1(1) Any person desiring to obtain a permit from the Department shall apply on forms prescribed by the Department and shall submit such additional information as the Department by law may require.
33(2) All applications and supporting documents shall be filed with the Department.
45(3) To ensure protection of public health, safety, and welfare, any construction, modification, or operation of an installation which may be a source of pollution, or of a public drinking water supply, shall be in accordance with sound professional engineering practices pursuant to Chapter 471, F.S.; and all final geological papers or documents involving the practice of the profession of geology shall be in accordance with sound professional geological practices pursuant to Chapter 492, F.S. All applications for a Department permit shall be certified by a professional engineer registered in the State of Florida except, when the application is for renewal of an air pollution operation permit at a non-Title V source as defined in Rule 16162-210.200, 162F.A.C., or where professional engineering is not required by Chapter 471, F.S. Where required by Chapter 471 or 492, F.S., applicable portions of permit applications and supporting documents which are submitted to the Department for public record shall be signed and sealed by the professional(s) who prepared or approved them.
212(4) Processing fees are as follows:
218(a) Air Pollution Permits.
2221. Construction Permit Fee for an Emissions Unit Requiring Prevention of Significant Deterioration or Nonattainment Area Preconstruction Review. The processing fee for a construction permit for an emissions unit requiring a Prevention of Significant Deterioration (PSD) or Nonattainment Area (NAA) preconstruction review pursuant to Rule 26762-212.400 268or 26962-212.500, 270F.A.C., respectively, shall be $7500.
2752. Construction Permit Fee for an Emissions Unit Not Requiring Prevention of Significant Deterioration or Nonattainment Area Preconstruction Review. No processing fee shall be required for a construction permit for an emissions unit not requiring Prevention of Significant Deterioration (PSD) or Nonattainment Area (NAA) preconstruction review, if the facility containing the emissions unit holds an air operation permit issued pursuant to Chapter 62-213, F.A.C. For any such emissions unit at a facility not holding a Chapter 62-213, F.A.C., air operation permit, the processing fee shall be as follows:
363a. Construction permit for an emissions unit having potential emissions of 100 or more tons per
379year of any single pollutant
384$5000
385b. Construction permit for an emissions unit having potential emissions of 50 or more tons
400per year, but less than 100 tons per year, of any single pollutant
413$4500
414c. Construction permit for an emissions unit having potential emissions of 25 or more tons per year,
431but less than 50 tons per year, of any single pollutant
442$2000
443d. Construction permit for an emissions unit having potential emissions of 5 or more tons per year,
460but less than 25 tons per year, of any single pollutant
471$1000
472e. Construction permit for an emissions unit having potential emissions of less than 5 tons per year of each pollutant
492$250
4933. Operation Permit Fee for an Emissions Unit at a Non-Title V Source.
506a. Operation permit for an emissions unit required to measure actual emissions by stack sampling
521$1500
522b. Operation permit for an emissions unit required to measure actual emissions by any method
537other than stack sampling (such as visible emissions observation or continuous emissions monitoring)
550$1000
551c. Operation permit for an emissions unit not required to measure actual emissions
564$750
5654. Similar Emissions Unit Fee. Where new or existing multiple emissions units located at the same facility are substantially similar in nature, the applicant may submit a single application and any required permit fee for construction or operation of the emissions units at the facility. To be considered substantially similar each of the emissions units must be substantially similar in regard to each of the following: nominal description or type of emissions unit; type of fuel burned; type of material processed, stored, or handled; type of air pollution control equipment; regulated pollutants emitted; applicable emissions standards; and applicable regulatory control criteria. For a construction permit, the single application fee shall be the fee that would apply for a single emissions unit with emissions that equal the total of the potential emissions of all of the substantially similar emissions units at the facility. The fee for an operation permit for a group of similar emissions units at the same facility, submitted under the same application and with the same emissions testing or monitoring requirements, shall be the fee that would apply to any emissions unit in the group if each emissions unit were being permitted singly.
7605. Multiple Emissions Unit Fee. If the Department issues a single construction or operation permit covering multiple emissions units or groups of similar emissions units at a facility, the permit processing fee shall be the sum of the fees applicable to each emissions unit and group of similar emissions units covered by the permit.
814(b) Domestic Wastewater Facility Permits.
8191. Preliminary Design Report reviews for Types I, II, and III domestic wastewater facilities as defined in Rule 83762-600.200, 838F.A.C. For new domestic wastewater facilities, the fee for review of a preliminary design report shall be in addition to the application processing fee.
862Type I
864Type II
866Type III
868a. Treatment plant with or without reuse/disposal system
876$5000
877$3750
878$1200
879b. Reuse/land application system and associated transmission/distribution facilities, when applied for separately from the treatment facility
895$5000
896$3750
897$1200
898c. Residuals/septage management facility
902$7500
903$4000
904$1200
905d. Limited wet weather discharge
910$1000
911$800
912$600
9132. Wastewater permits for Types I, II, and III domestic wastewater facilities as defined in Rule 92962-600.200, 930F.A.C.
931Type I
933Type II
935Type III
937a. Treatment plant with or without reuse/disposal system
945$5000
946$3000
947$1000
948b. Reuse/land application system and associated transmission/distribution facilities, when applied for separately from the treatment facility
964$5000
965$3000
966$1000
967c. Residuals/septage management facility
971$7500
972$4000
973$1000
974d. Limited wet weather discharge
979$1000
980$800
981$600
982e. Wastewater permits for Type III facilities having a permitted capacity of less than 10,000 gallons per day shall be $600.
10043. Wastewater Permit for a surface water discharge, when applied for separately from the treatment facility.
1020a. Type I facility
1024$2000
1025b. Type II facility
1029$1000
1030c. Type III facility
1034$500
10354. Minor revisions, as defined in Rule 104262-620.200, 1043F.A.C., to wastewater permits for domestic wastewater facilities other than minor modifications of permits listed in paragraph 106062-4.050(4)(s), 1061F.A.C.
1062a. Type I facility
1066$500
1067b. Type II facility
1071$300
1072c. Type III facility
1076$100
10775. Substantial revisions, as defined in Rule 108462-620.200, 1085F.A.C., to wastewater permits for domestic wastewater facilities shall require a new wastewater permit application and applicable fee. The applicable application fee shall be:
1109a. For substantial revisions resulting from substantial modifications to the facility which require an antidegradation determination as specified in Rule 112962-4.242, 1130F.A.C., or which increase the permitted capacity of the treatment, reuse, or disposal system, the preliminary design report fee specified in subparagraph (4)(b)1.
1153b. For substantial revisions resulting from substantial modifications to the facility, but which do not require an antidegradation determination as specified in Rule 117662-4.242, 1177F.A.C., and which do not increase the permitted capacity of the treatment, reuse, or disposal system, 50 percent of the preliminary design report fee specified in subparagraph (4)(b)1.
1205c. For substantial revisions not associated with substantial modifications to the facility, 20 percent of the applicable application fee specified in subparagraph (4)(b)2.
12286. Generic Permit for domestic wastewater treatment facilities.
1236a. Treatment facility with permitted capacity of 10,000 gallons per day up to 100,000 gallons per day shall be 1257$1,000
1259b. Treatment facility with permitted capacity less than 10,000 gallons per day shall be 1274$600
12757. Construction Permit for domestic wastewater collection/transmission system.
1283a. Domestic wastewater collection/transmission system serving 10 or more
1292$500
1293Equivalent Dwelling Units (EDUs). An EDU is equal to 3.5 persons
1304b. Domestic wastewater collection/transmission system serving less than 10 EDUs
1314$300
1315(c) Industrial Wastewater Facility Permits.
13201. Wastewater permits for Group 1 industrial wastewater treatment facilities which discharge process wastewater, as defined in Rule 133862-620.200, 1339F.A.C., from the following industry categories: Citrus Processing; Textiles; Organic Chemicals, Plastics, and Synthetic Fibers; Inorganic Chemicals; Soaps and Detergents; Fertilizer Manufacturing; Petroleum Refining; Iron and Steel Manufacturing; Nonferrous Metals; Phosphate Manufacturing; Steam Electric Power Generating; Asbestos Manufacturing; Pulp, Paper, and Paper Board; Builders Paper and Board Mills; Coal Mining; Phosphate Mining and Beneficiation; Ore Mining and Dressing; Paint Formulating; Ink Formulating; Gum and Wood Chemicals Manufacturing; Pesticides Chemicals Manufacturing; Explosives Manufacturing; Battery Manufacturing; Mechanized Scallop Processing; Distilled, Rectified, and Blended Liquors; Sugar Cane Processing.
1424a. Surface water discharges
1428$7500
1429b. Non-surface water discharges only
1434$6000
14352. Wastewater permits for Group 2 industrial wastewater treatment facilities which discharge process wastewater, as defined in Rule 145362-620.200, 1454F.A.C., from the following industry categories: Cement Manufacturing; Leather Tanning and Finishing; Glass Manufacturing; Rubber Processing; Carbon Black Manufacturing; Metal Molding and Casting; Coil Coating; Porcelain Enameling; Aluminum Forming; Copper Forming; Electrical and Electronic Components; Nonferrous Metals Forming and Metal Powders.
1495a. Surface water discharges
1499$5000
1500b. Non-surface water discharges only
1505$4000
15063. Wastewater permits for Group 3 industrial wastewater treatment facilities which discharge process wastewater, as defined in Rule 152462-620.200, 1525F.A.C., from the following industry categories: Bulk Oil Terminals, Drawdown and Loading Rack Discharges; Dairy Products; Canned and Preserved Fruits and Vegetables; Canned and Preserved Seafood; Concrete Batch Plants; Timber Products; Mineral Mining and Processing; Peat Mining; Plastic Molding and Forming; Aquaculture Facilities.
1568a. Surface water discharges
1572$2500
1573b. Non-surface water discharges only
15784. Wastewater permits for Group 4 industrial wastewater treatment facilities which discharge industrial wastewater from the following: Animal Feeding Operations, Feedlots, Egg Production Facilities.
1602$2000
1603a. Feedlots with greater than the number of animals listed in subsection 161562-670.200(3) 1616or
1617Rule 62-620.435, F.A.C.
1620$2500
1621b. Feedlots, Other
1624$1500
1625c. Egg Production Facility, Major
1630$2500
1631d. Egg Production Facility, Other
1636$1500
16375. Wastewater permits for Group 5 industrial wastewater treatment facilities which discharge concentrate
1650and regenerant from Reverse Osmosis, Membrane Softening, Ultrafiltration, Ion Exchange Units, and
1662similar processes at Drinking Water Treatment Facilities.
1669a. Design daily discharge flow of greater than 500,000 gpd
1680$6000
1681b. Design daily discharge flow of greater than 100,000 gpd up to 500,000 gpd
1697$4000
1698c. Design daily discharge flow of greater than 10,000 gpd up to 100,000 gpd
1714$2000
1715d. Design daily discharge flow of 10,000 gpd or less
1726$750
17276. Wastewater permits for Group 6 industrial wastewater treatment facilities which discharge once-through non-contact cooling water.
1743a. Greater than 100 million BTU/hour heat loss
1751$6000
1752b. Greater than 20 million BTU/hour, up to 100 million BTU/hour
1763$3000
1764c. Greater than 1 million BTU/hour, up to 20 million BTU/hour heat loss
1777$1500
1778d. 1 million BTU/hour, or less, heat loss
1786$500
17877. Wastewater permits for industrial wastewater treatment facilities in industry categories not specified in Groups 1 through 3 which discharge process wastewater to surface waters, or industrial wastewater treatment facilities which discharge non-process wastewater, as defined in Rule 182562-620.200, 1826F.A.C., but excluding once-through non-contact cooling water, to surface waters.
1836a. Design daily flow of greater than 500,000 gpd
1846$5000
1847b. Design daily flow of greater than 100,000 gpd up to 500,000 gpd
1862$3000
1863c. Design daily flow of greater than 50,000 gpd up to 100,000 gpd
1878$2000
1879d. Design daily flow of 50,000 gpd or less
1889$1000
18908. Wastewater permits for industrial wastewater treatment facilities in industry categories not specified in Groups 1 through 3 which discharge process wastewater to other than surface waters, or industrial wastewater treatment facilities which discharge non-process wastewater, as defined in Rule 193062-620.200, 1931F.A.C., but excluding once-through non-contact cooling water, to other than surface waters.
1943a. Design daily flow of greater than 500,000 gpd
1953$4000
1954b. Design daily flow of greater than 100,000 gpd up to 500,000 gpd
1969$2500
1970c. Design daily flow of greater than 50,000 gpd up to 100,000 gpd
1985$1500
1986d. Design daily flow of 50,000 gpd or less
1996$750
19979. Wastewater permits for industrial wastewater treatment facilities which recycle the wastewater and have no discharge to surface or ground waters, and are not otherwise exempt from permitting.
2025a. Facilities recycling greater than 10,000 gpd
2033$500
2034b. Facilities recycling 10,000 gpd or less
2042$100
204310. Minor revisions, as defined in subsection 205062-620.200(24), 2051F.A.C., to wastewater permits for industrial wastewater facilities other than minor modifications of permits listed in paragraph 206862-4.050(4)(q), 2069F.A.C.
2070a. Facilities which have no discharge to surface or ground waters
2081$100
2082b. All others
2085$250
208611. Substantial revisions, as defined in subsection 209362-620.200(45), 2094F.A.C., to wastewater permits for existing industrial wastewater facilities shall require a new wastewater permit application and applicable fee. The applicable fee shall be:
2118a. For substantial revisions resulting from substantial modifications to the facility which require an antidegradation determination as specified in Rule 213862-4.242, 2139F.A.C., or which increase the permitted capacity of the treatment or disposal system, the full applicable application fee.
2157b. For substantial revisions resulting from substantial modifications to the facility, but which do not require an antidegradation determination as specified in Rule 218062-4.242, 2181F.A.C., and which do not increase the permitted capacity of the treatment or disposal system, 50 percent of the applicable application fee.
2203c. For substantial revisions not associated with substantial modifications to the facility, 20 percent of the applicable application fee or $250, whichever is greater.
222712. The fee for review of engineering reports for new industrial facilities shall be in the same amount as the applicable application processing fee for the facility and shall be in addition to the application processing fee.
226413. Industrial wastewater general and generic permits.
2271a. General and generic permits requiring Professional Engineer or Professional Geologist certification
2283$500
2284b. General and generic permits not requiring Professional Engineer or Professional Geologist certification
2297$100
229814. Collection systems for industrial wastewater treatment facilities.
2306$500
230715. A permitted facility which falls in more than one of the fee categories in subparagraphs (4)(c)1. through 8. shall not be subject to multiple fees, but shall pay the larger of the fees.
2341(d) Stormwater facilities or activities regulated under Section 2349403.0885, F.S.
23511. Generic Permit for Stormwater Discharge from Large and Small Construction Activities.
2363a. Activities disturbing 5 or more acres (large)
2371$400
2372b. Activities disturbing 1 acre of land or greater and less than 5 acres (small)
2387$250
23882. Multi-Sector Generic Permit for Stormwater Discharge Associated with Industrial Activity
2399$500
24003. No Exposure Certification for Exclusion from NPDES Stormwater Permitting
2410$200
24114. Stormwater discharge associated with industrial activity permitted under Chapter 62-620, F.A.C.
2423$1,000
24255. Generic Permit for Discharge of Stormwater from Phase II Municipal Separate Storm Sewer Systems (MS4s):
2441a. Phase II MS4s in jurisdiction with a population of 50,000 or greater as determined by the 2000 Decennial Census by the U.S. Bureau of Census
2468$11,700
2470b. Phase II MS4s in a jurisdiction with a population of greater than 10,000 but less than 50,000 as determined by the 2000 Decennial Census by the U.S. Bureau of Census
2503$7,988
2505c. Phase II MS4s in a jurisdiction with a population of 10,000 or less as determined by the 2000 Decennial Census by the U.S. Bureau of Census; Florida Department of Transportation facilities
2538$5,625
2540(e) Wetland Resource Management (Dredge and Fill) Permits. This paragraph pertains to projects that have been grandfathered according to Sections 2560373.414(11) 2561(1994 Supp.), (12)(a) (1994 Supp.), (13), (14), (15) or (16), F.S., and projects, or portions thereof, located in the Northwest Florida Water Management District.
25851. Dredge and fill construction projects up to and including 5 years:
2597a. Standard form projects including dredge and fill activities that affect 10 or
2610$4,000
2612more acres of jurisdictional area pursuant to subsection 262062-312.070(2), 2621F.A.C.
2622b. Standard form construction projects that involve the construction of new docking
2634facilities pursuant to Rule 263862-312.070, 2639F.A.C., that provide:
2642(I) 50 or more new boat slips
2649$4,000
2651(II) 25 to 49 new boat slips
2658$4,000
2660(III) 10 to 24 new boat slips
2667$2,480
2669(IV) 3 to 9 new boat slips
2676$830
2677(V) 0 to 2 new boat slips
2684$500
2685c. Short form construction projects involving dredging or filling of 9.99 acres or less of jurisdictional
2701area, pursuant to subsection 270562-312.070(2), 2706F.A.C.
2707$830
2708d. Short form construction projects involving the construction of new docking or boardwalk facilities,
2722pursuant to Rule 272562-312.070, 2726F.A.C., that provide:
2729(I) 0 to 2 new boat slips
2736$500
2737(II) 3 to 9 new boat slips
2744$830
2745(III) The addition of 3 to 20 docking slips to existing functional docking facilities where the total facility
2763will not exceed 50 slips and the existing and proposed slips are not associated with commercial facilities or
2781facilities which provide supplies or services required for boating activities.2791$760
2792e. Short form and standard form projects solely for environmental restoration or enhancement activities,
2806provided such activities are not associated with a mitigation bank and are not being implemented as
2822mitigation for other activities that require a permit under Part IV of Chapter 373, F.S.2837$250
28382. Dredge and fill construction permits in excess of 5 years:
2849a. Short form permits from 6 years up to and including 10 years
2862$4,950
2864b. Standard form permits for 6 years
2871$10,650
2873c. Standard form permits for 7 years
2880$12,430
2882d. Standard form permits for 8 years
2889$14,200
2891e. Standard form permits for 9 years
2898$15,980
2900f. Standard form permits for 10 years
2907$17,750
2909g. Standard form permits for 11 years
2916$19,530
2918h. Standard form permits for 12 years
2925$21,300
2927i. Standard form permits for 13 years
2934$23,080
2936j. Standard form permits for 14 years
2943$24,850
2945k. Standard form permits for 15 years
2952$25,000
2954l. Standard form permits for 16 years
2961$25,000
2963m. Standard form permits for 17 years
2970$25,000
2972n. Standard form permits for 18 years
2979$25,000
2981o. Standard form permits for 19 years
2988$25,000
2990p. Standard form permits for 20 years
2997$25,000
2999q. Standard form permits for 21 years
3006$25,000
3008r. Standard form permits for 22 years
3015$25,000
3017s. Standard form permits for 23 years
3024$25,000
3026t. Standard form permits for 24 years
3033$25,000
3035u. Standard form permits for 25 years
3042$25,000
3044v. 6 to 10-year permits for beach restoration projects approved pursuant to Chapter 161, F.S., and to
3061maintenance dredge navigation channels, port harbors, turning basins and harbor berths located within
3074deepwater ports, pursuant to Section 3079403.816, F.S.3081$5,000
3083w. Permits for phosphate and attapulgite mines with a duration of greater than 25 years pursuant to the provisions of Section 3104373.414(15), F.S.
3106$25,000
3108x. Modifications involving permits issued pursuant to Section 3116403.816, F.S., 3118or Chapter 62-45, F.A.C.
3122$1,000
3124y. 6 to 25-year permits pursuant to Chapter 62-45, F.A.C., and all permits under Section 3139403.816, F.S.
3141$5,000
3143z. Short form and standard form projects solely for environmental restoration or enhancement activities,
3157provided such activities are not associated with a mitigation bank and are not being implemented as mitigation
3174for other activities that require a permit under Part IV of Chapter 373, F.S.3188$250
31893. Mitigation Banks
3192a. Mitigation Bank Permit, other than Conceptual Approval Permit
3201$6,050
3203b. Credit Release (credit available for sale)
3210$330
3211c. Credit Withdrawal (actual use of credit)
3218$0
3219d. Mitigation Bank Conceptual Approval Permit
3225$6,050
3227e. Major 3229modifications involving changes to one or more of the following components: service area; credit assessment; success or release criteria; hydrologic structures or alterations; construction or mitigation design that does not increase the project area; elimination of lands; or monitoring or management plans:
3271(I) Affecting one of the above components
3278$1,340
3280(II) Affecting two of the above components
3287$2,680
3289(III) Affecting three of the above components
3296$4,020
32984. Modifications:
3300a. Major modifications of Standard Form and Short Form Permits, as determined by Rule 331462-312.100, 3315F.A.C., and mitigation banks under Chapter 62-342, F.A.C., 3323that increase the project area or involve four or more of the components listed in sub-subparagraph 333962-4.050(4)(e)3.e., 3340F.A.C., 3341other than for Class I solid waste disposal facilities or as otherwise specified above
3355Same fee as
3358for a new
3361application
3362for the
3364activity
3365b. Minor modifications of Standard Form and Short Form Permits, including mitigation banks, where the modification will not require substantial technical evaluation by the Department, will not lead to substantially different environmental impacts or will lessen the impacts of the original permit, and as further determined by Rule 341362-312.100, 3414F.A.C., other than for Class I solid waste disposal facilities or as otherwise specified above:
3429(I) To correct minor errors or typographical mistakes and that do not involve technical review
3444$0
3445(II) To incorporate changes requested by the Department or required through permits issued by other regulatory agencies, and to change due dates for reporting or performance deadlines when such changes in the due date do not involve any new work, any new work locations, or any new activities, and will not alter, replace, or otherwise eliminate the requirements for otherwise performing the work required by the permit
3512$0
3513(III) That consist of transfers of permits or time extensions
3523$80
3524(IV) That consist of minor technical changes which involve new work, new work locations, new activities, or any other change which alters, replaces, or otherwise eliminates the work authorized by the permit when the original permit fee of the issued permit is less than $300, except for modifications to permits issued pursuant to Section 3578403.816, F.S.
3580$250
3581(V) That consist of minor technical changes which involve new work, new work locations, new activities, or any other change which alters, replaces, or otherwise eliminates the work authorized by the permit when the original permit fee of the issued permit is more than or equal to $300, except for permits issued pursuant to Section 3636403.816, F.S.
3638$420
3639(VI) For minor modifications for Class I solid waste disposal facilities
3650$2,110
36525. For the purposes of determining the fee for wetlands resource management permits, the term of duration for the permit shall be reduced by the period of time (in yearly increments) during which no dredging or filling activity occurs or no reclamation, restoration, or mitigation occurs and only minor monitoring and maintenance activities are required. The fee for the full term shall be submitted with the application. After the Department determines the period of time that the term of the permit can be reduced, the excess fee shall be returned.
37426. For permit applications which involve a combination of the project fee categories listed above, the highest fee that applies to the appropriate standard form or short form project, pursuant to Rule 377462-312.070, 3775F.A.C., shall be charged.
37797. Variances from permitting standards, permit conditions, or water quality standards associated with a wetland resource or mangrove alteration permit application:
3800a. Under Section 3803403.812, F.S.
3805(I) From the prohibition of subsection 381162-312.080(7), 3812F.A.C.
3813$170
3814(II) Other variances
3817$830
3818b. Under Section 3821120.542, F.S.
3823$0
38248. Verification of qualification to use a general permit, except:
3834$250
3835a. Paving of existing municipally owned roads under Rule 384462-312.824, 3845F.A.C.
3846$0
3847b. Environmental enhancement and restoration activities conducted by the U.S. Army Corps of Engineers under Rule 386362-312.825, 3864F.A.C.
3865$0
38669. Verification that an activity is exempt from regulation under Section 3877403.813, F.S., 3879or Part IV of Chapter 373, F.S.
3886$100
3887(f) Mangrove Alteration and Trimming
38921. Alteration of less than 20 mangroves under Section 3901403.9328, F.S.
3903$420
39042. Alteration of 20 or more mangroves under Section 3913403.9328, F.S.
3915$830
39163. General Permit under Section 3921403.9327, F.S.
3923$250
39244. Verification of an exemption for trimming or alteration
3933$0
39345. Minor modification, other than transfer & time extensions
3943$250
39446. Transfer of ownership or permit
3950$90
39517. Time extension
3954$90
39558. Variance under Section 3959403.9333, F.S.
3961$170
3962(g) Stormwater Permits under Chapter 62-25, F.A.C.
39691. Notice to use stormwater general permit per paragraphs 397862-25.801(1)(a) 3979through (d), F.A.C.
3982$420
39832. Conversion of construction permit to operation
3990$100
3991(h) Environmental Resource Permits. 3995Processing fees required by the Department and the Northwest Florida Water Management District (NWFWMD) for activities regulated under Chapter 62-330, F.A.C., are listed below. For purposes of determining the applicable processing fee, the terms “activity,” “project,” “project area,” and “works” are as defined in Section 2.0 of the Applicant’s Handbook Volume I incorporated by reference in paragraph 405562-330.010(4)(a), 4056F.A.C.
40571. Activities qualifying for an Agency’s electronic self-certification:
4065a. Self-certification in accordance with the general permit under Section 4075403.814(12), F.S.
4077$0
4078b. Self-certification for activities other than those under Section 4087403.814(12), F.S.
4089$0
40902. Determination of qualification for an activity exemption
4098a. Under Rules 410162-330.050 4102and 410362-330.051, 4104F.A.C.
4105$100
4106b. Under Rule 410962-330.0511, 4110F.A.C.
4111$0
41123. Determination of qualification to use a general permit
4121$250
41224. Individual or conceptual approval permit, excluding permits for a mitigation bank:
4134a. New application – the processing fee for a new permit application shall be as determined from the categories below:
4154(I) Total project area of less than 10 acres and less than 1 acre of works in, on, or over wetlands and other surface waters, and less than 10 new boat slips
4186$420
4187(II) Project exceeds any of the thresholds in 4.a.(I), above, but involves a total project area of less than 40 acres, less than 3 acres of works in, on, or over wetlands and other surface waters, and less than 30 new boat slips
4230$1,500
4232(III) Project exceeds any of the thresholds in 4.a.(II), above, but involves a total project area of less than 100 acres, less than 10 acres of works in, on, or over wetlands and other surface waters, and less than 50 new boat slips
4275$5,000
4277(IV) Project exceeds any of the thresholds in 4.a.(III), above, but involves a total project area of less than 640 acres, and less than 50 acres of works in, on, or over wetlands and other surface waters
4314$9,000
4316(V) Project exceeds any of the thresholds in 4.a.(IV), above
4326$14,000
4328(VI) Project exclusively for agricultural or silvicultural purposes; the fee for projects that are solely for agricultural or silvicultural purposes shall be the same as that required by the Water Management District in which the majority of the project area is located, in accordance with Rule 437440A-44.201, 4375F.A.C, (7-1-98) incorporated by reference herein (4382http://www.flrules.org/Gateway/reference.asp?No=Ref-026804384); and Rules 438740B-1.706, 438840C-1.603, 438940D-1.607, 4390or 439140E-1.607, 4392F.A.C., as applicable, as incorporated by reference in Rule 440162-330.071, 4402F.A.C.
4403The fee shall be the
4408same as that required
4412by the Water
4415Management District
4417in which the
4420majority of the
4423project area is
4426located.
4427(VII) Individual or conceptual approval permit solely for environmental restoration or enhancement, provided such activities are not associated with a mitigation bank and are not being implemented as mitigation for other activities that require a permit under Part IV of Chapter 373, F.S. For purposes of this provision, the term “environmental restoration or enhancement” means an action or actions designed and implemented solely to convert degraded or altered uplands, wetlands, or other surface waters to intact communities typical of those historically present, or to improve the quality and condition of currently degraded wetlands or other surface waters to a more healthy, functional, and sustaining condition for fish, wildlife, and listed species
4538$250
4539(VIII) Individual or conceptual approval permit solely to retrofit an existing stormwater management system or to add treatment to and reduce stormwater pollutant loadings from an existing stormwater management system
4569$250
4570(IX) Individual permit to construct, alter, maintain or operate a project that is consistent with a valid conceptual approval permit
459050% of the fee otherwise required for an individual permit under 4.a.(I) through (VIII), above, but not below the minimum required processing fee of $250
4615b. M4617ajor modification exceeding any of the thresholds in subsection 462662-330.315(3), 4627F.A.C.
4628Same fee as for new permit for the same activity under 4.a.(I) through (IX), above
46435. Individual or conceptual approval permit for a mitigation bank:
4653a. New application
4656$6,050
4658b. Major modification exceeding any of the thresholds in subsection 466862-330.315(3), 4669F.A.C.:
4670(I) Major modification affecting one of the following: the service area, credit assessment, success or release criteria, hydrologic structures or alterations, elimination of lands, monitoring or management plans, or construction or mitigation design that does not increase the project area
4710$1,340
4712(II) Affecting two of the components in 5.b.(I), above
4721$2,680
4723(III) Affecting three of the components in 5.b.(I), above
4732$4,020
4734(IV) All other major modifications
4739$6,050
4741c. Mitigation bank credit release
4746$330
4747d. Mitigation bank credit withdrawal
4752$0
47536. Minor modification of an individual or conceptual approval permit, including a permit for a mitigation bank, that does not exceed any of the thresholds in subsection 478062-330.315(3), 4781F.A.C.:
4782a. Extension of permit duration, where not exempt from payment of fees under Florida Statutes
4797$80
4798b. To correct minor errors that do not involve technical review
4809$0
4810c. To transfer ownership of a permit or to transfer the permit to an operation and maintenance entity
4828$0
4829d. All other minor modifications
4834$250
48357. Variance or waiver:
4839a. Under Section 4842120.542, F.S.
4844$0
4845b. Under Section 4848373.414(17), F.S.
4850$170
48518. Fee reductions:
4854a. Applications for an individual or conceptual approval permit or modification thereof submitted using the Agency’s electronic application system where the processing fee in subparagraph (h)4. or 5., above exceeds $250
4885Fee shall be reduced by $100, but not below the minimum required processing fee of $250
4901b. Applications for any activity by an entity qualifying under Section 4912218.075, F.S. 4914when the fee under paragraph (h) exceeds $100
4922$100
4923c. Applications for any activity when submitted by the U.S. Department of Defense
4936$0
4937(i) Determinations of the Landward Extent of Wetlands and Other Surface Waters:
49491. Informal determination 4952‒ fees shall be based on the acreage of the entire property for which the request applies, as follows:
4971a. Total area to be included in the determination is up to 1 acre
4985$100
4986b. Additional fee per acre (or portion thereof) beyond the first acre; total fe5000e not to exceed $500
5005$50
50062. Petitions for formal determination ‒ fees shall be based on the acreage of the entire property for which the petition is filed, as follows:
5031a. Total area to be included in the determination is less than 10 acres
5045$780
5046b. Tot5048al area to be included in the determination is at least 10, but less than 40 acres
5065$1,060
5067c. Total area to be included in the determination is at least 40, but no more than 100 acres
5086$2,110
5088d. Additional fee per 100 acres (or portion thereof) beyond the first 100 acres
5102$290
51033. Reissuance of a formal determination, in accordance with section 7.2.4 of Applicant’s Handbook Volume I.
5119$350
5120(j) Solid Waste Permits.
51241. Construction permit for a Class I facility.
5132$10,000
51342. Construction permit for a Class II facility.
5142$10,000
51443. Construction permit for a Class III facility.
5152$6000
51534. Construction permit for a waste-to-energy facility not covered by the Electric Power Plant Siting Act.
5169$10,000
51715. Construction permit for other resource recovery facilities.
5179$2000
51806. Construction permit for an incinerator.
5186$3000
51877. Construction permit for a yard trash composting facility.
5196$2000
51978. Construction permit for a manure composting facility.
5205$2000
52069. Construction permit for a solid waste composting facility.
5215$5000
521610. Construction/operation permit for a waste tire processing facility.
5225$1250
522611. Construction permit for all other solid waste facilities.
5235$1000
523612. Construction permit for an offsite Biohazardous Waste Treatment
5245$2000
5246Facility other than a biohazardous waste incinerator.
525313. Construction permit and/or an operation permit for a facility which has multiple solid waste management components which normally would require individual solid waste permits. A single application may be submitted and the permit fee will be the sum of each individual permit; however, the total permit fees for the facility shall not exceed $25,000, exclusive of modifications and renewals.
531414. Operation permit for a Class I facility.
5322$10,000
532415. Operation permit for a Class II facility.
5332$10,000
533416. Operation permit for a Class III facility.
5342$4000
534317. Operation permit for a waste-to-energy facility not covered by the Electric Power Plant Siting Act.
5359$10,000
536118. Operation permit for other resource recovery facilities.
5369$1000
537019. Operation permit for an incinerator.
5376$1000
537720. Operation permit for a yard trash composting facility.
5386$1000
538721. Operation permit for a manure composting facility.
5395$1000
539622. Operation permit for a solid waste composting facility.
5405$3000
540623. Operation permit for an offsite Biohazardous Waste Treatment Facility other than a biohazardous waste incinerator.
5422$1000
542324. Operation permit for all other solid waste facilities.
5432$500
543325. Request for an Alternate Procedure.
5439a. Landfill
5441$2000
5442b. Other
5444$500
544526. Research, Development and Demonstration permits (one year permit).
5454$1000
545527. Closure permit for a Class I facility.
5463$7500
546428. Closure permit for a Class II facility.
5472$7500
547329. Closure permit for a Class III facility.
5481$4000
548230. Closure permit for all other solid waste facilities.
5491$1000
549231. Renewal of Closure permit for landfills which address only long term care.
5505$1000
550632. Construction or Operation permits for Materials Recovery Facility.
5515$2000
551633. Ground Water Monitoring Plan Approvals for solid waste landfills with no other Department permit.
5531$500
5532(k) Petroleum Cleanup General Permits.
55371. Soil thermal treatment – mobile.
5543$500
55442. Soil thermal treatment – stationary.
5550$500
5551(l) Hazardous Waste Permits.
55551. Construction of container and/or tank hazardous waste storage facilities.
5565$15,000
55672. Construction of container and/or tank hazardous waste storage and treatment facilities.
5579$20,000
55813. Construction of landfill, surface impoundment, waste pile, land treatment, and miscellaneous unit facilities.
5595$25,000
55974. Construction of hazardous waste storage, treatment and/or disposal facilities with an incinerator, boiler or industrial furnace for treatment of hazardous wastes generated on-site.
5621$25,000
56235. Construction of commercial treatment, storage, and/or disposal facility with a commercial incinerator, boiler or industrial furnace managing hazardous wastes generated off-site.
5645$32,500
56476. Operation of container and/or tank hazardous waste storage facilities.
5657$10,000
56597. Operation of container and/or tank hazardous waste storage and treatment facilities.
5671$10,000
56738. Operation of landfill, surface impoundment, waste pile, land treatment, and miscellaneous unit facilities.
5687$15,000
56899. Operation of hazardous waste storage, treatment and/or disposal facilities with an incinerator, boiler or industrial furnace for treatment of hazardous wastes generated on-site.
5713$15,000
571510. Operation of commercial treatment, storage, and/or disposal facilities with a commercial incinerator, boiler or industrial furnace managing hazardous wastes generated off-site.
5737$32,500
573911. Closure of container and/or tank hazardous waste storage facilities.
5749$10,000
575112. Closure of container and/or tank hazardous waste storage and treatment facilities.
5763$10,000
576513. Closure of landfill, surface impoundment, waste pile, land treatment, previously closed
5777units required to demonstrate equivalent clean closure, and miscellaneous unit facilities.
5788$20,000
579014. Closure of hazardous waste storage, treatment and/or disposal facilities with an incinerator, boiler or industrial furnace for treatment of hazardous wastes generated on-site.
5814$15,000
581615. Closure of commercial treatment, storage, and/or disposal facilities with a commercial incinerator, boiler or industrial furnace managing hazardous wastes generated off-site.
5838$32,500
584016. Hazardous waste research, development and demonstration facilities.
5848$4000
584917. Fees for modifications to hazardous waste permits proposed by the permittee or required by Department rules shall be determined as stated below. All modifications listed below require public notice. Contact the appropriate District Office for guidance on how to determine which fee applies before submitting the required information.
5898a. Substantial modifications that require significant changes to the existing permit and require an extensive evaluation by the Department. These shall require the same fee as a new application. Examples in this category include alteration of the existing facility, change in the facility plan, ground water monitoring program assessment or remediation/engineering design or other general facility standard. The fee schedule for new permit applications is listed above.
5965b. Substantial modifications that require a moderate technical evaluation by the Department. Examples in this category include alterations of the existing facility or its operation which will require additional site-specific evaluation.
5996$10,000
5998c. Moderate modifications that require moderate technical evaluation by the Department. These require a new site inspection, lead to different environmental impacts, or lessen the impacts of the original permit.
6028$5,000
6030d. Minor modifications, as defined in this subsection, that are not otherwise specified, including common or frequently occurring changes needed to maintain a facility’s capacity to manage wastes safely, minor changes in ground water monitoring plans, or modifications to conform to new requirements.
6073$1,000
607518. Department variance from federal regulations under 608240 CFR 260.30.
6085$32,500
608719. All other hazardous waste facility permits or authorizations for which a specific fee is not specified.
6104$32,500
6106(m) Underground Injection Control Permits.
61111. Construction permit for each Class I test/injection well.
6120$12,500
61222. Construction permit for each Class I exploratory well.
6131$5,000
61333. Construction permit for each monitoring well associated with a Class I injection facility when not permitted under a Class I exploratory well or Class I test/injection well permit.
6162$1,000
6164per well not to exceed
6169$10,000 for the facility
61744. Permit to convert each well from a Class I to a Class V well.
6189$10,000
61915. Operation permit for each Class I well.
6199$10,000
62016. Permit to convert a Class I injection well or exploratory well to a monitoring well when not proposed under a construction permit.
6224$500
62257. Abandonment permit for each Class I well.
6233$100
62348. Construction permit for each Class III well.
6242$1,000
62449. Operation permit for each Class III well.
6252$1,000
625410. Abandonment permit for each Class III well.
6262$100
626311. Construction permit for each Class V well.
6271$750
627212. Operation permit for each Class V well.
6280$750
628113. Abandonment permit for each Class V well.
6289$25
629014. General permit for each Class V well.
6298a. General permits requiring Professional Engineer or Professional Geologist certification
6308$250
6309b. General permits not requiring Professional Engineer or Professional Geologist certification
6320$25
632115. Major modifications are modifications to an injection facility requiring substantial technical evaluation by the Department, and which will not lead to substantially different environmental impacts (unless those impacts will lessen the impacts of the original permit).
6358a. Major modification to a Class I injection facility.
6367$1,000
6369b. Major modification to a Class III injection facility.
6378$500
6379c. Major modification to a Class V injection facility.
6388$250
638916. Minor modifications are modifications to an injection facility that do not require a substantial technical evaluation by the Department, will not result in increased capacity of the injection system, do not require a new site inspection by the Department, and will not lead to substantially different environmental impacts or will lessen the impacts of the original permit.
6447a. Minor modification to a Class I or Class III injection facility.
6459$250
6460b. Minor modification to a Class V injection facility.
6469$100
647017. Rerating of the permitted capacity of a Class I injection well to the maximum injection velocity allowed under paragraph 62-28.230(1)(e), F.A.C.
6492$250
6493(n) Drinking Water (Public Water Supply) Permits.
65001. Construction permit for each Category I through III treatment plant, as defined in Rule 651562-699.310, 6516F.A.C.
6517a. Treatment plant – 5 MGD and above
6525$12,500
6527b. Treatment plant – 1 MGD up to 5 MGD
6537$10,000
6539c. Treatment plant – 0.25 MGD up to 1 MGD
6549$7,000
6551d. Treatment plant – 0.1 MGD up to 0.25 MGD
6561$4,000
6563e. Treatment plant – up to 0.1 MGD
6571$2,000
65732. Construction permit for each Category IV treatment plant, as defined in Rule 658662-699.310, 6587F.A.C.
6588a. Treatment plant – 5 MGD and above
6596$12,500
6598b. Treatment plant – 1 MGD up to 5 MGD
6608$10,000
6610c. Treatment plant – 0.25 MGD up to 1 MGD
6620$7,000
6622d. Treatment plant – 0.1 MGD up to 0.25 MGD
6632$4,000
6634e. Treatment plant – .01 MGD up to 0.1 MGD
6644$2,000
6646f. Treatment plant – up to 0.01 MGD
6654$800
66553. Construction permit for each Category V treatment plant, as defined in Rule 666862-699.310, 6669F.A.C.
6670a. Treatment plant – 5 MGD and above
6678$10,000
6680b. Treatment plant – 1 MGD up to 5 MGD
6690$6,000
6692c. Treatment plant – 0.25 MGD up to 1 MGD
6702$2,000
6704d. Treatment plant – up to 0.25 MGD
6712$1,000
6714e. Treatment plant – up to 0.1 MGD
6722$600
67234. Distribution and transmission systems, including raw water lines into the plant, except those under general permit.
6740a. Serving a community public water system
6747$900
6748b. Serving a non-transient non-community public water system
6756$700
6757c. Serving a non-community public water system
6764$500
67655. Construction permit for each public water supply well.
6774a. Well located in a delineated area pursuant to Chapter 62-524, F.A.C.
6786$1,000
6788b. Any other public water supply well.
6795$500
67966. Major modifications to systems that alter the existing treatment without expanding the capacity of the system and are not considered substantial changes pursuant to subsection 682262-4.050(7), 6823F.A.C., below.
6825a. 1 MGD and above
6830$4,000
6832b. 0.1 MGD up to 1 MGD
6839$2,000
6841c. 0.01 MGD up to 0.1 MGD
6848$1,000
6850d. Up to 0.01 MGD
6855$500
68567. Minor modifications to systems that result in no change in the treatment or capacity.
6871a. 0.1 MGD and above
6876$1,000
6878b. Up to 0.1 MGD
6883$500
68848. General Permit fee for any General Permit not specifically in subparagraphs 1. through 7. above:
6900a. General permits requiring Professional Engineer or Professional Geologist certification.
6910$650
6911b. General permits not requiring Professional Engineer or Professional Geologist certificaiton.
6922$500
6923(o) Temporary operation permits shall be 20 percent over the fee for the operation permit for the activity to be permitted.
6944(p) General Permit fee for any General Permit not specifically listed in paragraphs (a) through (l).
69601. General permits requiring Professional Engineer or Professional Geologist certification
6970$250
69712. General permits not requiring Professional Engineer or Professional Geologist certification.
6982$100
6983(q) Unless otherwise specified in this rule, the fee for applications for relief mechanisms shall be as follows:
70011. Site specific alternative criteria for each application
7009$15,000
70112. Variance or exemption for each water quality criteria
7020$6000
70213. Variance or exemption for public water system from maximum contaminant level/treatment techniques
7034$1000
70354. Variance from other permitting standards or conditions
7043$2000
70445. Aquifer exemption – major
7049$15,000
70516. Aquifer exemption – minor
7056$7500
7057(r) Permits to construct or operate any other type of facility or stationary installation not specifically listed in paragraphs (a) through (n).
7079$100
7080(s) Minor modifications of permits that do not require substantial technical evaluation by the Department, do not require a new site inspection by the Department, and will not lead to substantially different environmental impacts or will lessen the impacts of the original permit:
71231. To correct minor errors or typographical mistakes and that do not involve technical review
7138$0
71392. To incorporate changes requested by the Department or required through permits issued by other regulatory agencies, and to change due dates for reporting or performance deadlines when such changes in the due date do not involve any new work, any new work locations, or any new activities, and will not alter, replace, or otherwise eliminate the requirements for otherwise performing the work required by the permit
7206$0
72073. That consist of transfers of permits or time extensions
7217$50
72184. That consist of minor technical changes which involve new work, new work locations, new activities, or any other change which alters, replaces, or otherwise eliminates the work authorized by the permit when the original permit fee of the issued permit is less than $300, except for modifications to permits issued pursuant to Section 7272403.816, F.S.
7274$50
72755. That consist of minor technical changes which involve new work, new work locations, new activities, or any other change which alters, replaces, or otherwise eliminates the work authorized by the permit when the original permit fee of the issued permit is more than or equal to $300, except for Domestic Wastewater Facility Permits, Industrial Wastewater Facility Permits, Drinking Water (Public Water Supply) Permits, Underground Injection Control Permits and permits issued pursuant to Section 7349403.816, F.S.
7351$250
7352(t) For purposes of requiring a permit application and fee for the following facility types, each non-contiguous project shall be considered a stationary installation and shall require a separate application and fee.
73841. Domestic wastewater collection system.
73892. Drinking water distribution system.
7394(u) All fees shall be deposited in the Florida Permit Fee Trust Fund created pursuant to Section 7411403.087(5), F.S.
7413(v) If the department requires by rule or permit condition that any specific permit be renewed more frequently than once every five years, the permit fee shall be prorated based upon the permit fee schedule in effect at the time of permit renewal. Upon issuance of such a permit, a prorated refund of the fee shall be returned to the applicant. This provision does not apply to permits issued for less than five years which could be extended to five years without the filing of an application for renewal. However, applications for permits to continue operation of a facility where an existing permit has or is about to expire in accordance with Section 7526403.087(1), F.S., 7528shall be accompanied by the appropriate processing fee.
7536(w) This fee schedule does not apply to applications for certification pursuant to Sections 288.501-.518, F.S., Florida Industrial Siting Act; Sections 341.321-.386, F.S., the High Speed Rail Transportation Commission, except that fees may be assessed for the permitting of Ancillary Facilities under the Act for which a master plan approval was granted under the Act; to Sections 403.501-.519, F.S., Florida Electrical Power Plant Siting Act; or to Sections 403.52-.539, F.S., the Transmission Line Siting Act.
7611(x) This fee schedule will supersede all other references to fees in Department rules or forms, where in conflict except as noted in paragraph 763562-4.050(4)(n), 7636F.A.C.
7637(y) In the jurisdiction of an approved local program which in accordance with an interagency agreement assists the Department in the processing of permits the fee paid to the Department shall be reduced by the amount specified in the agreement. That amount shall be commensurate with the savings to the Department resulting from the assistance of the local program.
7696(z) 7697The fees in paragraphs (e) through (i), and (n) shall be increased March 1, 2013, and at subsequent 5-year intervals, to adjust the fees for inflation using the percentage change in the 7729Consumer Price Index for the “CPI-U, U.S. City Average, All Items” established by the Bureau of Labor Statistics 7747(BLS) (7749www.bls.gov/cpi/7750), computed as provided in the BLS publication “Handbook of Methods,” Chapter 17 (7765www.bls.gov/opub/hom/pdf/homch17.pdf7766). The Department shall use the percentage change in the Consumer Price Index from March 2008 to December 2012 for the 2013 fee calculations and the 7792percentage change in the rates from March to December for subsequent five-year periods. The Department shall round any increased fees to the next highest whole ten dollar increment. In the event of deflation during the 5-year interval, the Department shall consult with the Executive Office of the Governor and the Legislature to determine whether downward fee adjustments are appropriate based on the current budget and appropriation considerations.
7859(5)(a) To be considered by the Department, each application must be accompanied by the proper processing fee. The fee shall be paid by check, payable to the Department of Environmental Protection. The fee is non-refundable except as provided in Section 7899120.60, F.S., 7901and in this section.
7905(b) When an application is received without the required fee, the Department shall acknowledge receipt of the application and shall immediately notify the applicant by certified mail that the required fee was not received and advise the applicant of the correct fee. The Department shall take no further action until the correct fee is received. If a fee was received by the Department which is less than the amount required, the Department shall return the fee along with the written notification.
7986(c) Upon receipt of the proper application fee, the permit processing time requirements of Sections 8001120.60(1) 8002and 8003403.0876, F.S., 8005shall begin.
8007(d) If the applicant does not submit the required fee within ten days of receipt of written notification, the Department shall either return the unprocessed application or arrange with the applicant for the pick up of the application.
8045(e) If an applicant submits an application fee in excess of the required fee, the permit processing time requirements of Sections 8066120.60(1) 8067and 8068403.0876, F.S., 8070shall begin upon receipt, and the Department shall refund to the applicant the amount received in excess of the required fee.
8091(6) Any substantial modification to a complete application shall require an additional processing fee determined pursuant to the schedule set forth in Rule 811462-4.050, 8115F.A.C., and shall restart the time requirements of Sections 8124120.60 8125and 8126403.0876, F.S. 8128For purposes of this subsection, the term “substantial modification” shall mean a modification which is reasonably expected to lead to substantially different environmental impacts which require a detailed review.
8157(7) Modifications to existing permits proposed by the permittee which require substantial changes in the existing permit or require substantial evaluation by the Department of potential impacts of the proposed modifications shall require the same fee as a new application for the same time duration except for modification under Chapter 62-45, F.A.C.
8209(8) The difference between the processing fee for applications for individual permits and the processing fee for general permits shall be refunded only for those applications that qualify for a general permit solely as a result of a change in Department rules while the application is being processed. Processing fees for applications for individual permits shall not be refunded in whole or in part where an applicant modifies a project to qualify for a general permit when the project did not qualify for a general permit when processing commenced.
8298Rulemaking Authority 8300373.026, 8301373.043, 8302373.109, 8303373.4131, 8304373.414, 8305373.418, 8306373.421, 8307403.061, 8308403.087, 8309403.704(30), 8310403.805 FS. 8312Law Implemented 8314373.109, 8315373.309, 8316373.409, 8317373.413, 8318373.4135, 8319373.414(9), 8320(11), (12)(a), (13), (14), (15), (16), 8326373.4145, 8327373.418, 8328373.421, 8329403.061, 8330403.087, 8331403.0877, 8332403.088, 8333403.0885, 8334403.722, 8335403.861(7) FS. 8337History–New 5-17-72, Amended 6-19-74, 7-8-82, Formerly 17-4.05, Amended 118346-15-87, 8-31-88, 10-3-88, 4-4-89, 3-19-90, 6-11-90, 3-7-91, 3-18-91, 5-30-91, 10-30-91, 11-16-92, 12-21-92, 7-11-93, 2-2-94, Formerly 17-4.050, Amended 11-23-94, 4-30-95, 7-4-95, 12-15-98, 10-22-00, 6-1-01, 1-30-03, 2-19-03, 4-3-03, 5-1-03, 2-7-06, 10-31-07, 4-21-09, 5-9-13, 10-1-13, 2-17-16.
Historical Versions(5)
Select effective date to view different version.Related Statutes:
- 120.542, F.S.
- 120.60, F.S.
- 218.075, F.S.
- 260.30., F.S.
- 373.026, F.S.
- 373.043, F.S.
- 373.109, F.S.
- 373.309, F.S.
- 373.409, F.S.
- 373.413, F.S.
- 373.4131, F.S.
- 373.4135, F.S.
- 373.414, F.S.
- 373.4145, F.S.
- 373.418, F.S.
- 373.421, F.S.
- 373.4211, F.S.
- 403.061, F.S.
- 403.087, F.S.
- 403.0876, F.S.
- 403.0877, F.S.
- 403.088, F.S.
- 403.0885, F.S.
- 403.704, F.S.
- 403.722, F.S.
- 403.805, F.S.
- 403.812, F.S.
- 403.813, F.S.
- 403.814, F.S.
- 403.816, F.S.
- 403.861, F.S.
- 403.9327, F.S.
- 403.9328, F.S.
- 403.9333, F.S.
Related DOAH Cases (5)
- 21-001939TL In Re: Orlando Utilities Commission; St. Cloud East-Magnolia Ranch North 230 Kv Transmission Line Siting Application No. Ta21-18 vs. *
- 99-002234 Brenda B. Sheridan vs. Deep Lagoon Marina, A/K/A Deep Lagoon Boat Club, Ltd., And Department Of Environmental Protection
- 99-001915 Environmental Waste Recyclers, Inc. vs. Department Of Environmental Protection
- 96-001723 Save The Manatee Club, Inc., And Friends Of The Greenway vs. Citrus Recreational Marina, Inc., And Department Of Environmental Protection
- 93-006982 Alden Ponds, Inc. vs. Department Of Environmental Protection