Florida Administrative Code (Last Updated: November 11, 2024) |
60. Department of Management Services |
60GG. Florida Digital Service |
60GG-1. Department of Management Services Project Management and Oversight |
1(1) The Execution phase involves carrying out and managing all the activities described in the Project Management Plan.
19(2) The majority of Execution phase activities and documentation will be associated with the Agency’s specific Systems Development Life Cycle (SDLC) process and requirements.
43EXECUTION PHASE 45‒ Requirements by Risk & Complexity Category
524
533
542
551
56Operations and
58Maintenance (O&M) Plan
61Required ‒ Develop an O&M Plan prior to the scheduled completion of the project’s Execution phase. Document concurrence from those responsible for the operation a86nd maintenance (e.g., financial, information technology, and operational managers, etc.) on their readiness to support the system from a budgetary, staffing, technology, and operational perspective after go-live.
113Recommended
1144
1153
1162
1171
118Project Management Plans
121Required 122‒ As necessary, update Project Management Plan documents.
130(4) Agency project management activities required during the Execution phase are further described in Rule 14560GG146-1.006, 147F.A.C. 148‒ Monitoring and Controlling.
152Rulemaking Authority 154282.0051(6) 155FS156. Law Implemented 159282.0041, 160282.0051 161FS. History‒New 7-16-15, Amended 8-1-16, Formerly 74-1.005.