98-000749BID
Hubbard Construction Company vs.
Department Of Transportation
Status: Closed
Recommended Order on Friday, May 1, 1998.
Recommended Order on Friday, May 1, 1998.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8HUBBARD CONSTRUCTION COMPANY, )
12)
13Petitioner, )
15)
16vs. ) Case No. 98-0749BID
21)
22DEPARTMENT OF TRANSPORTATION, )
26)
27Respondent, )
29)
30and )
32)
33SMITH & COMPANY, INC., )
38)
39Intervenor. )
41_________________________________)
42RECOMMENDED ORDER
44On March 12 and 13, 1998, a formal administrative hearing was
55held in this case in Tallahassee, Florida, before J. Lawrence
65Johnston, Administrative Law Judge, Division of Administrative
72Hearings.
73APPEARANCES
74For Petitioner: F. Alan Cummings
79Thomas A. Valdez
82Cummings & Thomas, P.A.
861004 DeSoto Park Drive
90Tallahassee, Florida 32301
93For Respondent: Mary Sieger Miller
98Former Assistant General Counsel
102Department of Transportation
105605 Suwannee Street, Mail Station 58
111Tallahassee, Florida 32399-0458
114For Intervenor: Donna H. Stinson
119Broad & Cassel
122215 South Monroe Street, Suite 400
128Tallahassee, Florida 32301
131STATEMENT OF THE ISSUE
135The issue in this case is whether the Respondent, the Department
146of Transportation (DOT), should award State Project No. 97160-3320 to
156Intervenor, Smith & Company (Smith), notwithstanding the bid protest
165filed by the Petitioner, Hubbard Construction Company (Hubbard),
173alleging that its bid was responsive and lower than Smith's bid.
184PRELIMINARY STATEMENT
186The Petitioner, Hubbard, and several others, including Intervenor
194Smith, bid on State Project No. 97160-3320 in Polk County (the
205project). Upon the opening of the bids on or about October 29, 1997,
218Petitioner was the apparent low bidder at $8,650,169.84; Cone & Graham
231was the apparent second low bidder at $8,863,088.21; and Intervenor
243Smith was the apparent third low bidder at $8,944,382.70.
254The bids of Hubbard and Cone & Graham were reviewed by the DOT's
267Good Faith Efforts Committee of the DOT's Minority Programs Office for
278compliance with the project's Disadvantaged Business Enterprise (DBE)
286goals and were found to be non-responsive. Cone & Graham's bid was
298found to be non-responsive because no DBE utilization forms had been
309submitted. Hubbard's bid was found to be non-responsive because its
319DBE utilization forms relied on Suncoast Fabrics, which was not an
330approved DBE for state-funded projects; without Suncoast Fabric's
338participation, Hubbard's bid did not meet the project's DBE goals.
348Neither Cone & Graham nor Hubbard submitted a package to demonstrate
359good faith efforts to meet the DBE goals.
367The findings and recommendations of the Good Faith Efforts
376Committee were submitted to the DOT's Technical Review Committee.
385The Technical Review Committee concurred with the Good Faith
394Efforts Committee that the apparent low bid and second low bid were
406non-responsive and that the project should be awarded to Smith.
416The findings and recommendations of the Technical Review
424Committee were submitted to the DOT's Contract Awards Committee.
433The Contract Awards Committee concurred with the Good Faith Efforts
443Committee and the Technical Review Committee that the apparent low
453bid and the apparent second low bid were nonresponsive, and awarded
464the contract to Smith.
468DOT issued its Notice of Intent to Award the contract to
479Smith, and Hubbard timely filed its bid protest. No other bidder
490protested. Smith petitioned to intervene.
495On or about February 12, 1998, the DOT referred Hubbard's bid
506protest to the Division of Administrative Hearings. Final hearing
515was scheduled and held on March 12 and 13, 1998. Hubbard called
527six witnesses and had Petitioner's Exhibits 1 through 15 admitted
537in evidence. The DOT called one witness and had Department
547Exhibits 1, 2, 3, 9, 11, 12, 17 and 18 admitted in evidence. Smith
561called one witness.
564DOT ordered the preparation of a transcript of the final
574hearing, and the parties filed proposed recommended orders.
582(Hubbard's Motion to Supplement its proposed recommended order is
591granted over the written objections of the other parties.)
600FINDINGS OF FACT
6031. State Project No. 97160-3320 (the project) is for work on the
615Polk County Parkway in Polk County. This project is funded entirely
626with state funds. It had a Disadvantaged Business Enterprise (DBE)
636goal of twelve percent, consisting of four percent black, and eight
647percent non-minority female.
6502. The Florida Department of Transportation (DOT) manages two
659separate DBE programs--a federal DBE program for federally funded
668projects, and a state DBE program for state-funded projects. The
678state program is based upon a disparity study conducted by MGT of
690America for the DOT in 1993. This study was conducted as a result of
704the case of City of Richmond v. J. A. Croson Co. , 109 S.Ct. 706
718(1989), which determined that a preferential contract system which was
728not based on actual discrimination was unconstitutional.
7353. The MGT disparity study found that there was evidence of
746disparate treatment by DOT in Florida, and in a very small number of
759counties outside of Florida. As a result, the state DBE program only
771certifies DBEs with home offices in Florida or the other counties
782identified in the disparity study.
7874. The DOT publishes a DBE directory for each bidding cycle.
798The DBE Directory includes DBEs certified or in the process of
809renewing expired certifications at the time the directory is
818published. The DBE directory includes DBEs for both the federal and
829state DBE programs but clearly indicates which DBEs are approved only
840for projects with at least some federal funding. Under DOT's policies
851and practices, a bidder can use any approved DBE listed in the
863directory even if the DBE's certification expires between publication
872and the bid letting.
8765. The deadline for submission of bids for the project was
887October 29, 1997. Hubbard's initial bid included a DBE Utilization
897Summary form indicating that it would achieve the DBE goal established
908for the project.
9116. The DBE Utilization Summary form gave Hubbard notice that
921another DBE Utilization Summary form listing the DBEs Hubbard would
931use, along with the dollar amounts of the subcontracts for each DBE
943listed, together with completed DBE Utilization forms for each DBE,
953had to be received by the DOT no later than 5 p.m. on the third
968business day after the bid letting. The DBE Utilization Summary form
979also gave notice that, otherwise: "Bids may be declared non-responsive
989. . . ."
9937. On November 3, 1997, Hubbard submitted a completed DBE
1003Utilization Summary form, together with completed DBE Utilization
1011forms. These forms stated that Hubbard stated would be using Suncoast
1022Fabrics for erosion control work to meet $160,000 worth of the non-
1035minority female goal for the project. Without the subcontract with
1045Suncoast Fabrics, Hubbard would fall $160,000 short of meeting the
1056non-minority female goal.
10598. In fact, Suncoast is not certified as a DBE for projects
1071funded entirely by the State (i.e., without any federal funding). As
1082a result, Hubbard's bid was $160,000 short of meeting the non-minority
1094female goal for the project.
10999. After November 3, 1997, Hubbard discovered its error in
1109relying on Suncoast Fabrics as a DBE for the project and on
1121November 5, 1997, submitted another DBE Utilization Summary form
1130and DBE Utilization form stating that, instead of paying Suncoast
1140$160,000 for erosion control work, it would pay Margie Woods
1151Trucking an additional $160,000.
115610. Hubbard's bid was reviewed by the DOT's Good Faith
1166Efforts Committee of the DOT's Minority Programs Office for
1175compliance with the project's DBE goals and was found to be non-
1187responsive because Hubbard's DBE utilization forms relied on
1195Suncoast Fabrics, which was not an approved DBE for state-funded
1205projects and because, without Suncoast Fabric's participation,
1212Hubbard's bid did not meet the project's DBE goals.
122111. Hubbard did not submit a package to demonstrate good
1231faith efforts to meet the DBE goals (because Hubbard thought its
1242bid met the DBE goals). The Good Faith Efforts Committee found
1253that Hubbard's bid did not demonstrate good faith efforts to meet
1264the DBE goals, a finding which Hubbard does not dispute.
127412. The Good Faith Efforts Committee did not consider
1283Hubbard's November 5, 1997, submission attempting to substitute
1291Suncoast Fabric's participation with an increase in Margie Woods
1300Trucking's participation because it was submitted after the
1308deadline for submitting DBE utilization forms.
131413. The findings and recommendations of the Good Faith
1323Efforts Committee were submitted to the DOT's Technical Review
1332Committee. The Technical Review Committee concurred with the Good
1341Faith Efforts Committee that the apparent low bid and second low
1352bid were non-responsive and that the project should be awarded to
1363Smith.
136414. The findings and recommendations of the Technical Review
1373Committee were submitted to the DOT's Contract Awards Committee. The
1383Contract Awards Committee concurred with the Good Faith Efforts
1392Committee and the Technical Review Committee that the apparent low bid
1403and the apparent second low bid were nonresponsive, and awarded the
1414contract to Smith.
141715. None of the DOT committees reviewing Hubbard's bid in the
1428process of deciding to award the contract to Smith gave specific
1439consideration to the question whether Hubbard's failure to timely
1448submit DBE utiJization forms meeting the project's DBE goals should be
1459waived as being a minor irregularity.
146516. The Department's policy is to strictly enforce the three-day
1475period for submission of completed DBE utilization forms and to
1485consider failure to submit DBE utilization forms meeting a project's
1495DBE goals to be a material error mandating rejection of a bid as non-
1509responsive. From January 1995 through December 1997, the Department
1518rejected 18 out of 254 problem bids because the bids failed to meet
1531DBE goals.
153317. The DOT rejected the bid of Edward M. Chadbourne and
1544Associates in a prior letting on facts very similar to those in this
1557case. Chadbourne proposed Suncoast Sod Farms, Inc., a DBE firm based
1568in Alabama, for a project wholly funded by the state. As reflected in
1581the DBE Directory for that letting, Suncoast Sod was not eligible for
1593non-federally funded projects.
159618. In two prior state-funded projects for the Polk County
1606Parkway, Suncoast Fabrics had been used by a contractor in its DBE
1618submissions. The Department allowed the use of Suncoast Fabrics to
1628count towards the contractor's DBE percentage because the DBE
1637Directory for those projects erroneously failed to indicate that
1646Suncoast Fabrics was certified as a DBE only for federally-funded
1656projects.
165719. Similarly, the DOT awarded a contract to Murphree Bridge
1667Corporation in a prior letting although Murphree did not meet the
1678three percent DBE goal for that project. In that case, DOT
1689advertisements prior to the letting erroneously stated that the goal
1699was two percent, and Murphree met the advertised goal but not the
1711actual 3 percent goal.
171520. In the two prior instances involving Suncoast Fabrics and
1725the prior instance involving Murphree Bridge, the DOT declined to
1735penalize the contractors for DOT's errors. However, there was no
1745change in DOT's policy regarding the three-day period for submission
1755of completed DBE utilization forms that meet a project's DBE goals.
1766In addition, in those instances, DOT was unable to count the DBE
1778utilization for purposes of its affirmative action program, for which
1788it must report to the legislature.
179421. Suncoast Fabrics apparently did not realize it was not
1804approved for state-funded contracts, and it misled Hubbard when
1813Hubbard inquired as to Suncoast's DBE eligibility. But regardless
1822whether Suncoast had an excuse for its erroneous belief, it was
1833Hubbard's responsibility to use the DBE Directory to verify whether a
1844DBE is authorized for use on a particular project, and the applicable
1856DBE Directory clearly noted that Suncoast Fabrics was not approved for
1867this project. In fact, Suncoast Fabrics was appropriately identified
1876as not qualifying for state-funded projects in each DBE Directory
1886since March 1997. DOT made no statement, representation or indication
1896of any kind to Hubbard that would have misled Hubbard to think that
1909Suncoast Fabrics was qualified as a DBE for State Project No. 97160-
19213320. In this regard, Hubbard's situation is significantly different
1930from the two prior instances involving Suncoast Fabrics, the prior
1940instance involving Murphree Bridge.
194422. The Department did not intend for bidders to use the three-
1956day period for submission of completed DBE Utilization forms to shop
1967DBEs' prices, attempt to drive DBEs' prices down, or continue to
1978solicit quotes from DBEs. The Department has no statute, rule,
1988procedure, or policy permitting substitution of DBEs more than three
1998days after a bid letting and before work begins. The Department does
2010not permit substituting DBEs after an award is posted unless the DBE
2022fails to perform, and then only with the express prior approval of the
2035Department.
203623. Allowing a bidder the ability to shop DBEs' prices, attempt
2047to drive DBEs' prices down, or continue to solicit quotes from DBEs
2059after the three-day period could give the bidder a competitive
2069advantage over bidders who do not.
207524. The amount of the bid submitted by a contractor can be
2087affected by the bids it received from DBEs. The bid submitted may be
2100based upon quotes received from particular DBEs. If one contractor
2110were allowed to use an unqualified DBE whose price was low, and the
2123other contractors did not rely on such quote, knowing that the DBE was
2136unqualified, the first contractor could enjoy a competitive advantage.
2145Although Hubbard asserted that it did not decide which DBEs to use
2157until after its bid was submitted, the possibility of an advantage
2168exists.
216925. Hubbard also contends that its failure to submit DBE
2179Utilization forms meeting the DBE goal for the project is similar to
2191Smith's alleged error in submitting a single DBE Utilization Summary
2201form for both of the split goals (black and non-minority female),
2212contrary to the instructions for the form. Suffice it to say that
2224submitting the information on a single form is different from
2234Hubbard's error. It is clear from Smith's submission that Smith's bid
2245met the project's DBE goals; it was clear from Hubbard's bid that
2257Hubbard's did not.
226026. DOT's decision to reject Hubbard's bid for failure to comply
2271with the DBE requirements was not contrary to statute, rule, policy,
2282practice or the bid specifications. Hubbard did not show that the
2293Department's action was clearly erroneous, contrary to competition,
2301arbitrary, or capricious.
2304CONCLUSIONS OF LAW
230727. Section 120.57(3)(f), Florida Statutes (1997), provides in
2315pertinent part:
2317Unless otherwise provided by statute, the burden
2324of proof shall rest with the party protesting the
2333proposed agency action. In a competitive-
2339procurement protest, other than a rejection of
2346all bids, the administrative law judge shall
2353conduct a de novo proceeding to determine whether
2361the agency's proposed action is contrary to the
2369agency's governing statutes, the agency's rules
2375or policies, or the bid or proposal
2382specifications. The standard of proof for such
2389proceedings shall be whether the proposed agency
2396action was clearly erroneous, contrary to
2402competition, arbitrary, or capricious.
240628. Section 339.0805(1)(b), Florida Statutes (1997), provides in
2414pertinent part:
2416(b) Upon a determination by the department of
2424past and continuing discrimination in
2429nonfederally funded projects on the basis of
2436race, color, creed, national origin, or sex, the
2444department may implement a program tailored to
2451address specific findings of disparity. The
2457program may include the establishment of annual
2464goals for expending a percentage of state-
2471administered highway funds with small business
2477concerns. . . . The head of the department may
2487elect to set goals only when significant
2494disparity is documented. (Emphasis supplied.)
249929. Florida Administrative Code Rule 14-78.004 provides in
2507pertinent part:
2509(1) Purpose. It is the purpose of the Non-
2518Federally Funded State DBE Program, hereinafter
2524referred to as "State DBE Program," to take
2532specific affirmative actions to eliminate
2537discrimination and the effects of past
2543discrimination . . . .
2548* * *
2551(4)(b) Eligible DBE's. Only DBE's certified
2557under Rule 14-78.005 and 14-78.007, who meet all
2565of the following criteria shall be eligible to
2573participate in the State DBE Program. These
2580DBE's are presumed to have experienced past
2587discrimination by the Department, but the
2593presumption is rebuttable.
25961. Those DBE's with their primary
2602place of business in the State of
2609Florida or other counties where the
2615disparity study has shown
2619discrimination by the Department . . .
2626. (emphasis added)
262930. Florida Administrative Code Rule 14-78.003(2)(b)3 provides
2636in pertinent part:
2639For all contracts for which DBE contract goals
2647have been established, each bidder shall meet or
2655exceed or demonstrate that it could not meet,
2663despite its good faith efforts, the contract
2670goals set by the Department. The DBE
2677participation information shall be submitted as
2683outlined in 14-78.003(2) (b)3.a. and b. below.
2690Award of the contract shall be conditioned upon
2698such submission of the DBE participation
2704information and upon satisfaction of the contract
2711goals or, if the goals are not met, upon
2720demonstrating that good faith efforts were made
2727to meet the goals. Failure to satisfy the
2735information requirements shall result in a
2741contractor's bid being deemed nonresponsive and
2747the bid being rejected.
2751a. The contractor's bid submission shall include
2758information, pursuant to 49 C.F.R. Subtitle A,
2765Subpart C, 23.45(h)(1)(i), submitted on a
2771completed Disadvantaged Business Enterprise (DBE)
2776Utilization Form, Form 275-020-004, Rev. 10/95
2782and Disadvantaged Business Enterprise (DBE)
2787Utilization Summary Form, Form 275-020-003, Rev.
279310/95.
2794b. In lieu of a completed Disadvantaged
2801Business Enterprise (DBE) Utilization Summary
2806Form, Department of Transportation Form 275 020-
2813003, Rev. 10/95, and a Disadvantaged Business
2820Enterprise (DBE) Utilization Form, Department of
2826Transportation Form 275-020-004, Rev. 10/95, the
2832contractor will submit a Disadvantaged Business
2838Enterprise (DBE) Utilization Summary Form which
2844indicates that either the contractor will achieve
2851the DBE goal established for the project for
2859which the bid has been submitted, or that the
2868contractor has submitted sufficient information
2873to demonstrate that the contractor made good
2880faith efforts to meet the DBE goal as part of the
2891bid submission. If the contractor has submitted
2898a Disadvantaged Business Enterprise (DBE)
2903Utilization Summary Form on which the contractor
2910has indicated that the DBE goal will be achieved,
2919the contractor will provide to the Minority
2926Programs Office by 5:00 P.M. on the third
2934business day following the bid letting day . . .
2944. (emphasis added)
2947This rule was amended to add option b. Before the amendment, all
2959DBE utilization forms had to be included in the initial bid
2970submission
297131. Hubbard's primary contention in this case is that its
2981failure to submit DBE utilization forms meeting the project's DBE
2991goals within the three-day period specified in Rule 14-
300078.003(2)(b)3.b was a minor irregularity that DOT should waive.
"3009[A]lthough a bid containing a material variance is unacceptable,
3018not every deviation from the invitation to bid is material. It is
3030only material if it gives the bidder a substantial advantage over
3041the other bidders and thereby restricts or stifles competition.
3050[T]he purpose of competitive bidding is to secure the lowest
3060possible responsible offer and minor irregularities can be waived
3069in effectuating this purpose." Tropabest Foods, Inc. v. Department
3078of General Services , 493 So. 2d 50 (Fla. 1st DCA 1986).
308932. The Department has consistently interpreted Florida
3096Administrative Code Rule 14-78.003(2)(b)3 to mean what it says:
"3105Failure to satisfy the information requirements shall result in a
3115contractor's bid being deemed nonresponsive and the bid being
3124rejected." Although in this case the DBE information was not
3134required until three days after the initial bid submission, the
3144principles are the same.
314833. In the Final Order, Murphy Construction Co. v. Department
3158of Transportation , Case No. 91-0848BID, entered May 10, 1991,
3167failure to provide a description of the work to be done on the DBE
3181form was found to be a material error because" the irregularity was
3193a violation of DOT rules which provide on their face that a
3205violation will result in a bid being nonresponsive, and the DOT
3216interprets the rule to mean what it says." This reasoning is
3227equally applicable to the matter at issue in this case. Similarly,
3238in the Recommended Order in Martin Eby Construction Company, Inc.
3248v. State of Florida Department of Transportation , Case No. 93-
32585703BID, entered December 28, 1993, a bidder relied on the
3268assertion of a potential DBE that it would be approved for the
3280letting, but the DBE was not listed in the applicable DBE
3291directory. The matter was considered to be a material error:
3301To allow Petitioner to substitute certified
3307DBEs for an uncertified DBE in its bid after
3316the bid letting would give Petitioner a
3323substantial advantage over the other bidders,
3329or an advantage or benefit not enjoyed by the
3338other bidders, or both. Hence, the
3344irregularity in Petitioner's bid is material
3350and not waiveable; Petitioner cannot be
3356permitted to substitute certified DBEs for
3362Gearing, an uncertified DBE, after bid letting.
336934. Courts have also recognized that the failure to list
3379subcontractors when required is a material deviation, in that such
3389failure provides the opportunity for bid shopping. In E.M.
3398Watkins & Co., v. Board of Regents , 414 So. 2d 583 (Fla. 1st DCA
34121982), the Court noted that:
3417The unfair bidding advantage one contractor
3423derives from the failure to list required
3430subcontractors is generally threefold: (1) it
3436provides the precious few minutes which may be
3444saved by failing to provide a name for the
3453appropriate blank on form D-1 and matching the
3461name with the price used in the bid
3469computation, (2) it allows the potential for
3476speculation, by use of a phantom price and
3484efforts to shop that item or trade until a
3493subcontractor can be found at the speculative
3500contract price, and (3) it permits a successful
3508bidder to accept additional subcontractor bids
3514after the bid opening, giving the opportunity
3521for undercutting the low subcontractor on whom
3528he relied in formulating his bid.
353435. Section 120.57(3)(f), Florida Statutes (1997), also
3541provides in pertinent part:
3545(f) In a competitive-procurement protest, no
3551submissions made after the bid or proposal
3558opening amending or supplementing the bid or
3565proposal shall be considered.
3569It is concluded that, for purposes of this statute, Hubbard's DBE
3580utilization forms should be considered to have been "opened" at the
3591end of the three-day period for their submission under Florida
3601Administrative Code Rule 14-78.003(2)(b)3.b. Hubbard's attempt to
3608change its DBE utilization forms after the deadline should not be
3619considered.
362036. Hubbard made the argument that, for purposes of Section
3630120.57(3)(f), the bid opening in this case was on October 29, 1997,
3642and Hubbard's timely DBE utilization forms submitted on November 3,
36521997, should not be considered, leaving only the representation in
3662the DBE Utilization Summary form Hubbard included with its initial
3672bid submission that Hubbard would meet the DBE goals for the
3683project. This argument is rejected. Clearly, DBE utilization
3691forms submitted in accordance with Florida Administrative Code Rule
370014-78.003(2)(b)3.b should be considered. Besides, if those forms
3708are not considered, Rule 14-78.003(2)(b)3 would require rejection
3716of the bid as non-responsive.
372137. Hubbard cites State Contracting & Engineering Corp. v.
3730Dept. of Transp. , 1998 WL 161227, 23 Fla. L. Week D942 (Fla. 1st
3743DCA 1998), for the proposition that Florida Administrative Code
3752Rule 14-78.003(2)(b)3 is not dispositive. In State Contracting &
3761Engineering (which has not yet been released for publication in the
3772permanent law and is still subject to revision or withdrawal), the
3783court observed that the requirements of some subsections of Rule
379314-78 are enforced at the time the subcontracts are reviewed. But
3804that observation related to the enforcement of subsections of Rule
381414-78 imposing requirements concerning the sources of labor and
3823materials that qualify as a part of the DBE goal. Those rule
3835provisions do not suggest that their requirements must be met at
3846the time the bid is submitted to the agency; as the DOT interprets
3859them, those requirements are enforced at the time the subcontracts
3869are reviewed.
387138. In contrast, State Contracting & Engineering also
3879acknowledges the DOT's consistent interpretation of Rule 14-
388778.003(2)(b)3--i.e., that the sufficiency of the DBE Utilization
3895forms included in a bid submission is determined at the time of bid
3908submission based on the forms themselves. The actual holding of
3918State Contracting & Engineering affirms this interpretation of Rule
392714-78.003 (2) (b) 3.
393139. Hubbard relied on the decision in Overstreet Paving Co.
3941v. Dept. of Transp. , 608 So. 2d 851 (Fla. 1st DCA 1992), as
3954standing for the proposition that errors of the kind made by
3965Hubbard in this case are not material. But in Overstreet , the
3976issue was whether a required DBE utilization form was inadvertently
3986omitted from a bid submission or whether DOT lost it. There was
3998never any question as to the existence or contents of the form.
4010Given those facts, the court held that Overstreet's evidence
4019shifted the burden to DOT to prove that the form was not submitted
4032and that DOT failed to meet its burden.
404040. To help explain its holding, Overstreet contained dicta
4049that omission of the DBE utilization form in that case was a "minor
4062technical discrepancy" and that the form itself was a "mere
4072technicality." However, it is not clear from the decision that the
4083court would not have ruled differently if the contents of the form
4095were not clear. It also cannot be inferred from the decision that
4107the court would countenance changing the contents of a DBE
4117utilization form after the Rule 14-78.003(2)(b)3.b deadline has
4125expired.
412641. Hubbard also relied on Hubbard Construction Co. v. Dept.
4136of Transp. , 642 So. 2d 1192 (Fla. 1st DCA 1994), as additional
4148support for the proposition that errors of the kind made by Hubbard
4160in this case are not material. Although not apparent from the
4171court decision itself, the Recommended Order, Hubbard Construction
4179Co. v. Dept. of Transp., DOAH Case No. 92-4018BID, entered October
419021, 1992, clarifies the facts. In that case, Hubbard used a DBE
4202who was not listed in the applicable DBE Directory because its DBE
4214certificate had expired and its pending application for
4222recertification was not filed 90 days prior to expiration.
4231However, the DBE's application for recertification was delayed due
4240to the DOT's last-minute requests for additional information that
4249had no basis, in law or fact. In addition, while DOT had a policy to
4264leave an expired DBE in the directory if its application for
4275recertification was filed prior to 90 days before the expiration of
4286its certificate, regardless of the length of time necessary to process
4297the application for recertification, including any delays created by
4306the DOT's requests for additional information, DOT had no rule that
4317required DBE applicants for recertification to file for renewal not
4327later than 90 days prior to expiration of their certifications. The
4338Hearing Officer recommended that, on those facts, Hubbard should be
4348allowed to count the DBE's participation towards meeting the project's
4358DBE goals, but DOT's Final Order rejected the recommendation.
436742. The court in Hubbard Construction simply held that the
4377Recommended Order was supported by competent and substantial evidence
4386and should not have be rejected in the DOT's Final Order. As in the
4400case of the prior erroneous uses of Suncoast Fabric on the Polk County
4413Parkway project, and the case of Murphree Bridge, it appears that
4424Recommended Order reinstated by the Hubbard Construction decision
4432turned more on fairness considerations than materiality. It cannot be
4442inferred from Hubbard Construction that the outcome would have been
4452the same without the DOT's misconduct. In contrast, in this case
4463Hubbard was not induced by DOT to use Suncoast Fabrics. Hubbard knew
4475State Project No. 97160-3320 was a state-funded project, and Suncoast
4485was clearly noted to be unqualified in the applicable DBE directory.
4496RECOMMENDATION
4497Based upon the foregoing Findings of Fact and Conclusions of Law,
4508it is
4510RECOMMENDED that the Department of Transportation enter a final
4519order awarding State Project No. 97160-3320 to Smith & Company.
4529RECOMMENDED this 1st day of May, 1998, in Tallahassee, Leon
4539County, Florida.
4541___________________________________
4542J. LAWRENCE JOHNSTON
4545Administrative Law Judge
4548Division of Administrative Hearings
4552The DeSoto Building
45551230 Apalachee Parkway
4558Tallahassee, Florida 32399-3060
4561(850) 488-9675 SUNCOM 278-9675
4565Fax Filing (850) 921-6847
4569Filed with the Clerk of the
4575Division of Administrative Hearings
4579this 1st day of May, 1998.
4585COPIES FURNISHED:
4587F. Alan Cummings, Esquire
4591Cummings & Thomas, P.A.
4595Post Office Box 1116
4599Ft. Lauderdale, Florida 33302-1116
4603Paul Sexton, Esquire
4606Chief, Administrative Law Section
4610Department of Transportation
4613605 Suwannee Street
4616Tallahassee, Florida 32399-0458
4619Donna H. Stinson, Esquire
4623Broad & Cassel
4626215 South Monroe Street
4630Suite 400
4632Tallahassee, Florida 32301
4635Thomas F. Barry, Secretary
4639Attention: Diedre Grubbs
4642Haydon Burns Building
4645Mail Station 58
4648605 Suwannee Street
4651Tallahassee, Florida 32399-0450
4654Pamela Leslie, General Counsel
4658Department of Transportation
4661Haydon Burns Building
4664Mail Station 58
4667605 Suwannee Street
4670Tallahassee, Florida 32399-0450
4673NOTICE OF RIGHTS TO SUBMIT EXCEPTIONS
4679All parties have the right to submit written exceptions within 15 days
4691from the date of this Recommended Order. Any exceptions to this
4702Recommended Order should be filed with the agency that will issue the
4714final order in this case.
- Date
- Proceedings
- Date: 05/27/1998
- Proceedings: Final Order filed.
- PDF:
- Date: 05/01/1998
- Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 03/12-13/98.
- Date: 04/27/1998
- Proceedings: Intervenor`s Response to Motion to Supplement (filed via facsimile).
- Date: 04/22/1998
- Proceedings: Department`s Response to Motion to Supplement filed.
- Date: 04/17/1998
- Proceedings: Motion to Supplement (Petitioner) filed.
- Date: 04/13/1998
- Proceedings: Department`s Proposed Recommended Order filed.
- Date: 04/13/1998
- Proceedings: Intervenor`s Proposed Recommended Order (disk Attached)filed.
- Date: 04/10/1998
- Proceedings: Notice of Substitution of Counsel, Notice of Filing , Hubbard Construction Company`s Proposed Recommended Order filed.
- Date: 04/09/1998
- Proceedings: Department`s Response to Petitioners` Motion for Extension of Time (filed via facsimile).
- Date: 04/09/1998
- Proceedings: Department`s Response to Petitioner`s Motion for Extension of Time (filed via facsimile).
- Date: 04/09/1998
- Proceedings: Hubbard Construction Company`s Motion for Enlargement of Time to File Its Proposed Recommended Order (filed via facsimile).
- Date: 03/31/1998
- Proceedings: Notice of Filing; DOAH Court Reporter Final Hearing Transcripts (Volumes 1, 2, 3, tagged) filed.
- Date: 03/11/1998
- Proceedings: Department`s Notice of Filing Petitioner`s Answers to Department`s First Set of Interrogatories filed.
- Date: 03/11/1998
- Proceedings: Joint Prehearing Statement of Respondent Department of Transportation and Intervenor, Smith & Company (filed via facsimile).
- Date: 03/11/1998
- Proceedings: Hubbard Construction Company`s Unilateral Prehearing Stipulation filed.
- Date: 03/11/1998
- Proceedings: Department`s Notice of Serving Answers to Petitioner`s First Set of Interrogatories; Department`s Notice of Filing Deposition; The Deposition of: Ernest J. Wolf filed.
- Date: 03/11/1998
- Proceedings: (Smith & Co.) Amended Notice of Taking Deposition (filed via facsimile).
- Date: 03/09/1998
- Proceedings: Department`s Response to Petitioner`s First Request for Admissions; Department`s Response to Petitioner`s Second Request for Production of Documents filed.
- Date: 03/06/1998
- Proceedings: (Petitioner) Notice of Taking Corporate Deposition filed.
- Date: 03/04/1998
- Proceedings: Hubbard Construction Company`s Responses to Respondent`s First Request for Admissions; Hubbard Construction Company`s First Request for Production of Documents filed.
- Date: 03/04/1998
- Proceedings: Hubbard Construction Company`s Responses to Respondent`s First Set of Interrogatories; Hubbard Construction Company`s Responses to Respondent`s First Request for Production of Documents filed.
- Date: 03/04/1998
- Proceedings: (Petitioner) (2) Notice of Taking Deposition; Amended Notice of Taking Deposition; Notice of Taking Corporate Deposition; Notice of Service of Hubbard Construction Company`s Responses to Respondent`s First Set of Interrogatories filed.
- Date: 03/04/1998
- Proceedings: Hubbard Construction Company`s Second Request for Production of Documents; Hubbard Construction Company`s First Request for Admissions; Hubbard Construction Company`s First Set of Interrogatories filed.
- Date: 03/04/1998
- Proceedings: Hubbard Construction Company`s Supplemental Responses to Respondent`s First Set of Interrogatories; Hubbard Construction Company`s Second Supplement to Its Responses to Respondent`s First Set of Interrogatories filed.
- Date: 03/03/1998
- Proceedings: Department`s Motion for Award of Attorney`s Fees and Costs from Petitioner, Hubbard Construction Company filed.
- Date: 03/03/1998
- Proceedings: Hubbard Construction Company`s Responses to Respondent`s First set of Interrogatories filed.
- Date: 03/03/1998
- Proceedings: Hubbard Construction Company`s Request for Production of Documents, Notice of Service of Hubbard Construction Company`s Responses to Respondent`s first set of Interrogatories filed.
- Date: 03/03/1998
- Proceedings: Hubbard Construction Company`s Responses to Respondent`s First Request for Production of Documents, Hubbard Construction Company`s Responses to Respondent`s First Request for Admissions filed.
- Date: 03/03/1998
- Proceedings: Notice of Taking Corporate Deposition, Notice of Taking Deposition filed.
- Date: 03/03/1998
- Proceedings: Department`s Response to Petitioner`s First Request for Production of Documents filed.
- Date: 03/02/1998
- Proceedings: Department`s Motion to Quash Petitioner`s Notice of Taking Deposition of Jimmy Lairscey filed.
- Date: 03/02/1998
- Proceedings: Department`s Motion for an Order to Compel Discovery, Motion for Award of Attorney`s Fees a and Costs Request for Oral Argument filed.
- Date: 02/27/1998
- Proceedings: (Respondent) Notice of Taking Corporate Deposition Duces Tecum filed.
- Date: 02/27/1998
- Proceedings: (Smith) Notice for Deposition Duces Tecum of Corporate Representative (filed via facsimile).
- Date: 02/18/1998
- Proceedings: Letter to Judge Smith from F. Cummings Re: Hubbard Construction Company disagrees with the statement of issues contained in the Department`s letter filed.
- Date: 02/17/1998
- Proceedings: Order Granting Leave to Intervene sent out. (for Smith & Company, Inc.)
- Date: 02/17/1998
- Proceedings: Notice of Final Hearing sent out. (hearing set for March 12-13, 1998; 9:00am; Tallahassee)
- Date: 02/17/1998
- Proceedings: Prehearing Order sent out.
- Date: 02/12/1998
- Proceedings: Department`s First Set of Interrogatories to Hubbard Construction Company; Department`s First Request for Production of Documents; Department`s First Request for Admissions from Hubbard Construction Company (w/answers) filed.
- Date: 02/12/1998
- Proceedings: (Smith & Company, Inc.) Petition to Intervene; Notice of Serving Respondent`s First Set of Interrogatories to Petitioner; Agency`s Notice of Compliance With Florida Rule of Administrative Procedure 60Q-2.006 filed.
- Date: 02/12/1998
- Proceedings: Agency Referral Letter; Letter to DOT from A. Cummings (re: Notice of intent to protest); Bid Protest Bond; Power of Attorney Appointing Individual Attorney-In-Fact; Formal Protest filed.