62C-29.006. Workover Operations  


Effective on Sunday, March 24, 1996
  • 1(1) Notification. Each operator shall notify the Department’s agent prior to commencing a workover operation or, during an emergency, as soon thereafter as possible.

    25(2) Blowout Preventer Requirements. All workover operations for Type I wells shall provide blowout preventer systems and tests which shall meet or exceed the requirements in Chapter 62C-27, F.A.C.

    54(3) Reporting Requirements. The operator shall submit to the Department within 30 days of completion of any workover operation a revised Well Record (Oil & Gas Form 8).

    82Rulemaking 83Authority 84377.22 FS. 86Law Implemented 88377.22 FS. 90History–New 11-26-81, Formerly 16C-29.06, Amended 6-4-89, Repromulgated 5-12-93, Formerly 16C-29.006, Amended 3-24-96.

     