  • 1A utility’s service availability policy shall be designed in accordance with the following guidelines:

    15(1) The maximum amount of contributions-in-aid-of-construction, net of amortization, should not exceed 75% of the total original cost, net of accumulated depreciation, of the utility’s facilities and plant when the facilities and plant are at their designed capacity; and

    54(2) The minimum amount of contributions-in-aid-of-construction should not be less than the percentage of such facilities and plant that is represented by the water transmission and distribution and sewage collection systems.

    85Rulemaking Authority 87367.101, 88367.121(1) FS. 90Law Implemented 92367.101 FS. 94History–New 6-14-83, Formerly 25-30.58, 25-30.058, Amended 1-31-00.

     