98-000749BID Hubbard Construction Company vs. Department Of Transportation
 Status: Closed
Recommended Order on Friday, May 1, 1998.


View Dockets  
Summary: Bidder used DBE not approved for non-federally funded project and failed to meet goal. DOT was not estopped or otherwise responsible. Bidder attempt to change DBE was after deadline for DBE utilization forms.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8HUBBARD CONSTRUCTION COMPANY, )

12)

13Petitioner, )

15)

16vs. ) Case No. 98-0749BID

21)

22DEPARTMENT OF TRANSPORTATION, )

26)

27Respondent, )

29)

30and )

32)

33SMITH & COMPANY, INC., )

38)

39Intervenor. )

41_________________________________)

42RECOMMENDED ORDER

44On March 12 and 13, 1998, a formal administrative hearing was

55held in this case in Tallahassee, Florida, before J. Lawrence

65Johnston, Administrative Law Judge, Division of Administrative

72Hearings.

73APPEARANCES

74For Petitioner: F. Alan Cummings

79Thomas A. Valdez

82Cummings & Thomas, P.A.

861004 DeSoto Park Drive

90Tallahassee, Florida 32301

93For Respondent: Mary Sieger Miller

98Former Assistant General Counsel

102Department of Transportation

105605 Suwannee Street, Mail Station 58

111Tallahassee, Florida 32399-0458

114For Intervenor: Donna H. Stinson

119Broad & Cassel

122215 South Monroe Street, Suite 400

128Tallahassee, Florida 32301

131STATEMENT OF THE ISSUE

135The issue in this case is whether the Respondent, the Department

146of Transportation (DOT), should award State Project No. 97160-3320 to

156Intervenor, Smith & Company (Smith), notwithstanding the bid protest

165filed by the Petitioner, Hubbard Construction Company (Hubbard),

173alleging that its bid was responsive and lower than Smith's bid.

184PRELIMINARY STATEMENT

186The Petitioner, Hubbard, and several others, including Intervenor

194Smith, bid on State Project No. 97160-3320 in Polk County (the

205project). Upon the opening of the bids on or about October 29, 1997,

218Petitioner was the apparent low bidder at $8,650,169.84; Cone & Graham

231was the apparent second low bidder at $8,863,088.21; and Intervenor

243Smith was the apparent third low bidder at $8,944,382.70.

254The bids of Hubbard and Cone & Graham were reviewed by the DOT's

267Good Faith Efforts Committee of the DOT's Minority Programs Office for

278compliance with the project's Disadvantaged Business Enterprise (DBE)

286goals and were found to be non-responsive. Cone & Graham's bid was

298found to be non-responsive because no DBE utilization forms had been

309submitted. Hubbard's bid was found to be non-responsive because its

319DBE utilization forms relied on Suncoast Fabrics, which was not an

330approved DBE for state-funded projects; without Suncoast Fabric's

338participation, Hubbard's bid did not meet the project's DBE goals.

348Neither Cone & Graham nor Hubbard submitted a package to demonstrate

359good faith efforts to meet the DBE goals.

367The findings and recommendations of the Good Faith Efforts

376Committee were submitted to the DOT's Technical Review Committee.

385The Technical Review Committee concurred with the Good Faith

394Efforts Committee that the apparent low bid and second low bid were

406non-responsive and that the project should be awarded to Smith.

416The findings and recommendations of the Technical Review

424Committee were submitted to the DOT's Contract Awards Committee.

433The Contract Awards Committee concurred with the Good Faith Efforts

443Committee and the Technical Review Committee that the apparent low

453bid and the apparent second low bid were nonresponsive, and awarded

464the contract to Smith.

468DOT issued its Notice of Intent to Award the contract to

479Smith, and Hubbard timely filed its bid protest. No other bidder

490protested. Smith petitioned to intervene.

495On or about February 12, 1998, the DOT referred Hubbard's bid

506protest to the Division of Administrative Hearings. Final hearing

515was scheduled and held on March 12 and 13, 1998. Hubbard called

527six witnesses and had Petitioner's Exhibits 1 through 15 admitted

537in evidence. The DOT called one witness and had Department

547Exhibits 1, 2, 3, 9, 11, 12, 17 and 18 admitted in evidence. Smith

561called one witness.

564DOT ordered the preparation of a transcript of the final

574hearing, and the parties filed proposed recommended orders.

582(Hubbard's Motion to Supplement its proposed recommended order is

591granted over the written objections of the other parties.)

600FINDINGS OF FACT

6031. State Project No. 97160-3320 (the project) is for work on the

615Polk County Parkway in Polk County. This project is funded entirely

626with state funds. It had a Disadvantaged Business Enterprise (DBE)

636goal of twelve percent, consisting of four percent black, and eight

647percent non-minority female.

6502. The Florida Department of Transportation (DOT) manages two

659separate DBE programs--a federal DBE program for federally funded

668projects, and a state DBE program for state-funded projects. The

678state program is based upon a disparity study conducted by MGT of

690America for the DOT in 1993. This study was conducted as a result of

704the case of City of Richmond v. J. A. Croson Co. , 109 S.Ct. 706

718(1989), which determined that a preferential contract system which was

728not based on actual discrimination was unconstitutional.

7353. The MGT disparity study found that there was evidence of

746disparate treatment by DOT in Florida, and in a very small number of

759counties outside of Florida. As a result, the state DBE program only

771certifies DBEs with home offices in Florida or the other counties

782identified in the disparity study.

7874. The DOT publishes a DBE directory for each bidding cycle.

798The DBE Directory includes DBEs certified or in the process of

809renewing expired certifications at the time the directory is

818published. The DBE directory includes DBEs for both the federal and

829state DBE programs but clearly indicates which DBEs are approved only

840for projects with at least some federal funding. Under DOT's policies

851and practices, a bidder can use any approved DBE listed in the

863directory even if the DBE's certification expires between publication

872and the bid letting.

8765. The deadline for submission of bids for the project was

887October 29, 1997. Hubbard's initial bid included a DBE Utilization

897Summary form indicating that it would achieve the DBE goal established

908for the project.

9116. The DBE Utilization Summary form gave Hubbard notice that

921another DBE Utilization Summary form listing the DBEs Hubbard would

931use, along with the dollar amounts of the subcontracts for each DBE

943listed, together with completed DBE Utilization forms for each DBE,

953had to be received by the DOT no later than 5 p.m. on the third

968business day after the bid letting. The DBE Utilization Summary form

979also gave notice that, otherwise: "Bids may be declared non-responsive

989. . . ."

9937. On November 3, 1997, Hubbard submitted a completed DBE

1003Utilization Summary form, together with completed DBE Utilization

1011forms. These forms stated that Hubbard stated would be using Suncoast

1022Fabrics for erosion control work to meet $160,000 worth of the non-

1035minority female goal for the project. Without the subcontract with

1045Suncoast Fabrics, Hubbard would fall $160,000 short of meeting the

1056non-minority female goal.

10598. In fact, Suncoast is not certified as a DBE for projects

1071funded entirely by the State (i.e., without any federal funding). As

1082a result, Hubbard's bid was $160,000 short of meeting the non-minority

1094female goal for the project.

10999. After November 3, 1997, Hubbard discovered its error in

1109relying on Suncoast Fabrics as a DBE for the project and on

1121November 5, 1997, submitted another DBE Utilization Summary form

1130and DBE Utilization form stating that, instead of paying Suncoast

1140$160,000 for erosion control work, it would pay Margie Woods

1151Trucking an additional $160,000.

115610. Hubbard's bid was reviewed by the DOT's Good Faith

1166Efforts Committee of the DOT's Minority Programs Office for

1175compliance with the project's DBE goals and was found to be non-

1187responsive because Hubbard's DBE utilization forms relied on

1195Suncoast Fabrics, which was not an approved DBE for state-funded

1205projects and because, without Suncoast Fabric's participation,

1212Hubbard's bid did not meet the project's DBE goals.

122111. Hubbard did not submit a package to demonstrate good

1231faith efforts to meet the DBE goals (because Hubbard thought its

1242bid met the DBE goals). The Good Faith Efforts Committee found

1253that Hubbard's bid did not demonstrate good faith efforts to meet

1264the DBE goals, a finding which Hubbard does not dispute.

127412. The Good Faith Efforts Committee did not consider

1283Hubbard's November 5, 1997, submission attempting to substitute

1291Suncoast Fabric's participation with an increase in Margie Woods

1300Trucking's participation because it was submitted after the

1308deadline for submitting DBE utilization forms.

131413. The findings and recommendations of the Good Faith

1323Efforts Committee were submitted to the DOT's Technical Review

1332Committee. The Technical Review Committee concurred with the Good

1341Faith Efforts Committee that the apparent low bid and second low

1352bid were non-responsive and that the project should be awarded to

1363Smith.

136414. The findings and recommendations of the Technical Review

1373Committee were submitted to the DOT's Contract Awards Committee. The

1383Contract Awards Committee concurred with the Good Faith Efforts

1392Committee and the Technical Review Committee that the apparent low bid

1403and the apparent second low bid were nonresponsive, and awarded the

1414contract to Smith.

141715. None of the DOT committees reviewing Hubbard's bid in the

1428process of deciding to award the contract to Smith gave specific

1439consideration to the question whether Hubbard's failure to timely

1448submit DBE utiJization forms meeting the project's DBE goals should be

1459waived as being a minor irregularity.

146516. The Department's policy is to strictly enforce the three-day

1475period for submission of completed DBE utilization forms and to

1485consider failure to submit DBE utilization forms meeting a project's

1495DBE goals to be a material error mandating rejection of a bid as non-

1509responsive. From January 1995 through December 1997, the Department

1518rejected 18 out of 254 problem bids because the bids failed to meet

1531DBE goals.

153317. The DOT rejected the bid of Edward M. Chadbourne and

1544Associates in a prior letting on facts very similar to those in this

1557case. Chadbourne proposed Suncoast Sod Farms, Inc., a DBE firm based

1568in Alabama, for a project wholly funded by the state. As reflected in

1581the DBE Directory for that letting, Suncoast Sod was not eligible for

1593non-federally funded projects.

159618. In two prior state-funded projects for the Polk County

1606Parkway, Suncoast Fabrics had been used by a contractor in its DBE

1618submissions. The Department allowed the use of Suncoast Fabrics to

1628count towards the contractor's DBE percentage because the DBE

1637Directory for those projects erroneously failed to indicate that

1646Suncoast Fabrics was certified as a DBE only for federally-funded

1656projects.

165719. Similarly, the DOT awarded a contract to Murphree Bridge

1667Corporation in a prior letting although Murphree did not meet the

1678three percent DBE goal for that project. In that case, DOT

1689advertisements prior to the letting erroneously stated that the goal

1699was two percent, and Murphree met the advertised goal but not the

1711actual 3 percent goal.

171520. In the two prior instances involving Suncoast Fabrics and

1725the prior instance involving Murphree Bridge, the DOT declined to

1735penalize the contractors for DOT's errors. However, there was no

1745change in DOT's policy regarding the three-day period for submission

1755of completed DBE utilization forms that meet a project's DBE goals.

1766In addition, in those instances, DOT was unable to count the DBE

1778utilization for purposes of its affirmative action program, for which

1788it must report to the legislature.

179421. Suncoast Fabrics apparently did not realize it was not

1804approved for state-funded contracts, and it misled Hubbard when

1813Hubbard inquired as to Suncoast's DBE eligibility. But regardless

1822whether Suncoast had an excuse for its erroneous belief, it was

1833Hubbard's responsibility to use the DBE Directory to verify whether a

1844DBE is authorized for use on a particular project, and the applicable

1856DBE Directory clearly noted that Suncoast Fabrics was not approved for

1867this project. In fact, Suncoast Fabrics was appropriately identified

1876as not qualifying for state-funded projects in each DBE Directory

1886since March 1997. DOT made no statement, representation or indication

1896of any kind to Hubbard that would have misled Hubbard to think that

1909Suncoast Fabrics was qualified as a DBE for State Project No. 97160-

19213320. In this regard, Hubbard's situation is significantly different

1930from the two prior instances involving Suncoast Fabrics, the prior

1940instance involving Murphree Bridge.

194422. The Department did not intend for bidders to use the three-

1956day period for submission of completed DBE Utilization forms to shop

1967DBEs' prices, attempt to drive DBEs' prices down, or continue to

1978solicit quotes from DBEs. The Department has no statute, rule,

1988procedure, or policy permitting substitution of DBEs more than three

1998days after a bid letting and before work begins. The Department does

2010not permit substituting DBEs after an award is posted unless the DBE

2022fails to perform, and then only with the express prior approval of the

2035Department.

203623. Allowing a bidder the ability to shop DBEs' prices, attempt

2047to drive DBEs' prices down, or continue to solicit quotes from DBEs

2059after the three-day period could give the bidder a competitive

2069advantage over bidders who do not.

207524. The amount of the bid submitted by a contractor can be

2087affected by the bids it received from DBEs. The bid submitted may be

2100based upon quotes received from particular DBEs. If one contractor

2110were allowed to use an unqualified DBE whose price was low, and the

2123other contractors did not rely on such quote, knowing that the DBE was

2136unqualified, the first contractor could enjoy a competitive advantage.

2145Although Hubbard asserted that it did not decide which DBEs to use

2157until after its bid was submitted, the possibility of an advantage

2168exists.

216925. Hubbard also contends that its failure to submit DBE

2179Utilization forms meeting the DBE goal for the project is similar to

2191Smith's alleged error in submitting a single DBE Utilization Summary

2201form for both of the split goals (black and non-minority female),

2212contrary to the instructions for the form. Suffice it to say that

2224submitting the information on a single form is different from

2234Hubbard's error. It is clear from Smith's submission that Smith's bid

2245met the project's DBE goals; it was clear from Hubbard's bid that

2257Hubbard's did not.

226026. DOT's decision to reject Hubbard's bid for failure to comply

2271with the DBE requirements was not contrary to statute, rule, policy,

2282practice or the bid specifications. Hubbard did not show that the

2293Department's action was clearly erroneous, contrary to competition,

2301arbitrary, or capricious.

2304CONCLUSIONS OF LAW

230727. Section 120.57(3)(f), Florida Statutes (1997), provides in

2315pertinent part:

2317Unless otherwise provided by statute, the burden

2324of proof shall rest with the party protesting the

2333proposed agency action. In a competitive-

2339procurement protest, other than a rejection of

2346all bids, the administrative law judge shall

2353conduct a de novo proceeding to determine whether

2361the agency's proposed action is contrary to the

2369agency's governing statutes, the agency's rules

2375or policies, or the bid or proposal

2382specifications. The standard of proof for such

2389proceedings shall be whether the proposed agency

2396action was clearly erroneous, contrary to

2402competition, arbitrary, or capricious.

240628. Section 339.0805(1)(b), Florida Statutes (1997), provides in

2414pertinent part:

2416(b) Upon a determination by the department of

2424past and continuing discrimination in

2429nonfederally funded projects on the basis of

2436race, color, creed, national origin, or sex, the

2444department may implement a program tailored to

2451address specific findings of disparity. The

2457program may include the establishment of annual

2464goals for expending a percentage of state-

2471administered highway funds with small business

2477concerns. . . . The head of the department may

2487elect to set goals only when significant

2494disparity is documented. (Emphasis supplied.)

249929. Florida Administrative Code Rule 14-78.004 provides in

2507pertinent part:

2509(1) Purpose. It is the purpose of the Non-

2518Federally Funded State DBE Program, hereinafter

2524referred to as "State DBE Program," to take

2532specific affirmative actions to eliminate

2537discrimination and the effects of past

2543discrimination . . . .

2548* * *

2551(4)(b) Eligible DBE's. Only DBE's certified

2557under Rule 14-78.005 and 14-78.007, who meet all

2565of the following criteria shall be eligible to

2573participate in the State DBE Program. These

2580DBE's are presumed to have experienced past

2587discrimination by the Department, but the

2593presumption is rebuttable.

25961. Those DBE's with their primary

2602place of business in the State of

2609Florida or other counties where the

2615disparity study has shown

2619discrimination by the Department . . .

2626. (emphasis added)

262930. Florida Administrative Code Rule 14-78.003(2)(b)3 provides

2636in pertinent part:

2639For all contracts for which DBE contract goals

2647have been established, each bidder shall meet or

2655exceed or demonstrate that it could not meet,

2663despite its good faith efforts, the contract

2670goals set by the Department. The DBE

2677participation information shall be submitted as

2683outlined in 14-78.003(2) (b)3.a. and b. below.

2690Award of the contract shall be conditioned upon

2698such submission of the DBE participation

2704information and upon satisfaction of the contract

2711goals or, if the goals are not met, upon

2720demonstrating that good faith efforts were made

2727to meet the goals. Failure to satisfy the

2735information requirements shall result in a

2741contractor's bid being deemed nonresponsive and

2747the bid being rejected.

2751a. The contractor's bid submission shall include

2758information, pursuant to 49 C.F.R. Subtitle A,

2765Subpart C, 23.45(h)(1)(i), submitted on a

2771completed Disadvantaged Business Enterprise (DBE)

2776Utilization Form, Form 275-020-004, Rev. 10/95

2782and Disadvantaged Business Enterprise (DBE)

2787Utilization Summary Form, Form 275-020-003, Rev.

279310/95.

2794b. In lieu of a completed Disadvantaged

2801Business Enterprise (DBE) Utilization Summary

2806Form, Department of Transportation Form 275 020-

2813003, Rev. 10/95, and a Disadvantaged Business

2820Enterprise (DBE) Utilization Form, Department of

2826Transportation Form 275-020-004, Rev. 10/95, the

2832contractor will submit a Disadvantaged Business

2838Enterprise (DBE) Utilization Summary Form which

2844indicates that either the contractor will achieve

2851the DBE goal established for the project for

2859which the bid has been submitted, or that the

2868contractor has submitted sufficient information

2873to demonstrate that the contractor made good

2880faith efforts to meet the DBE goal as part of the

2891bid submission. If the contractor has submitted

2898a Disadvantaged Business Enterprise (DBE)

2903Utilization Summary Form on which the contractor

2910has indicated that the DBE goal will be achieved,

2919the contractor will provide to the Minority

2926Programs Office by 5:00 P.M. on the third

2934business day following the bid letting day . . .

2944. (emphasis added)

2947This rule was amended to add option b. Before the amendment, all

2959DBE utilization forms had to be included in the initial bid

2970submission

297131. Hubbard's primary contention in this case is that its

2981failure to submit DBE utilization forms meeting the project's DBE

2991goals within the three-day period specified in Rule 14-

300078.003(2)(b)3.b was a minor irregularity that DOT should waive.

"3009[A]lthough a bid containing a material variance is unacceptable,

3018not every deviation from the invitation to bid is material. It is

3030only material if it gives the bidder a substantial advantage over

3041the other bidders and thereby restricts or stifles competition.

3050[T]he purpose of competitive bidding is to secure the lowest

3060possible responsible offer and minor irregularities can be waived

3069in effectuating this purpose." Tropabest Foods, Inc. v. Department

3078of General Services , 493 So. 2d 50 (Fla. 1st DCA 1986).

308932. The Department has consistently interpreted Florida

3096Administrative Code Rule 14-78.003(2)(b)3 to mean what it says:

"3105Failure to satisfy the information requirements shall result in a

3115contractor's bid being deemed nonresponsive and the bid being

3124rejected." Although in this case the DBE information was not

3134required until three days after the initial bid submission, the

3144principles are the same.

314833. In the Final Order, Murphy Construction Co. v. Department

3158of Transportation , Case No. 91-0848BID, entered May 10, 1991,

3167failure to provide a description of the work to be done on the DBE

3181form was found to be a material error because" the irregularity was

3193a violation of DOT rules which provide on their face that a

3205violation will result in a bid being nonresponsive, and the DOT

3216interprets the rule to mean what it says." This reasoning is

3227equally applicable to the matter at issue in this case. Similarly,

3238in the Recommended Order in Martin Eby Construction Company, Inc.

3248v. State of Florida Department of Transportation , Case No. 93-

32585703BID, entered December 28, 1993, a bidder relied on the

3268assertion of a potential DBE that it would be approved for the

3280letting, but the DBE was not listed in the applicable DBE

3291directory. The matter was considered to be a material error:

3301To allow Petitioner to substitute certified

3307DBEs for an uncertified DBE in its bid after

3316the bid letting would give Petitioner a

3323substantial advantage over the other bidders,

3329or an advantage or benefit not enjoyed by the

3338other bidders, or both. Hence, the

3344irregularity in Petitioner's bid is material

3350and not waiveable; Petitioner cannot be

3356permitted to substitute certified DBEs for

3362Gearing, an uncertified DBE, after bid letting.

336934. Courts have also recognized that the failure to list

3379subcontractors when required is a material deviation, in that such

3389failure provides the opportunity for bid shopping. In E.M.

3398Watkins & Co., v. Board of Regents , 414 So. 2d 583 (Fla. 1st DCA

34121982), the Court noted that:

3417The unfair bidding advantage one contractor

3423derives from the failure to list required

3430subcontractors is generally threefold: (1) it

3436provides the precious few minutes which may be

3444saved by failing to provide a name for the

3453appropriate blank on form D-1 and matching the

3461name with the price used in the bid

3469computation, (2) it allows the potential for

3476speculation, by use of a phantom price and

3484efforts to shop that item or trade until a

3493subcontractor can be found at the speculative

3500contract price, and (3) it permits a successful

3508bidder to accept additional subcontractor bids

3514after the bid opening, giving the opportunity

3521for undercutting the low subcontractor on whom

3528he relied in formulating his bid.

353435. Section 120.57(3)(f), Florida Statutes (1997), also

3541provides in pertinent part:

3545(f) In a competitive-procurement protest, no

3551submissions made after the bid or proposal

3558opening amending or supplementing the bid or

3565proposal shall be considered.

3569It is concluded that, for purposes of this statute, Hubbard's DBE

3580utilization forms should be considered to have been "opened" at the

3591end of the three-day period for their submission under Florida

3601Administrative Code Rule 14-78.003(2)(b)3.b. Hubbard's attempt to

3608change its DBE utilization forms after the deadline should not be

3619considered.

362036. Hubbard made the argument that, for purposes of Section

3630120.57(3)(f), the bid opening in this case was on October 29, 1997,

3642and Hubbard's timely DBE utilization forms submitted on November 3,

36521997, should not be considered, leaving only the representation in

3662the DBE Utilization Summary form Hubbard included with its initial

3672bid submission that Hubbard would meet the DBE goals for the

3683project. This argument is rejected. Clearly, DBE utilization

3691forms submitted in accordance with Florida Administrative Code Rule

370014-78.003(2)(b)3.b should be considered. Besides, if those forms

3708are not considered, Rule 14-78.003(2)(b)3 would require rejection

3716of the bid as non-responsive.

372137. Hubbard cites State Contracting & Engineering Corp. v.

3730Dept. of Transp. , 1998 WL 161227, 23 Fla. L. Week D942 (Fla. 1st

3743DCA 1998), for the proposition that Florida Administrative Code

3752Rule 14-78.003(2)(b)3 is not dispositive. In State Contracting &

3761Engineering (which has not yet been released for publication in the

3772permanent law and is still subject to revision or withdrawal), the

3783court observed that the requirements of some subsections of Rule

379314-78 are enforced at the time the subcontracts are reviewed. But

3804that observation related to the enforcement of subsections of Rule

381414-78 imposing requirements concerning the sources of labor and

3823materials that qualify as a part of the DBE goal. Those rule

3835provisions do not suggest that their requirements must be met at

3846the time the bid is submitted to the agency; as the DOT interprets

3859them, those requirements are enforced at the time the subcontracts

3869are reviewed.

387138. In contrast, State Contracting & Engineering also

3879acknowledges the DOT's consistent interpretation of Rule 14-

388778.003(2)(b)3--i.e., that the sufficiency of the DBE Utilization

3895forms included in a bid submission is determined at the time of bid

3908submission based on the forms themselves. The actual holding of

3918State Contracting & Engineering affirms this interpretation of Rule

392714-78.003 (2) (b) 3.

393139. Hubbard relied on the decision in Overstreet Paving Co.

3941v. Dept. of Transp. , 608 So. 2d 851 (Fla. 1st DCA 1992), as

3954standing for the proposition that errors of the kind made by

3965Hubbard in this case are not material. But in Overstreet , the

3976issue was whether a required DBE utilization form was inadvertently

3986omitted from a bid submission or whether DOT lost it. There was

3998never any question as to the existence or contents of the form.

4010Given those facts, the court held that Overstreet's evidence

4019shifted the burden to DOT to prove that the form was not submitted

4032and that DOT failed to meet its burden.

404040. To help explain its holding, Overstreet contained dicta

4049that omission of the DBE utilization form in that case was a "minor

4062technical discrepancy" and that the form itself was a "mere

4072technicality." However, it is not clear from the decision that the

4083court would not have ruled differently if the contents of the form

4095were not clear. It also cannot be inferred from the decision that

4107the court would countenance changing the contents of a DBE

4117utilization form after the Rule 14-78.003(2)(b)3.b deadline has

4125expired.

412641. Hubbard also relied on Hubbard Construction Co. v. Dept.

4136of Transp. , 642 So. 2d 1192 (Fla. 1st DCA 1994), as additional

4148support for the proposition that errors of the kind made by Hubbard

4160in this case are not material. Although not apparent from the

4171court decision itself, the Recommended Order, Hubbard Construction

4179Co. v. Dept. of Transp., DOAH Case No. 92-4018BID, entered October

419021, 1992, clarifies the facts. In that case, Hubbard used a DBE

4202who was not listed in the applicable DBE Directory because its DBE

4214certificate had expired and its pending application for

4222recertification was not filed 90 days prior to expiration.

4231However, the DBE's application for recertification was delayed due

4240to the DOT's last-minute requests for additional information that

4249had no basis, in law or fact. In addition, while DOT had a policy to

4264leave an expired DBE in the directory if its application for

4275recertification was filed prior to 90 days before the expiration of

4286its certificate, regardless of the length of time necessary to process

4297the application for recertification, including any delays created by

4306the DOT's requests for additional information, DOT had no rule that

4317required DBE applicants for recertification to file for renewal not

4327later than 90 days prior to expiration of their certifications. The

4338Hearing Officer recommended that, on those facts, Hubbard should be

4348allowed to count the DBE's participation towards meeting the project's

4358DBE goals, but DOT's Final Order rejected the recommendation.

436742. The court in Hubbard Construction simply held that the

4377Recommended Order was supported by competent and substantial evidence

4386and should not have be rejected in the DOT's Final Order. As in the

4400case of the prior erroneous uses of Suncoast Fabric on the Polk County

4413Parkway project, and the case of Murphree Bridge, it appears that

4424Recommended Order reinstated by the Hubbard Construction decision

4432turned more on fairness considerations than materiality. It cannot be

4442inferred from Hubbard Construction that the outcome would have been

4452the same without the DOT's misconduct. In contrast, in this case

4463Hubbard was not induced by DOT to use Suncoast Fabrics. Hubbard knew

4475State Project No. 97160-3320 was a state-funded project, and Suncoast

4485was clearly noted to be unqualified in the applicable DBE directory.

4496RECOMMENDATION

4497Based upon the foregoing Findings of Fact and Conclusions of Law,

4508it is

4510RECOMMENDED that the Department of Transportation enter a final

4519order awarding State Project No. 97160-3320 to Smith & Company.

4529RECOMMENDED this 1st day of May, 1998, in Tallahassee, Leon

4539County, Florida.

4541___________________________________

4542J. LAWRENCE JOHNSTON

4545Administrative Law Judge

4548Division of Administrative Hearings

4552The DeSoto Building

45551230 Apalachee Parkway

4558Tallahassee, Florida 32399-3060

4561(850) 488-9675 SUNCOM 278-9675

4565Fax Filing (850) 921-6847

4569Filed with the Clerk of the

4575Division of Administrative Hearings

4579this 1st day of May, 1998.

4585COPIES FURNISHED:

4587F. Alan Cummings, Esquire

4591Cummings & Thomas, P.A.

4595Post Office Box 1116

4599Ft. Lauderdale, Florida 33302-1116

4603Paul Sexton, Esquire

4606Chief, Administrative Law Section

4610Department of Transportation

4613605 Suwannee Street

4616Tallahassee, Florida 32399-0458

4619Donna H. Stinson, Esquire

4623Broad & Cassel

4626215 South Monroe Street

4630Suite 400

4632Tallahassee, Florida 32301

4635Thomas F. Barry, Secretary

4639Attention: Diedre Grubbs

4642Haydon Burns Building

4645Mail Station 58

4648605 Suwannee Street

4651Tallahassee, Florida 32399-0450

4654Pamela Leslie, General Counsel

4658Department of Transportation

4661Haydon Burns Building

4664Mail Station 58

4667605 Suwannee Street

4670Tallahassee, Florida 32399-0450

4673NOTICE OF RIGHTS TO SUBMIT EXCEPTIONS

4679All parties have the right to submit written exceptions within 15 days

4691from the date of this Recommended Order. Any exceptions to this

4702Recommended Order should be filed with the agency that will issue the

4714final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
Date: 05/27/1998
Proceedings: Final Order filed.
PDF:
Date: 05/26/1998
Proceedings: Agency Final Order
PDF:
Date: 05/26/1998
Proceedings: Recommended Order
PDF:
Date: 05/01/1998
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 03/12-13/98.
Date: 04/27/1998
Proceedings: Intervenor`s Response to Motion to Supplement (filed via facsimile).
Date: 04/22/1998
Proceedings: Department`s Response to Motion to Supplement filed.
Date: 04/17/1998
Proceedings: Motion to Supplement (Petitioner) filed.
Date: 04/13/1998
Proceedings: Department`s Proposed Recommended Order filed.
Date: 04/13/1998
Proceedings: Intervenor`s Proposed Recommended Order (disk Attached)filed.
Date: 04/10/1998
Proceedings: Notice of Substitution of Counsel, Notice of Filing , Hubbard Construction Company`s Proposed Recommended Order filed.
Date: 04/09/1998
Proceedings: Department`s Response to Petitioners` Motion for Extension of Time (filed via facsimile).
Date: 04/09/1998
Proceedings: Department`s Response to Petitioner`s Motion for Extension of Time (filed via facsimile).
Date: 04/09/1998
Proceedings: Hubbard Construction Company`s Motion for Enlargement of Time to File Its Proposed Recommended Order (filed via facsimile).
Date: 03/31/1998
Proceedings: Notice of Filing; DOAH Court Reporter Final Hearing Transcripts (Volumes 1, 2, 3, tagged) filed.
Date: 03/11/1998
Proceedings: Department`s Notice of Filing Petitioner`s Answers to Department`s First Set of Interrogatories filed.
Date: 03/11/1998
Proceedings: Joint Prehearing Statement of Respondent Department of Transportation and Intervenor, Smith & Company (filed via facsimile).
Date: 03/11/1998
Proceedings: Hubbard Construction Company`s Unilateral Prehearing Stipulation filed.
Date: 03/11/1998
Proceedings: Department`s Notice of Serving Answers to Petitioner`s First Set of Interrogatories; Department`s Notice of Filing Deposition; The Deposition of: Ernest J. Wolf filed.
Date: 03/11/1998
Proceedings: (Smith & Co.) Amended Notice of Taking Deposition (filed via facsimile).
Date: 03/09/1998
Proceedings: Department`s Response to Petitioner`s First Request for Admissions; Department`s Response to Petitioner`s Second Request for Production of Documents filed.
Date: 03/06/1998
Proceedings: (Petitioner) Notice of Taking Corporate Deposition filed.
Date: 03/04/1998
Proceedings: Hubbard Construction Company`s Responses to Respondent`s First Request for Admissions; Hubbard Construction Company`s First Request for Production of Documents filed.
Date: 03/04/1998
Proceedings: Hubbard Construction Company`s Responses to Respondent`s First Set of Interrogatories; Hubbard Construction Company`s Responses to Respondent`s First Request for Production of Documents filed.
Date: 03/04/1998
Proceedings: (Petitioner) (2) Notice of Taking Deposition; Amended Notice of Taking Deposition; Notice of Taking Corporate Deposition; Notice of Service of Hubbard Construction Company`s Responses to Respondent`s First Set of Interrogatories filed.
Date: 03/04/1998
Proceedings: Hubbard Construction Company`s Second Request for Production of Documents; Hubbard Construction Company`s First Request for Admissions; Hubbard Construction Company`s First Set of Interrogatories filed.
Date: 03/04/1998
Proceedings: Hubbard Construction Company`s Supplemental Responses to Respondent`s First Set of Interrogatories; Hubbard Construction Company`s Second Supplement to Its Responses to Respondent`s First Set of Interrogatories filed.
Date: 03/03/1998
Proceedings: Department`s Motion for Award of Attorney`s Fees and Costs from Petitioner, Hubbard Construction Company filed.
Date: 03/03/1998
Proceedings: Hubbard Construction Company`s Responses to Respondent`s First set of Interrogatories filed.
Date: 03/03/1998
Proceedings: Hubbard Construction Company`s Request for Production of Documents, Notice of Service of Hubbard Construction Company`s Responses to Respondent`s first set of Interrogatories filed.
Date: 03/03/1998
Proceedings: Hubbard Construction Company`s Responses to Respondent`s First Request for Production of Documents, Hubbard Construction Company`s Responses to Respondent`s First Request for Admissions filed.
Date: 03/03/1998
Proceedings: Notice of Taking Corporate Deposition, Notice of Taking Deposition filed.
Date: 03/03/1998
Proceedings: Department`s Response to Petitioner`s First Request for Production of Documents filed.
Date: 03/02/1998
Proceedings: Department`s Motion to Quash Petitioner`s Notice of Taking Deposition of Jimmy Lairscey filed.
Date: 03/02/1998
Proceedings: Department`s Motion for an Order to Compel Discovery, Motion for Award of Attorney`s Fees a and Costs Request for Oral Argument filed.
Date: 02/27/1998
Proceedings: (Respondent) Notice of Taking Corporate Deposition Duces Tecum filed.
Date: 02/27/1998
Proceedings: (Smith) Notice for Deposition Duces Tecum of Corporate Representative (filed via facsimile).
Date: 02/18/1998
Proceedings: Letter to Judge Smith from F. Cummings Re: Hubbard Construction Company disagrees with the statement of issues contained in the Department`s letter filed.
Date: 02/17/1998
Proceedings: Order Granting Leave to Intervene sent out. (for Smith & Company, Inc.)
Date: 02/17/1998
Proceedings: Notice of Final Hearing sent out. (hearing set for March 12-13, 1998; 9:00am; Tallahassee)
Date: 02/17/1998
Proceedings: Prehearing Order sent out.
Date: 02/12/1998
Proceedings: Department`s First Set of Interrogatories to Hubbard Construction Company; Department`s First Request for Production of Documents; Department`s First Request for Admissions from Hubbard Construction Company (w/answers) filed.
Date: 02/12/1998
Proceedings: (Smith & Company, Inc.) Petition to Intervene; Notice of Serving Respondent`s First Set of Interrogatories to Petitioner; Agency`s Notice of Compliance With Florida Rule of Administrative Procedure 60Q-2.006 filed.
Date: 02/12/1998
Proceedings: Agency Referral Letter; Letter to DOT from A. Cummings (re: Notice of intent to protest); Bid Protest Bond; Power of Attorney Appointing Individual Attorney-In-Fact; Formal Protest filed.

Case Information

Judge:
J. LAWRENCE JOHNSTON
Date Filed:
02/12/1998
Date Assignment:
02/13/1998
Last Docket Entry:
05/27/1998
Location:
Tallahassee, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Related DOAH Cases(s) (3):

Related Florida Statute(s) (2):

Related Florida Rule(s) (1):