining into the
3376headwaters of the Merritt Canal near the southwest corner of
3386the refuge, the refuge also drains into the northerly borrow
3396canal running along the north side of I-75. In the vicinity
3407of the Merritt Canal, the four borrow canals running along the
3418north and south sides of I-75, on both sides of the Merritt
3430Canal, drain in the direction of the Merritt Canal.
343938. Listed species using the Florida Panther National
3447Wildlife Refuge include the Florida panther, Florida black
3455bear, wood stork, roseate spoonbill, limpkin, and Eastern
3463Indigo snake. In October 1995, an inordinate amount of rain
3473fell in the area. Attracted by the increased water depths,
3483which more closely approximated historic conditions, 75 wood
3491storks nested in the Lucky Lake Strand; in drier years, wood
3502storks do not nest in the strand.
350939. Lucky Lake Strand occupies the southwest corner of
3518the Florida Panther National Wildlife Refuge. Lucky Lake and
3527two other ponds are present in this area. When full, Lucky
3538Lake and one of the ponds are about 50 meters wide, and the
3551third pond is about half of this width. During the dry
3562season, a person can throw a stone across any of the ponds.
357440. Historically, Lucky Lake and Stumpy strands passed
3582surface water into the Picayune Strand, which is west of the
3593Merritt Canal and south of I-75, from which the water ran into
3605the Fakahatchee Strand. Lucky Lake Strand presently narrows
3613to about 1000 feet at I-75.
361941. The hydrologic connection between the outlet of
3627Lucky Lake Strand and the headwaters of the Merritt Canal has
3638contributed significantly to the overdrainage of these two
3646strands, which occupy a significant area within the federal
3655refuge. The FWS wildlife biologist stationed at the Florida
3664Panther National Wildlife Refuge reported in a habitat
3672assessment report prepared in August 1996 that four ponds in
3682the strand dried out by December so that they could not
3693sustain fish or provide feeding habitat for birds.
3701III. Permitting Criteria
3704A. Public Health, Safety, or Welfare or Others' Property
371342. One of the main disputes between the parties is the
3724affect of the proposed weir on flooding. This case is largely
3735about flooding or, more generally, the amount of water to be
3746stored for a specified period of time. Petitioners and
3755Intervenors fear that the District's effort will cause
3763flooding to areas south of I-75 and east and west of the
3775Merritt Canal.
377743. Occupying property within a vast area whose natural
3786drainage patterns have been greatly disrupted, Petitioners and
3794Intervenors justifiably fear the ravages of flood and fire.
3803Although this area was undoubtedly subject to these hazards
3812prior to man's alteration of the natural landscape, large-
3821scale alterations to natural drainage in Southwest Florida
3829have artificially heightened the risk presented by these
3837natural hazards.
383944. Destructive flooding follows the inhabitation of
3846areas historically devoted to the storage of considerable
3854volumes of water; the flooding is exacerbated where, as here,
3864natural drainage features have been replaced by artificial
3872facilities that are inadequate for both the natural flows and
3882the new, artificial flows generated by development. Although
3890inadequate for the natural and artificial flows generated by
3899even design storm events, the artificial drainage facilities
3907nevertheless change historic drainage rates, accelerating the
3914rate and volume of natural drainage and shortening the
3923hydroperiod. In this manner, the artificial drainage
3930facilities contribute to the desiccation of previously
3937saturated soils and foster conditions suitable for dangerous
3945fires.
394645. Initially, Petitioners and Intervenors contend that
3953the District seeks approval of the proposed weir as an
3963indirect means of implementing the Southern Golden Gate
3971Estates Rehydration Plan. Little evidence supports this
3978concern.
397946. The Southern Golden Gate Estates Rehydration Plan
3987outlines several alternatives for the proposed rehydration of
3995Southern Golden Gate Estates. The preferred alternative does
4003not call for a weir at the proposed location. The purpose of
4015the proposed weir is to rehydrate an area north of the
4026Southern Golden Gate Estates. As discussed below, the role of
4036the proposed weir in rehydrating Southern Golden Gate Estates
4045appears insubstantial to the point of nonexistent.
405247. Focusing on the location of the proposed weir over
4062half of a mile downstream from the southernmost part of the
4073area intended to be rehydrated, Petitioners and Intervenors
4081dispute the stated purpose of the project, focusing on the
4091District's earlier relocation of the proposed weir from
4099positions just north and then just south of I-75 to its
4110present position a half-mile farther to the south.
411848. The District did nothing to allay this concern of
4128Petitioners and Intervenors when its employees could not
4136provide a reasonably detailed explanation of the process by
4145which someone moved the proposed site to the south. From the
4156District's evidence, one would infer that the decision to
4165relocate the proposed weir to the south spontaneously emerged,
4174without human sponsor, in the course of bureaucratic
4182decisionmaking.
418349. The District asserted that the northerly sites were
4192impractical due to access problems. However, the District
4200made little, if any, real effort to see if the Department of
4212Transportation would allow access to these more northerly
4220sites--one of which the District might be able to access
4230without the consent of the Department of Transportation.
423850. The record does not reveal why the District
4247relocated the proposed weir to its present location,
4255considerably south of its initial two locations at I-75.
4264Again, though, the evidence does not support the contention of
4274Petitioners and Intervenors that the relocation decision was
4282part of a private plan among District employees to incorporate
4292the proposed weir as part of a more ambitious project to
4303rehydrate Southern Golden Gate Estates.
430851. Nor does the evidence establish, as Petitioners and
4317Intervenors contend, that the relocation decision was driven
4325by the concerns of three influential landholders to the north
4335of I-75--Collier Enterprises, Barron Collier Company, and Ford
4343Motor Company. These three landholders approved the proposed
4351weir in its present location over a half-mile to the south of
4363its original locations and may have expressed concern that the
4373original locations at I-75 would unreasonably raise the risk
4382of flooding their land and business and agricultural
4390activities to the north of I-75.
439652. If the District's real reason for relocating the
4405proposed weir was due to objections from these landowners to
4415the north of I-75, this reason would not itself help
4425Petitioners and Intervenors. If the District acceded to the
4434demands of these landowners to the north, it does not
4444necessarily follow that the District lacked confidence in its
4453flood calculations. A relocation decision under these
4460circumstances would have as likely reflected political, as
4468scientific, concerns.
447053. Additionally, if the District moved the proposed
4478weir at the insistence or suggestion of the landowners to the
4489north, any flooding concerns voiced by these landowners raise
4498different issues from the flooding concerns raised by
4506Petitioners and Intervenors. Owners of land immediately to
4514the north and west of the federal refuge are more directly
4525within the area of the intended effects than are Petitioners
4535and Intervenors.
453754. More substantially, Petitioners and Intervenors
4543claim that the proposed activity is so negligently designed or
4553will be so negligently operated as to result in heightened and
4564more frequent flooding of areas to the west and east of the
4576proposed weir.
457855. The District's record in operating weirs in Collier
4587County is not flawless. In recent years, the District
4596constructed and maintained a weir with unlawfully high gates
4605and did not correct the noncompliant water-control structure
4613for several months after first learning of the violation.
4622However, this appears to have been an isolated violation.
463156. The division of responsibility between the District
4639and Collier County for the maintenance of drainage canals is
4649based on whether the canal is a primary or secondary drainage
4660facility. The District has assumed responsibility for all of
4669the primary drainage facilities in Collier County.
4676Surprisingly, though, the record reveals no master map or
4685index of the primary drainage facilities and at least the
4695larger nonprimary drainage facilities.
469957. However, Petitioners and Intervenors failed to show
4707that any confusion concerning maintenance responsibilities
4713that may exist between the District and Collier County would
4723appreciably raise the probabilities that the District would
4731operate the proposed weir in such a way as to exacerbate
4742present flooding concerns. The District and Collier County
4750agree that the District has jurisdiction over the Merritt
4759Canal. Petitioners and Intervenors have also failed to show
4768that any confusion concerning secondary-drainage contributions
4774that may exist between the District and Collier County would
4784have a substantial impact on the successful operation of the
4794proposed weir.
479658. The most significant claim raised by Petitioners and
4805Intervenors asserts that the District failed to provide
4813reasonable assurance that the proposed weir would not
4821exacerbate flooding. Although the weir gates would be closed
4830only during the dry season, the proposed activity requires
4839analysis of the risk of heightened water elevations upstream
4848of the proposed weir. In theory, flooding could result from
4858the effects of the weir even when the gates are open, as well
4871as the possibility of an extreme storm event during the dry
4882season.
488359. Expert witnesses on both sides clashed over whether
4892the design of the proposed weir was sufficient not to
4902exacerbate existing levels, rates, and frequencies of flooding
4910of adjacent uplands. The crucial feature over which the
4919experts disagreed was the spoil banks running along the canal.
492960. When the Merritt Canal was constructed, the spoil
4938was dumped along the banks. In the ensuing years, vegetation
4948colonized and stabilized the spoil banks, which now function
4957as levees.
495961. The expert witness called by Petitioners and
4967Intervenors disregarded the spoil banks in his calculations.
4975His lack of confidence in the opposing expert witness's use of
4986top-of-bank elevations was partly justified for the reasons
4994stated below. Although a minor point, part of the argument of
5005Petitioners and Intervenors' expert witness proved too much by
5014asserting that levees cannot maintain water levels higher
5022inside the levee than the existing ground elevation outside
5031the levee.
503362. On the other hand, in showing that the proposed weir
5044would not exacerbate flooding, the District's expert witness
5052relied, not entirely justifiably, on the top-of-bank
5059elevations. The District took only spot elevations of the
5068spoil bank and then assumed that these elevations prevailed
5077along the entire 3600 feet of canal upstream of the weir. The
5089District did not inspect the upstream banks for unpermitted
5098culverts, of which at least one was discovered during the
5108lengthy hearing in this case.
511363. There is a possibility of material differences in
5122elevations along the spoil banks. These spoil banks were not
5132constructed to a specified elevation; they were an excavation
5141byproduct that was haphazardly deposited beside the excavated
5149canal. Additionally, the record suggests that this general
5157area has been the site of unpermitted works, such as the
5168installation of a culvert and creation of unpermitted canal
5177plugs.
517864. In the months over which the hearing took place,
5188Petitioners and Intervenors alertly found a culvert breaching
5196the spoil bank upstream of the proposed weir. At least one of
5208their representatives demonstrated superior familiarity with
5214the spoil bank over the familiarity demonstrated by the
5223District's representatives. It is a fair inference that, if
5232the spoil bank was substantially missing at any point upstream
5242of the proposed weir, Petitioners and Intervenors would have
5251brought such evidence to the hearing. The absence of such
5261evidence, coupled with the reasonable inferences that may be
5270drawn from the concededly more cursory investigation of the
5279site by the District, precludes a finding that the spoil bank
5290is substantially missing at any material point so as to
5300warrant the use of ground elevations, as used by the expert
5311witness called by Petitioners and Intervenors. At best, from
5320the perspective of Petitioners and Intervenors, the record
5328supports the finding that the spoil banks may not be as
5339continuously as high as the District posits, but they are not
5350nearly as low (i.e., nonexistent) at any point as Petitioners
5360and Intervenors contend.
536365. The two experts also disagreed over two subordinate
5372inputs used in running the flood calculations. The expert
5381called by Petitioners and Intervenors claimed that initial
5389tailwaters (i.e., water elevations downstream of the weir) in
5398excess of 8.53 feet were appropriate. Although the canal has
5408experienced historically higher tailwaters than 8.53 feet, the
5416expert did not explain adequately why such higher tailwaters
5425should be used in running the model, especially since flood
5435calculations are not used to predict flooding conditions in
5444all storms, such as a 1000-year storm. Absent a showing that
5455tailwater in excess of 8.53 feet would be present at the
5466relevant time preceding or during the design storm event, the
5476expert called by Petitioners and Intervenors failed to show
5485why the District's tailwater input was unreasonable.
549266. On the other hand, the District's expert claimed
5501that the model required an adjustment to the friction factor
5511or Manning's N coefficient. This adjustment, which decreased
5519the friction factor by an order of magnitude, approximated a
5529bottom that was many times smoother than the actual bottom of
5540the Merritt Canal. The District's expert did not explain
5549adequately why the lower friction factor should be used in
5559running the model, and he frankly did not demonstrate the same
5570familiarity with this friction factor as did the expert called
5580by Petitioners and Intervenors. The most likely inference is
5589that the District's expert erred in making this adjustment.
559867. There was another controversy between the parties
5606regarding a subordinate input for the flooding calculations.
5614Petitioners and Intervenors raised the possibility that
5621agricultural discharges from the Collier properties adjacent
5628to the federal refuge, which the District ignored in its
5638calculations, might further undermine any assurances as to
5646flooding. This could have been useful information if
5654developed in the record, but the record permits no basis to
5665quantify the value of this additional discharge or ascertain
5674its timing relative to wet and dry seasons and storm events,
5685if in fact this agricultural discharge takes place at all.
5695Also, offsetting any such discharge would be two factors: the
5705District ran its calculations assuming a runoff rate 25
5714percent greater than that appropriately used by the Florida
5723Department of Transportation for modeling the design storm
5731event, and the District ignored the plugs in the I-75 borrow
5742canals, which attenuate the runoff into the Merritt Canal.
575168. Although Petitioners and Intervenors incorrectly
5757inputted ground elevation in place of the top-of-bank
5765elevation--when the best elevation is somewhere in between
5773these two values--their expert's calculations are useful for
5781illustrating a scenario that, for this reason, exceeds the
5790worst-case scenario. Again, this is an illustration of a
5799scenario that predicts greater flooding than reasonably should
5807be predicted because, in actuality, the restraining elevation
5815is higher than ground elevation.
582069. Using the 8.53-feet initial value for tailwater,
5828Petitioners' Exhibit 27 illustrates the different water
5835elevations resulting from running the model with and without
5844the excessive reduction of the friction factor. Petitioners
5852Exhibit 27 illustrates the effect of the design storm on
5862upstream water elevations with the gates open. Petitioners
5870Exhibit 27 ignores the spoil banks and instead uses prevailing
5880ground elevations.
588270. At the site of the proposed weir, the canal bottom
5893is at about -1.5 feet NGVD. The proposed weir would add fixed
5905barriers up to an elevation of 5.0 feet NGVD; the adjustable
5916gates would, when closed, extend the barrier from 5.0 feet
5926NGVD to 9.5 feet NGVD. Approximate existing ground elevation
5935averages about 10 feet NGVD downstream of I-75, with one dip
5946to below 9 feet NGVD about 600 feet downstream of I-75. For
5958about 6000 feet upstream of I-75, where there is no spoil bank
5970whatsoever, the average ground elevation, outside of the
5978slough, is about 13 feet. The slough bottom in this area
5989gently slopes from about 9 feet NGVD to 10 feet NGVD.
600071. Ignoring the spoil bank, Petitioners Exhibit 27
6008predicts flooding in two major areas in the design storm
6018event, even with the gates open. One of these is about 300
6030feet long, starting about 400 feet downstream of I -75. The
6041other is at least 300 feet long, starting near the northern
6052extreme of the modeled area and running off the modeled area.
6063The District did not survey in detail the spoil bank along the
6075300 feet downstream of I-75. There is no spoil bank upstream
6086of I-75 because there is no dredged canal.
609472. The water elevation about 400 feet downstream of
6103I -75 would be almost one foot greater than the ground
6114elevation. The water elevation about 6000 feet upstream of
6123I -75 will be as much as half of a foot greater than the ground
6138elevation. At the more downstream point, the actual water
6147elevation would exceed the District's projection by nearly
6155three-quarter of one foot. At the more upstream point, the
6165actual water elevation would exceed the District's projection
6173by over 1.5 feet.
617773. Although the record could have been better developed
6186on this important point, there is reasonable assurance that
6195the existing spoil-bank elevations are sufficient to contain
6203these flood elevations predicted by the expert called by
6212Petitioners and Intervenors.
621574. Petitioners and Intervenors claimed that the
6222District could achieve its stated purpose of extending the
6231hydroperiod in the Florida Panther National Wildlife Refuge
6239without increasing the risk or extent of flooding of adjacent
6249uplands. Petitioners and Intervenors suggested that the
6256District repair an existing plug in the Merritt Canal just
6266south of I-75. (This "plug" is actually the original ground
6276surface, which evidently was undisturbed during the
6283construction of I-75. Given the excavation of canals on both
6293sides of what is now a narrow strip of earth, the land
6305resembles a plug, and this recommended order refers to it as a
6317plug, although this term is descriptive only of the feature's
6327present appearance, not its method of creation.)
633475. There are actually six plugs--again, in the broad
6343sense of the word--in the vicinity of the junction of the
6354Merritt Canal and I-75. Two plugs interrupt the flow into the
6365Merritt Canal of the borrow canals to the north of I-75. Two
6377plugs likewise interrupt the flow into the Merritt Canal of
6387the borrow canals to the south of I-75. The last two plugs
6399are in the Merritt Canal, a few feet north and south of I-75.
641276. Repairing the plug immediately south of I-75 would
6421raise the water elevation by about 1.3 feet under the I-75
6432bridge. By about 2000 feet upstream of I-75, there is no
6443significant difference between the water elevation using the
6451model of Petitioners and Intervenors' expert for the proposed
6460weir 3600 feet downstream of I-75 and the water elevation for
6471the proposed plug repair just south of I-75. Repairing the
6481plugs would have reduced the water elevation downstream of I-
649175 by less than one half of a foot.
650077. Petitioners, Intervenors, and their expert have
6507proposed a promising alternative to the proposed weir. The
6516alternative appears to serve the stated purpose of the
6525proposed activity at least as well as the proposed weir would,
6536if not somewhat better due to its closer proximity to the
6547targeted federal refuge, and the alternative project would
6555cost much less to construct, maintain, and operate. The
6564restorative nature of the work would probably relieve the
6573District of the necessity of obtaining a permit. Perhaps the
6583prospect of such work might motivate other state and federal
6593agencies to grant the District access to the area at I-75 to
6605build the weir at one of its first two locations.
661578. However, the issue is whether the District has
6624provided reasonable assurance for the activity that it has
6633proposed. As to flooding, the District has provided
6641reasonable assurance that the proposed activity will not
6649exacerbate flooding during the design storm events or even
6658more severe storm events.
666279. Even assuming an absence of reasonable assurance as
6671to flooding, the first criterion requires consideration of
6679whether the proposed activity would adversely affect the
6687public health, safety, and welfare or the property of others.
6697Extending the hydroperiod of the federal refuge protects the
6706property of others by reducing the period of time that the
6717turf is dried out. This provides a wide range of
6727environmental protection, including protection against the
6733risk of fire caused by excessive drainage, for the federal
6743refuge and other property in the area.
675080. Retarding the artificially high rate of drainage
6758will improve water quality in at least two respects. The
6768proposed weir will retard and reduce the nutrients conveyed
6777down the canal and into the estuary into which it eventually
6788empties. The proposed weir will also tend to restore somewhat
6798the rate and timing of historic freshwater inputs on which the
6809viability of the estuary and its inhabitants depends.
6817Concerns about public health, safety, and welfare, as well as
6827the property of others, cannot be severed from these
6836broadscale environmental benefits to be derived from the
6844proposed activity. Public health concerns are tied to these
6853considerations.
685481. Thus, even if the District had failed to provide
6864reasonable assurance as to flooding alone, the District has
6873provided reasonable assurance that, on balance, the proposed
6881weir will not adversely affect the matters set forth in the
6892first criterion.
6894B. Conservation of Fish and Wildlife, Including
6901Endangered or Threatened Species, or Their Habitats
690882. The proposed weir will serve the conservation of a
6918wide range of flora and fauna, as well as their wetlands
6929habitat, within the targeted federal refuge. These species
6937include listed species. The evidence does not support a
6946finding that extending the hydroperiod of the federal refuge
6955would in any way disturb the Florida panther.
6963C. Navigation, Flow of Water, or Harmful Erosion
6971or Shoaling
697383. The proposed weir will have not adversely affect
6982navigation or the flow of water within the canal, and it will
6994not cause erosion or shoaling.
6999D. Fishing or Recreational Values or Marine
7006Productivity in the Vicinity of the Activity
701384. The proposed weir will not adversely affect fishing
7022or recreational values or marine productivity in the vicinity
7031of the proposed weir. To the contrary, the proposed weir will
7042enhance these values in the immediate vicinity of the proposed
7052weir and downstream at the estuary at the mouth of the Merritt
7064Canal.
7065E. Temporary or Permanent Nature
707085. The proposed weir will be of a permanent nature.
7080F. Significant Historic and Archaeological Resources
708686. The record provides no basis for a finding that the
7097proposed weir jeopardizes significant historic and
7103archaeological resources.
7105G. Current Condition and Relative Value of Functions
7113of Areas Affected by the Proposed Activity
712087. The federal refuge is functioning well
7127environmentally, despite the adverse impact of dramatic
7134disruptions of the natural drainage regime. The value of
7143these functions is high. Likewise, the receiving estuarine
7151waters are functioning well, despite the adverse impact of
7160dramatic disruptions of the natural drainage regime.
7167Extending the hydroperiod of the federal refuge will partially
7176offset these historic disruptions. Thus, the proposed weir
7184will assist in the functioning of natural systems that are now
7195functioning well, but could use some help.
7202H. Public Interest
720588. The proposed weir is not in an Outstanding Florida
7215Water. Thus, the question is whether the proposed activity is
7225not contrary to the public interest. The District has
7234provided reasonable assurances as to the preceding seven
7242criteria sufficient to demonstrate that, on balance, the
7250proposed activity is not contrary to the public interest.
7259I. Cumulative Impacts
726289. There is no evidence that the proposed weir will
7272cause any adverse cumulative impacts upon wetlands or surface
7281waters.
7282J. Other Criteria
728590. The District has proved that the proposed weir would
7295not violate any water quality standards. To the contrary, any
7305effect from the proposed activity would be to improve water
7315quality, especially downstream at the estuary. The
7322restoration of conditions more typical of historic drainage
7330would allow more nutrients to be captured upstream and would
7340tend to restore the historic timing and volume of freshwater
7350inputs into the estuary.
735491. For the reasons set forth above, the District has
7364also provided reasonable assurance that the proposed activity
7372meets the 11 criteria contained in Rule 40E-4.301, which
7381largely duplicate the seven criteria discussed above, and the
7390relevant provisions of the Basis of Review. It is true that
7401the monitoring provisions are largely illusory because they
7409provide no quantifiable parameter beyond which the District
7417must take specified action. In other words, at best, the
7427monitoring provisions assure that the District will collect
7435post-operational flooding data, but they do not promise that
7444the District will take any action if certain levels of
7454flooding take place. However, the monitoring provisions are
7462of little importance given the factual findings concerning
7470flooding, as discussed above, and the legal requirements of
7479the Basis of Review, as discussed below.
7486CONCLUSIONS OF LAW
748992. The Division of Administrative Hearings has
7496jurisdiction over the subject matter. Section 120.57(1),
7503Florida Statutes. (All references to Sections are to Florida
7512Statutes, except for references to Sections of the District's
7521Basis of Review (BOR). All references to Rules are to the
7532Florida Administrative Code.)
753593. Section 373.413(1) provides that the District or DEP
7544may require permits and impose "reasonable conditions" that
7552are "necessary to assure" that the construction or alteration
7561of any stormwater management system or dam, among other
7570activities, "will comply with the provisions of this part and
7580applicable rules . . . and will not be harmful to the water
7593resources of the district."
759794. Section 373.414(1) adds that the District or DEP
7606shall require an applicant to provide "reasonable assurance"
7614that the proposed activity will not violate state water
7623quality standards and is not "contrary to the public
7632interest." If the proposed activity "significantly degrades
7639or is within an Outstanding Florida Water," the applicant must
7649provide "reasonable assurance" that the proposed activity will
7657be "clearly in the public interest."
766395. Pursuant to Section 373.414(1)(a), the public-
7670interest determination requires the issuing agency to
"7677consider and balance" seven criteria:
76821. Whether the activity will adversely
7688affect the public health, safety, or
7694welfare or the property of others;
77002. Whether the activity will adversely
7706affect the conservation of fish and
7712wildlife, including endangered or
7716threatened species, or their habitats;
77213. Whether the activity will adversely
7727affect navigation or the flow of water or
7735cause harmful erosion or shoaling;
77404. Whether the activity will adversely
7746affect the fishing or recreational values
7752or marine productivity in the vicinity of
7759the activity;
77615. Whether the activity will be of
7768temporary or permanent nature;
77726. Whether the activity will adversely
7778affect or will enhance significant
7783historical and archaeological resources
7787under the provisions of s. 267.061; and
77947. The current condition and relative
7800value of functions being performed by
7806areas affected by the proposed activity.
781296. Section 373.414(1)(b) adds that, if an applicant is
7821unable to meet these seven criteria, then the District or DEP
7832shall consider mitigation measures. Section 373.414(8)
7838requires that the District or DEP "consider the cumulative
7847impacts upon surface water and wetlands" when deciding whether
7856to issue a permit. Rule 40E-4.302 restates the seven criteria
7866stated in Section 373.414(1)(a) and otherwise tracks the
7874statutory requirements.
787697. Rule 40E-4.301 identifies eleven criteria that
7883largely, if not entirely, overlap the seven criteria
7891identified in Section 373.414(1)(a) and Rule 40E-4.302. The
7899application and purpose of Rule 40E-4.301 are unclear. For
7908instance, in applying Rule 40E-4.301, it is unclear whether
7917the factfinder should balance the eleven criteria; unlike Rule
792640E-4.302 and Section 373.414(1)(a), Rule 40E-4.301 does not
7934expressly so provide. More importantly, if the two sets of
7944criteria are not wholly duplicative, the District's rules fail
7953to explain what happens when a proposed activity meets the
7963seven criteria identified in the statute and Rule 40E-4.302,
7972but fails to meet the eleven criteria identified in
7981Rule 40E -4.301.
798498. Rule 40E-4.302(3) incorporates the District's Basis
7991of Review in the determination whether an applicant has
8000provided the reasonable assurances required by Rules 40E-4.301
8008and 40E-4.302.
801099. In this case, the District is the applicant, not the
8021permitting agency; DEP is the permitting agency. In
8029Rules 62 -330.100(1) and 62-330.200(4), DEP adopts various
8037rules of the water management districts for the issuance of
8047ERPs, including the relevant rules already discussed. In
8055Rule 62 -330.200(4)(b), DEP adopted the District's Basis of
8064Review (BOR), except for Sections 1.0 through 3.1.2.9, 4.4,
8073and 4.5, and revised Section 4.2.2.
8079100. BOR Section 4.0 states that the District's
8087permitting goal is "no net loss in wetland and other surface
8098water functions." (Although a DEP rule converts all
8106references to the "District" to "DEP," this recommended order
8115retains the actual language of the BOR.) BOR Section 4.0
8125provides that the District requires permits so it can
"8134conserve the beneficial functions of . . . wetlands or other
8145surface waters."
8147101. BOR Subsection 4.2.1 states, in part:
8154The degree of impact to wetland and other
8162surface water functions caused by a
8168proposed system, whether the impact to
8174these functions can be mitigated and the
8181practicability of design modifications for
8186the site, as well as alignment
8192alternatives for a proposed linear system,
8198which could eliminate or reduce impacts to
8205these functions, are all factors in
8211determining whether an application will be
8217approved by the District. Design
8222modifications to reduce or eliminate
8227adverse impacts must be explored, as
8233described in subsection 4.2.1.1. Any
8238adverse impacts remaining after
8242practicable design modifications have been
8247implemented may be offset by mitigation as
8254described in subsections 4.3-4.3.8. . . .
8261To receive District approval, a system
8267cannot cause a net adverse impact on
8274wetland functions and other surface water
8280functions which is not offset by
8286mitigation.
8287102. The preceding section outlines a two-step process
8295of minimization and mitigation. However, according to BOR
8303Subsection 4.2.1.1, the District will not require project
8311modifications to achieve minimization unless the proposed
8318activity fails to meet the requirements of Subsections 4.2.2
8327through 4.2.3.7.
8329103. Subsection 4.2.2 requires that an applicant provide
8337reasonable assurance that a proposed activity will not impact
8346the values of wetlands and other surface water functions so as
8357to impact adversely the abundance, diversity, or habitat of
8366fish, wildlife, and listed species.
8371104. Subsection 4.2.2.4 requires that an applicant
8378provide reasonable assurance that the regulated activity will
8386not change the hydroperiod or a wetland or other surface
8396water, so as to affect adversely wetland functions or other
8406surface water functions.
8409105. Subsection 4.2.2.4(b) addresses proposed activities
8415that may increase the "depth, duration, or frequency of
8424inundation through changing the rate or method of discharge or
8434water to wetlands or other surface waters or by impounding
8444water in wetlands or other surface waters." Applicants for
8453permits for such activities must provide reasonable assurance
8461that the activities will not "adversely affect the functioning
8470of the specific wetland or other surface water subject to the
8481increased discharge or water level."
8486106. Subsection 4.2.2.4(c) requires that an applicant
8493proposing an activity that "could have the effect of altering
8503water levels in wetlands or surface waters" " shall be
8512required . . . to monitor the wetland or other surface waters
8524to demonstrate that such alterations has not resulted in
8533adverse impacts . . . or calibrate the system to prevent
8544adverse impacts." This subsection states: "Monitoring
8550parameters, methods, schedules, and reporting requirements
8556shall be specified in permit conditions."
8562107. Subsection 4.2.3 addresses the seven statutory
8569criteria detailing the public-interest test.
8574108. Subsection 4.2.3.1 states that, in balancing the
8582seven criteria, the District must determine whether the
8590proposed activity will cause, among other things, flooding and
8599environmental impacts to the property of others, although not
8608with respect to property values or taxes.
8615Subsection 4.2.3.1(c) adds, as to flooding: "There is at least
8625a neutral factor in the public interest balance with respect
8635to the potential for causing or alleviating flooding problems
8644if the applicant meets the water quantity criteria in section
8654six of this Basis of Review."
8660109. BOR Section 6 addresses water quantity criteria.
8668Subsection 6.2 provides that the offsite discharge rate may
8677not cause "adverse impacts to existing offsite properties" and
8686is limited to "historic discharge rates," previously permitted
8694rates, or rates specified in District criteria stated in an
8704appendix for various canals. Subsection 6.3 identifies the
8712design storm as the three-day, 25-year storm.
8719110. Historically, the land in question was inundated
8727during the wet season, so Section 6 is satisfied. Thus, by
8738operation of the BOR, the presumption is that the proposed
8748activity is no worse than neutral as to flooding. In fact,
8759though, the District has provided reasonable assurance as to
8768flooding. Because the proposed activity satisfies the
8775requirements of BOR Subsections 4.2.2 through 4.2.3.7, the
8783District is not required to consider alternative alignments to
8792this proposed linear system.
8796111. The proposed activity satisfies the other factors
8804mentioned by the BOR. As found above, the monitoring
8813provisions of the proposed permit, although largely illusory,
8821nonetheless satisfy the BOR requirements concerning
8827monitoring, as these requirements themselves do not require
8835the imposition of enforceable performance standards in the
8843monitoring provisions.
8845112. Based on the findings set forth above, the District
8855has provided reasonable assurance that, on balance, the
8863proposed activity meets the seven criteria identified in the
8872statute and Rule 40E-4.302.
8876113. Based on the findings set forth above, the District
8886has provided reasonable assurance that the proposed activity
8894meets the eleven criteria identified in Rule 40E-4.301.
8902RECOMMENDATION
8903It is
8905RECOMMENDED that the Department of Environmental
8911Protection enter a final order granting the permit for the
8921construction of the proposed weir about 3600 feet south of
8931I -75 in the Merritt Canal.
8937DONE AND ENTERED this 25th day of June, 1998, in
8947Tallahassee, Leon County, Florida.
8951___________________________________
8952ROBERT E. MEALE
8955Administrative Law Judge
8958Division of Administrative Hearings
8962The DeSoto Building
89651230 Apalachee Parkway
8968Tallahassee, Florida 32399-3060
8971(850) 488-9675 SUNCOM 278-9675
8975Fax Filing (850) 921-6847
8979Filed with the Clerk of the
8985Division of Administrative Hearings
8989this 25th day of June, 1998.
8995COPIES FURNISHED:
8997James W. McDonald, Jr., Esquire
9002McDonald & Associates
9005Community Plaza, Suite 306
900915600 Southwest 288th Street
9013Homestead, Florida 33030
9016A. Glenn Simpson
9019Qualified Representative
90215961 22nd Avenue Southwest
9025Naples, Florida 34116
9028Marcy I. LaHart
9031Associate Attorney
9033South Florida Water Management District
90383301 Gun Club Road
9042West Palm Beach, Florida 33416-4680
9047Francine M. Ffolkes
9050Assistant General Counsel
9053Department of Environmental Protection
9057Mail Station 35
90603900 Commonwealth Boulevard
9063Tallahassee, Florida 32399-3000
9066Walter R. Shaw, Sr., pro se
90721400 Northwest 62nd Avenue
9076Sunrise, Florida 33313-6138
9079Cliffort L. Fort
90828410 Northwest 16th Street
9086Pembroke Pines, Florida 33024
9090Kathy Carter, Agency Clerk
9094Department of Environmental Protection
9098Mail Station 35
91013900 Commonwealth Boulevard
9104Tallahassee, Florida 32399-3000
9107F. Perry Odom, General Counsel
9112Department of Environmental Protection
9116Mail Station 35
91193900 Commonwealth Boulevard
9122Tallahassee, Florida 32399-3000
9125NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
9131All parties have the right to submit written exceptions within
914115 days from the date of this recommended order. Any
9151exceptions to this recommended order must be filed with the
9161agency that will issue the final order in this case.
- Date
- Proceedings
- Date: 09/28/1998
- Proceedings: Letter to C. Tears from J. McDonald Re: Flooding filed.
- Date: 09/23/1998
- Proceedings: Letter to C. Tears from J. McDonald Re: Property Flooding filed.
- Date: 08/06/1998
- Proceedings: Final Order filed.
- PDF:
- Date: 06/25/1998
- Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 08/12, 13. 28 & 29/97 & 10/01,02,08, & 09/97 & 11/1 3,14,17,18, & 19/97 & 01/06-08/98.
- Date: 03/20/1998
- Proceedings: Notice of Intervenor Action for Motion to Dismiss for Mootness and/or the Division of Administrative Hearings Lacked Subject Matter Jurisdiction or in the Alternative Recommended Order (filed via facsimile).
- Date: 03/16/1998
- Proceedings: Intervenor Clifford Fort`s Recommended Order Including Supplemental Material to Petitioners` Proposed Recommended Order and Notice of Filing filed.
- Date: 03/16/1998
- Proceedings: Petitioner`s Notice of Filing Proposed Recommended Order; (Petitioner) Proposed Recommended Order filed.
- Date: 03/16/1998
- Proceedings: South Florida Water Management District`s Proposed Recommended Order filed.
- Date: 03/02/1998
- Proceedings: (Intervenor) Emergency Motion for Extension of Time to Produce Recommended Order and/or the Filing of Other Motions filed.
- Date: 03/02/1998
- Proceedings: (SFWMD) Exhibits filed.
- Date: 02/27/1998
- Proceedings: Corrected Petitioner`s Motion for Extension of Time to Submit Proposed Recommended Order (filed via facsimile).
- Date: 02/27/1998
- Proceedings: Petitioner`s Motion for Extension of Time to Submit Proposed Recommended Order filed.
- Date: 02/19/1998
- Proceedings: (DEP) Exhibits filed.
- Date: 02/09/1998
- Proceedings: (From J. McDonald) Notice of Filing Trial Exhibit Nos. 30, 31 and 32; Exhibits filed.
- Date: 02/04/1998
- Proceedings: (From W. Shaw, Jr.) Notice of Filing Trial Exhibits; Exhibits filed.
- Date: 02/02/1998
- Proceedings: (3 Volumes) Transcript filed.
- Date: 01/30/1998
- Proceedings: (From J. McDonald) Notice of Providing Exhibits to Respondent filed.
- Date: 01/30/1998
- Proceedings: (From W. Shaw) Emergency Motion for Extension of Time for Production of Exhibits filed.
- Date: 01/28/1998
- Proceedings: Petitioner`s Motion for Extension of Time for Production of Petitioners` Trial Exhibit Nos. 30, 31 and 32; Cover Letter (filed via facsimile).
- Date: 01/28/1998
- Proceedings: DEP`s hearing Exhibits filed.
- Date: 01/27/1998
- Proceedings: (From J. McDonald) Notice of Filing Trial Exhibits filed.
- Date: 01/27/1998
- Proceedings: Intervenor, Cliff Fort`s Trial Exhibits List; Intervenor`s Exhibits ; Cover Letter to Judge Meale from J. McDonald filed.
- Date: 01/27/1998
- Proceedings: (W. Shaw) Exhibit 12 ; Cover Letter to Judge Meale from J. McDonald filed.
- Date: 01/27/1998
- Proceedings: SFWMD Exhibits 1-2, 4,-5, 6a-6d, 8, 16 - 22 filed.
- Date: 01/27/1998
- Proceedings: Emergency Motion for Extension of time for production of exhibits (Intervenor) (filed via facsimile).
- Date: 01/26/1998
- Proceedings: (From J. McDonald) Notice of Filing Trial Exhibits; Exhibits filed.
- Date: 01/14/1998
- Proceedings: (I Volume) Transcript of Proceedings filed.
- Date: 01/06/1998
- Proceedings: CASE STATUS: Hearing Held.
- Date: 01/06/1998
- Proceedings: (From F. Ffolkes) Notice of Substitution of Counsel for Department of Environmental Protection filed.
- Date: 12/22/1997
- Proceedings: Transcripts (volumes 1 thru 4, tagged) filed.
- Date: 12/15/1997
- Proceedings: (3 Volumes) Transcript filed.
- Date: 12/12/1997
- Proceedings: Letter to J. McDonald from M. LaHart Re: Continuance of Deposition filed.
- Date: 12/05/1997
- Proceedings: Second Supplemental Notice of Hearing sent out. (hearing set for 1/6/98; 9:00am; Naples)
- Date: 11/17/1997
- Proceedings: Hearing Partially Held, continued to date not certain.
- Date: 11/13/1997
- Proceedings: Hearing Partially Held, continued to date not certain.
- Date: 11/03/1997
- Proceedings: (4 Volumes) Transcript filed.
- Date: 10/30/1997
- Proceedings: CC: Letter to James W. McDonald, Jr. from Marcy I. LaHart (RE: response to letter concerning the scheduling of witnesses for the remainder of the hearing) filed.
- Date: 10/29/1997
- Proceedings: (From W. Matturro) Notice of Appearance of Counsel for Department of Environmental Protection filed.
- Date: 10/27/1997
- Proceedings: Respondent South Florida Water Management District`s Motion to Quash (filed via facsimile).
- Date: 10/27/1997
- Proceedings: Copy of Letter to A. Nath from James McDonald (filed via facsimile).
- Date: 10/27/1997
- Proceedings: Copy of Letter to Marcy LaHart from James McDonald (re:witnesses) filed.
- Date: 10/16/1997
- Proceedings: Supplemental Notice of Hearing sent out. (hearing set for 11/13/97; 9:00am; Naples)
- Date: 10/08/1997
- Proceedings: CASE STATUS: Hearing Held.
- Date: 10/01/1997
- Proceedings: CASE STATUS: Hearing Partially Held, continued to Oct. 8-9, 1997.
- Date: 09/29/1997
- Proceedings: (Petitioner) Motion for Case Management Conference filed.
- Date: 09/29/1997
- Proceedings: (Petitioner) Response to Petitioner`s Motion for Case Management Conference; (Petitioner) Witness and Exhibit List (filed via facsimile).
- Date: 09/26/1997
- Proceedings: (From J. McDonald) Notice of Unavailability filed.
- Date: 09/17/1997
- Proceedings: Letter to J. McDonald from M. LaHart Re: Subpoenas filed.
- Date: 08/29/1997
- Proceedings: (From J. McDonald) Re-Notice of Taking Deposition Duces Tecum (Location change only); Second Amendment to Witness and Exhibit List filed.
- Date: 08/28/1997
- Proceedings: CASE STATUS: Hearing Partially Held, continued to Oct. 1-2, 1997.
- Date: 08/28/1997
- Proceedings: (From W. Shaw) Amended Notice of Taking Deposition; Amended Witness and Exhibit List filed.
- Date: 08/26/1997
- Proceedings: (Clifford Fort) Subpoena for Trial (filed via facsimile).
- Date: 08/26/1997
- Proceedings: Respondents Sputh Florida Water Management District`s and Florida Department of Environmental Protection`s Joint Motion to Quash (filed via facsimile).
- Date: 08/26/1997
- Proceedings: Respondent South Florida Water Management District`s Motion to Quash (filed via facsimile).
- Date: 08/26/1997
- Proceedings: (From W. Shaw) Witness and Exhibit List filed.
- Date: 08/25/1997
- Proceedings: First Amendment to Witness and Exhibit List; Request for Production of Documents; Petitioner`s Notice of Service of Interrogatories filed.
- Date: 08/25/1997
- Proceedings: (Petitioners) Witness and Exhibit List; (16) Subpoena for Trial ; (2) Notice of Taking Depositions Duces Tecum; (2) Corrected Subpoena for Deposition Duces Tecum; (4) Subpoena for Deposition Duces Tecum filed.
- Date: 08/15/1997
- Proceedings: Letter to Judge Meale from J. McDonald Re: Taking deposition filed.
- Date: 08/14/1997
- Proceedings: Supplemental Notice of Hearing sent out. (hearing set for Aug. 28-29, Oct. 1-2 & 8-9, 1997; 9:00am; Naples)
- Date: 08/13/1997
- Proceedings: Intervenor`s Notice of Filing Answers to First Set of Interrogatories Propounded by South Florida Water Management District filed.
- Date: 08/13/1997
- Proceedings: (From J. McDonald) Motion for Continuance; (From W. Shaw) Motion for Continuance filed.
- Date: 08/12/1997
- Proceedings: South Florida Water Management District`s Motion to Take Official Recognition filed.
- Date: 08/12/1997
- Proceedings: Hearing Partially Held, continued to date not certain.
- Date: 08/11/1997
- Proceedings: Letter to Judge Meale from J. McDonald Re: Motion for Continuance; Letter to Judge Meale from J. McDonald Re: Deposition filed.
- Date: 08/08/1997
- Proceedings: (SFWMD) Motion in Opposition to Continuance (filed via facsimile).
- Date: 08/05/1997
- Proceedings: Order Denying Amended Motion to Dismiss sent out.
- Date: 08/01/1997
- Proceedings: South Florida Water Management District`s Amended Motion to Dismiss (filed via facsimile).
- Date: 07/24/1997
- Proceedings: Order Denying Request for Change in Venue and Continuance sent out.
- Date: 07/21/1997
- Proceedings: Petitioners` Notice of Filing Amended Answers to Interrogatories Propounded by South Florida Water Management District; Answers filed.
- Date: 07/21/1997
- Proceedings: (W. Shaw) Statement of Facts filed.
- Date: 07/17/1997
- Proceedings: Order Compelling Discovery sent out.
- Date: 07/17/1997
- Proceedings: South Florida Water Management District`s Motion to Dismiss; Petitioners` Declaratory Statements Pursuant to Order Granting Motion to Intervene and Denying District`s Motions in Opposition Executed June 30, 1997 (filed via facsimile).
- Date: 07/15/1997
- Proceedings: Petitioners` Notice of Filing Answers to Interrogatories Propounded by South Florida Water Management District filed.
- Date: 07/11/1997
- Proceedings: (SFWMD) Notice of Service of Interrogatories filed.
- Date: 07/10/1997
- Proceedings: Respondent South Florida Water Management District`s Motion to Compel Discovery (filed via facsimile).
- Date: 06/30/1997
- Proceedings: Order Granting Motion to Intervene and Denying District`s Motions in Opposition sent out. (W. Shaw Granted Intervenor Status)
- Date: 05/19/1997
- Proceedings: (SFWMD) Notice of Service of Interrogatories filed.
- Date: 05/16/1997
- Proceedings: Notice of Hearing sent out. (hearing set for Aug. 12-13, 1997; 9:00am; Naples)
- Date: 05/13/1997
- Proceedings: South Florida Water Management District`s Motion in Opposition to Motion for Intervention (filed via facsimile).
- Date: 04/22/1997
- Proceedings: (Walter Shaw) Motion to Intervene (filed via facsimile).
- Date: 04/18/1997
- Proceedings: Joint Response to Initial Order filed.
- Date: 04/15/1997
- Proceedings: South Florida Water Management Distraict`s Motion In Opposition to Petition for Administrative Hearing (filed via facsimile).
- Date: 04/14/1997
- Proceedings: (Marcy Lahart) Notice of Appearance (filed via facsimile).
- Date: 04/14/1997
- Proceedings: Initial Order issued.
- Date: 04/04/1997
- Proceedings: Petition For Administrative Hearing; Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Agency Action Letter filed.
Case Information
- Judge:
- ROBERT E. MEALE
- Date Filed:
- 04/04/1997
- Date Assignment:
- 04/14/1997
- Last Docket Entry:
- 09/28/1998
- Location:
- Naples, Florida
- District:
- Middle
- Agency:
- ADOPTED IN TOTO