1A petition for a limited proceeding shall include:
9(1) A list of all issues the petitioner believes should be decided;
21(2) A detailed statement of the reason(s) why the limited proceeding has been requested and why a limited proceeding is the appropriate type of proceeding for consideration of the requested relief;
52(3) A schedule showing the specific rate base components for which the utility seeks recovery, on both a system and jurisdictional basis, if the utility is requesting recovery of rate base components;
84(4) A detailed description of the expense(s) requested on both a system and jurisdictional basis, if the utility is requesting recovery of operating expenses;
108(5) A schedule showing how the utility proposes to allocate any change in revenues to rate classes, and the proposed rates, if the petition requests a change in retail rates; and
139(6) Any other information that the utility deems relevant.
148Rulemaking Authority 150350.127(2), 151366.05, 152366.06(1) FS. 154Law Impl156emented 157366.05(1), 158366.06(1), 159366.076(1) FS. 161History‒New 10-8-13.