04-004252BID Magnum Construction Management Corporation, D/B/A Mcm Corp. vs. Broward County School Board
 Status: Closed
Recommended Order on Monday, March 21, 2005.


View Dockets  
Summary: A status-based scoring preference for former contract holders by giving extra points to favored proposers and taking points away from disfavored proposers, is contrary to competition. Recommend that the proposed award be rescinded.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8MAGNUM CONSTRUCTION MANAGEMENT ) )

13CORPORATION, d/b/a MCM CORP., )

18)

19Petitioner, )

21) Case No. 04-4252BID

25vs. )

27)

28BROWARD COUNTY SCHOOL BOARD, )

33)

34Respondent, )

36)

37and )

39)

40JAMES B. PIRTLE CONSTRUCTION )

45COMPANY, INC., )

48)

49Intervenor. )

51RECOMMENDED ORDER

53This case came before Administrative Law Judge John G.

62Van Laningham for final hearing on January 19 and 20, 2005, in

74Fort Lauderdale, Florida.

77APPEARANCES

78For Petitioner: J. Alfredo De Armas, Esquire

85Alvarez, De Armas & Borron, P. A.

923211 Ponce De Leon Boulevard, Suite 302

99Coral Gables, Florida 33134

103For Respondent: Robert Paul Vignola, Esquire

109School Board of Broward County

114K. C. Wright Administrative Building

119600 Southeast Third Avenue, 11th Floor

125Fort Lauderdale, Florida 33301

129For Intervenor: Kevin A. Fernander, Esquire

135Tripp Scott, P. A.

139AutoNation Tower, 15th Street

143110 Southeast Sixth Street

147Fort Lauderdale, Florida 33301

151STATEMENT OF THE ISSUES

155The issues in this bid protest are whether, in making a

166preliminary decision to award a public contract, Respondent

174acted contrary to a governing statute, rule, policy, or project

184specification; and if so, for each such instance, whether the

194misstep was clearly erroneous, arbitrary or capricious, or

202contrary to competition.

205PRELIMINARY STATEMENT

207Respondent Broward County School Board issued Request for

215Proposals 2021-24-01 on May 18, 2004, for the procurement of

225Design/Build services in connection with the construction of a

234middle school. Responses to the RFP were received from six

244proposers and opened on August 31, 2004. Each proposer was a

255team comprised of a building contractor and a design

264professional.

265The proposals were reviewed and short-listed by a

273Consultant's Review Committee in accordance with the Request for

282Proposals' specifications. The committee recommended that one

289of the six proposals be rejected as nonresponsive. The

298remaining five proposals were then forwarded to the board, which

308was responsible for conducting its own evaluation and making the

318award. The short-listed proposals included those of Petitioner

326Magnum Construction Management Corporation and Intervenor James

333B. Pirtle Construction Company, Inc.

338Respondent held a special meeting on October 12, 2004,

347whereat the proposers made presentations to the board and

356participated in a question-and-answer session, following which

363each board member scored every responsive proposal. Pursuant to

372the Request for Proposals, the proposer receiving the most

381points from a board member would be considered that member's

391first choice. The Request for Proposals provided for the award

401to be made, if at all, to the proposer receiving a majority of

414the first choice votes. When the votes were counted, Intervenor

424received a plurality of four first choices, and the board voted

435to award Intervenor the contract.

440Petitioner filed a formal written protest of the intended

449award on October 25, 2004. At Petitioner's request, its formal

459written protest was referred to the Florida Division of

468Administrative Hearings ("DOAH"), which held a formal hearing in

479the matter on January 19 and 20, 2005, as scheduled.

489The parties stipulated to a number of facts. The

498stipulated facts were memorialized in the record and taken as

508established without need of further proof. Additionally, Joint

516Exhibits 1-39 were admitted into evidence without objection.

524In its case, Petitioner elicited testimony from Fernando

532Munilla; Stephanie Arma Kraft; Lois Wexler; Judie S. Budnick;

541Marty Rubinstein; Darla L. Carter; Benjamin J. Williams; Adolfo

550Cotilla; Dr. Robert D. Parks; and Beverly A. Gallagher. 1

560Respondent presented the testimony of Michelle Bryant Wilcox and

569Denis Herrmann. Intervenor called one witness, Paul Carty.

577The parties stipulated to the filing of proposed

585recommended orders within 20 days after the filing of the

595transcript of the formal hearing. The transcript was filed with

605DOAH on February 9, 2005, making the proposed recommended orders

615due on March 1, 2005. All parties timely filed proposed

625recommended orders containing proposed findings of fact and

633conclusions of law. The parties' proposed recommended orders

641have been carefully considered during the preparation of this

650Recommended Order.

652Unless otherwise indicated, citations to the Florida

659Statutes refer to the 2004 Florida Statutes.

666FINDINGS OF FACT

6691. On May 18, 2004, Respondent School Board of Broward

679County ("School Board" or "SBBC") 2 issued Request for Proposals

691No. 2021-24-01 (the "RFP") to solicit offers on a contract for

703the design and construction of a middle school (the "Project").

7142. Proposals were submitted by Petitioner Magnum

721Construction Management Corporation, d/b/a MCM Corp. ("MCM");

730Intervenor James P. Pirtle Construction Company, Inc.

737("Pirtle"); Seawood Builders, a Division of Catalfumo

746Construction, LLC ("Seawood"); Stiles Construction Co.

754("Stiles"); James A. Cummings, Inc. ("Cummings"); and Skanska

766USA Building, Inc. ("Skanska"). SBBC opened these six proposals

777on August 31, 2004.

7813. In accordance with the evaluation procedure set forth

790in the RFP, the proposals were reviewed by a Consultant's Review

801Committee ("CRC"), whose task was to evaluate the proposals and

813prepare a "short list" of between three and six firms for the

825School Board, which would make the final determination. At its

835first meeting on September 14, 2004, the CRC rejected Skanska's

845proposal as nonresponsive for failing to submit an original bid

855bond. On September 30, 2004, the CRC met again and, after

866deliberating, decided to place the five remaining proposers on

875the "short list."

8784. Following the CRC's review, the evaluation proceeded

886pursuant to Section 1.21 of the RFP, which states:

895A. The Facilities and Construction

900Management Division will forward to the

906Superintendent of Schools the completed

911short-list of the Proposer's Submittal. The

917Superintendent will then forward the Short-

923List to The School Board of Broward County,

931Florida for its use in the interview and

939final selection of the successful

944Proposer(s). The short list of [sic ] will

952be forwarded to the School Board of Broward

960County, Florida unranked.

963B. The short-listed firms shall present

969their design solutions to The School Board

976of Broward County, Florida. Short-listed

981firms will be notified of the time and place

990for their respective presentations.

994Proposer may utilize any media for their

1001presentations, but shall restrict their

1006presentations to 30 minutes total (5 minutes

1013for set-up, 10 minutes for presentation, and

102015 minutes for questions and answers).

1026C. At the conclusion of the Proposer's

1033presentation to the Board, Board Members may

1040ask questions concerning the presentation,

1045the Proposer's assembled Design/Build team,

1050and the Design Criteria Professional's

1055assessment of the Proposer’s submittal or

1061topic of the Board Member's choice [sic ]

1069preliminary design concept for the project,

1075including means and methods.

1079D. At the conclusion of the presentation

1086and interview of all short-listed firms, The

1093School Board of Broward County, Florida will

1100deliberate and utilize the short-listing

1105evaluation criteria and point schedule to

1111finalize a selection of the successful

1117Proposer. The Board reserves the right to

1124award a contract for the project or award no

1133contract (reject all submittals).

1137E. During and at the conclusion of the

1145presentation and interview of all short-

1151listed firms, the School Board of Broward

1158County, Florida will assign points to each

1165Proposer utilizing the above evaluation

1170criteria and rank them according to their

1177scores. The firm receiving the most points

1184by a Board Member will be considered the

1192first choice of that Board member. The firm

1200that receives a majority of the first choice

1208votes may be awarded the contract.[ 3 ] In the

1218event of a tie, a voice vote will be taken

1228until the tie is broken. The Board reserves

1236the right to award a contract for the

1244project or award no contract.

12495. The "evaluation criteria and point schedule" referred

1257to in Section 1.21(D) and (E) are found in Section 1.20, which

1269provides as follows:

1272A. The School Board of Broward County,

1279Florida's final selection will be based on

1286the Selection Criteria Score Sheet.

1291Evaluation Criteria Maximum Points

1295Profile & Qualifications

1298of Proposer's Team 6

1302Proposed Project Scheduling 7

1306Past Work Performance

1309and References 10

1312Site Design 7

1315Building Design 23

1318Cost proposal 25

1321S.I.T. Award 15

1324MBE Participation 7________

1327Total Points Possible 100

1331B. The School Board of Broward County,

1338Florida will award points up to a maximum,

1346for evaluation criteria numbers listed above

1352as based upon an evaluation of the

1359Proposer's submittal and presentation.

13636. On October 12, 2004, the School Board held a special

1374meeting to discuss the procurement with staff, hear the

1383presentations of the short-listed proposers, and grade the

1391proposals. Eight board members participated. 4

13977. One subject that generated considerable discussion was

1405the "S.I.T. Award," an evaluation criterion worth 15 points.

1414The S.I.T. Award (the acronym stands for School Infrastructure

1423Thrift) was based on a mathematical calculation that left no

1433room for discretion. Points were awarded on a predetermined

1442scale according to the percentage by which a proposer's base

1452proposal amount fell below, or exceeded, the Project's

1460established budget as a function of cost per student station.

1470Because the allowable cost per student station is $15,390 and

1481the Project calls for 1,998 student stations, the budget, for

1492purposes of the S.I.T. Award, is $30,749,200.

15018. As the School Board's staff had determined before the

1511special board meeting on October 12, 2004, MCM's base proposal

1521amount is 15.48 percent below the S.I.T budget. The cost of

1532Cummings' proposal is 11.36 percent below the budget, Pirtle's

1541about three percent below $30.7 million, Seawood's roughly equal

1550to the budget, and Stiles' proposal 12 percent above the

1560established budget. On these percentages, using the scoring

1568scale prescribed in the RFP, MCM and Cummings were entitled to

157915 points apiece in the S.I.T. Award category, Pirtle seven

1589points, Seawood six points, and Stiles zero points. The School

1599Board was informed of these scores before its members graded the

1610proposals on the seven remaining criteria.

16169. After the proposers had made their presentations, the

1625board members individually assigned points to the proposals.

1633MCM received the highest aggregate score (713), followed by

1642Pirtle (705), Cummings (698), Seawood (668), and Stiles (541).

1651Pirtle, however, received the most first choice votes of any

1661proposer——four. Cummings received two first choice votes, and

1669MCM and Seawood were each ranked first by one member.

167910. The following table depicts the rankings by member:

1688Budnick Carter Gallagher Kraft Parks Rubinstein Wexler Williams

16961 Seawood MCM Pirtle Pirtle Cummings Pirtle Cummings Pirtle

17052 MCM Cummings MCM/Seawood Seawood MCM MCM MCM Cummings

1714(-1) (-4) (-2) (-1) (-1)

17193 Cummings Pirtle Cummings Pirtle Cummings Pirtle/Seawood MCM

17274 Pirtle Seawood Cummings MCM Seawood Seawood Seawood

17355 Stiles Stiles Stiles Stiles Stiles Stiles Stiles Stiles

1744The parenthetic numbers in the second row show by how many

1755points MCM trailed the first choice.

176111. Although Pirtle did not receive a majority of the

1771first choice votes, the School Board nevertheless voted to award

1781the contract to Pirtle. 5

178612. Pirtle has argued that MCM lacks standing to maintain

1796this protest because MCM came in tied (with Seawood) for third——

1807behind Pirtle and Cummings, respectively——according to the

1814number of first choice votes each proposal received. While the

1824RFP does not specify a procedure for ranking the proposals

1834behind the number one choice, the method suggested by Pirtle is

1845inconsistent with the RFP's plain language, which is clearly

1854intended to ensure that the contract is awarded to the first

1865choice of a majority of the board members. To determine second

1876place, the proper question is not, Who had the most first choice

1888votes after Pirtle? but rather, Who would be the first choice of

1900a majority if Pirtle were unavailable?

190613. To begin to answer the relevant question, Pirtle must

1916be removed from the rankings of the respective members, and each

1927proposer below Pirtle moved up a spot. When this is done, the

1939rankings look like this:

1943Budnick Carter Gallagher Kraft Parks Rubinstein Wexler Williams

19511 Seawood MCM MCM/Seawood Seawood Cummings MCM Cummings Cummings

19602 MCM Cummings Cummings MCM Cummings MCM MCM

19683 Cummings Seawood Cummings MCM Seawood Seawood Seawood Seawood

19774 Stiles Stiles Stiles Stiles Stiles Stiles Stiles Stiles

19865

198714. What the foregoing table shows is that without Pirtle,

1997there is no clear favorite, but essentially a three-way tie

2007between Seawood, MCM, and Cummings. Under the RFP, the School

2017Board would need to take a voice vote until one of the three

2030commanded majority support. That, of course, did not occur in

2040the event. Therefore, it is impossible to determine, on the

2050instant record, which proposer was the School Board's second

2059choice (or third or fourth choice, for that matter).

206815. On October 15, 2004, MCM timely filed a notice of

2079intent to protest the School Board's preliminary decision to

2088award Pirtle the contract. MCM followed its notice of intent

2098with a formal written protest, which was timely filed on October

210925, 2004.

211116. MCM's protest rests on two pillars. The first is a

2122contention that the School Board employed an unstated evaluation

2131criterion, namely a preference for builders who had previously

2140done work for SBBC. The second is an argument that Pirtle's

2151proposal is materially nonresponsive for failing to comply with

2160the RFP's directives on M/WBE participation. 6 The findings that

2170follow are pertinent to MCM's specific protest grounds.

217817. Regarding the alleged unstated evaluation criterion,

2185it is undisputed that the RFP does not expressly disclose that

2196past work for SBBC will or might count for more than similar

2208work for another school district. The RFP does, however,

2217contain a clear and unambiguous statement of experiential

2225preferences, in Section 1.1(E), which states:

2231The School Board of Broward County would

2238prefer to select a Design/Builder with

2244proven successful experience in the Design

2250and Construction of 3 school projects

2256completed within the past 5 years in the

2264State of Florida.

226718. This sentence enumerates five discrete experience-

2274related preferences, which are that, (1) in the past five years,

2285the builder should have (2) designed and built school projects

2295(3) on three occasions, (4) in the State of Florida, (5) each of

2308which was a proven success.

231319. The list of experiential preferences in Section 1.1(E)

2322is clearly exclusive, meaning that it does not purport to

2332include other similar or related preferences, but rather is

2341intended to identify all such preferences. This is demonstrated

2350by the absence of any language, such as "including but not

2361limited to" or "among other things," manifesting an intention to

2371include other matters that are ejusdem generis 7 with the items

2382listed.

238320. Notice, too, that of the five experiential

2391preferences, three are purely objective. Specifically,

2397preference nos. 1, 3, and 4 (as numbered herein) are simply

2408matters of historical fact that either happened or did not

2418happen, for reasons wholly extrinsic to the mind of any School

2429Board member. Moreover, the satisfaction of these three

2437experience-related preferences is not a matter of degree: the

2446desired quality is either objectively present, or it is absent;

2456there is no discretionary middle ground. The upshot is that, as

2467between two proposers who, as a matter of fact, have experience

2478satisfying preference nos. 1, 3, and 4, no qualitative

2487distinction can rationally be drawn as to those particulars.

249621. The other two experiential preferences, in contrast,

2504are infused, in varying degrees, with elements of subjectivity.

2513Thus, preference no. 2 allows the individual evaluator some

2522discretion to determine what constitutes a "school project" and,

2531more important, to distinguish qualitatively between one "school

2539project" and another. Preference no. 5 is even more subjective,

2549for "success," like beauty, is in the eye of the beholder.

2560Rational distinctions could be drawn, therefore, between one

2568proposer and another, based on personal (i.e. subjective)

2576assessments of the relative "success" of the respective

2584builders' prior "school projects." 8

258922. In evaluating the five short-listed proposals, seven

2597of the eight participating board members 9 did, in fact, award

2608more points (on some criteria) to proposers that previously have

2618built schools for SBBC (namely Pirtle, Cummings, and Seawood),

2627while deducting or withholding points (on some criteria) from

2636proposers who have not previously done work for SBBC (MCM and

2647Stiles), based on each proposer's status as a former SBBC-

2657contract holder or a newcomer to SBBC contracting. 10 This strong

2668parochial preference most dramatically affected the scoring of

2676the Past Work Performance and References criterion, although

2684some board members also considered a proposer's past work for

2694SBBC (or lack thereof) in scoring Profile & Qualifications of

2704Proposer's Team and even Proposed Project Scheduling. 11

271223. The preference for builders having previous business

2720experience with SBBC had a palpable impact on the scoring and

2731was likely decisive. Although it is impossible to quantify

2740precisely the effect of the parochial preference, its influence

2749can easily be seen in a comparison of the scores awarded, on the

2762criterion of Past Work Performance and References, by the seven

2772board members who favored SBBC-experienced builders:

2778MCM Cummings Pirtle Stiles Seawood

2783Budnick 7 10 10 3 8

2789Gallagher 3 5 10 6 8

2795Kraft 7 9 10 9 9

2801Parks 9 10 10 9 10

2807Rubinstein 5 10 10 8 6

2813Wexler 7 10 10 8 8

2819Williams 5 9 10 5 5

282524. As the table shows, Pirtle, who has performed the most

2836work for SBBC of any of the five competitors, received the

2847maximum score from all seven of the board members who employed

2858the parochial preference. Cummings, whose previous work for

2866SBBC is significant but less extensive than Pirtle's, received

2875an average score of 9 in the past work category. Seawood, which

2887has performed some construction work for SBBC in the past, but

2898not as much as either Pirtle or Cummings, received an average

2909score of 7.71. Stiles and MCM, neither of which has done

2920construction work for SBBC, received average scores of 6.86 and

29306.14, respectively. At bottom, MCM and Stiles received, in the

2940past work category, at least a point less, on average, than the

2952lowest-ranked of the three builders having previous experience

2960with SBBC. Given that three board members (Budnick, Rubinstein,

2969and Wexler) ranked MCM just one point below their respective

2979first choices, the parochial preference could well have

2987determined the result even if its application produced only a

2997small scoring discrepancy in a single evaluative category.

300525. One aspect of the preference for SBBC-experienced

3013builders needs to be repeated for emphasis. The preference was

3023manifested not only as an advantage conferred on builders having

3033such experience, but also as a disadvantage imposed on builders

3043lacking previous experience with SBBC. Builders having worked

3051for SBBC received more points, for that reason, than they would

3062have been awarded, had their previous projects been performed

3071for owners other than SBBC, whereas builders who had not worked

3082for SBBC received fewer points than they would have received, if

3093their previous projects had been built for SBBC. The parochial

3103preference, in other words, operated as a two-edged handicap,

3112making it doubly powerful.

311626. In fact, the preference was so strong that SBBC

3126experience was not, for seven evaluators out of eight, simply a

3137factor to be considered in evaluating a builder's past work; it

3148was effectively a condition of, or a prerequisite to, receiving

3158the total possible points of 100. That is, the effect of the

3170preference was such that unless a builder had previous

3179experience with SBBC, the builder could not receive 10 points in

3190the past work category from most of the board members,

3200regardless of how extensive——and how successful——its experience

3207in building schools for others had been.

321427. In sum, it is determined that the School Board used an

3226undisclosed preference for builders having experience with SBBC

3234in scoring and ranking the proposals, and that the use of this

3246preference had a material effect on the evaluation——probably

3254even deciding the outcome. Indeed, but for the use of this

3265undisclosed preference, there is a good chance (though it is not

3276certain) that MCM would have been the first choice of a majority

3288of the board members. Whether the School Board's conduct in

3298this regard requires that the proposed award to Pirtle be set

3309aside will be taken up in the Conclusions of Law below.

332028. Turning to MCM's other principal contention, it is

3329alleged that Pirtle's proposal deviated materially from the

3337RFP's specifications because Pirtle allegedly failed to comply

3345with the minimum requirements for minority participation in the

3354Project.

335529. On the subject of minority participation, the RFP

3364states, in relevant part:

3368The School Board of Broward County, Florida

3375is committed to affirmatively ensuring a

3381substantial increase in the awarding of

3387construction subcontracts to Minority

3391Businesses. Design/Build firms selected to

3396participate in this RFP must . . . have

3405M/WBE subcontracting goals[,] and [the

3411successful firm must] fully participate in

3417the MBE Program.

3420The M/WBE Contract Goal Range for this

3427project is 20-22 percent.

3431The Proposer should attempt to fulfill the

3438goal with the following ethnic

3443distributions:

3444A. African American 6-8 percent

3449B. Hispanic: 4-5 percent

3453C. White Female 4-6 percent

3458D. Other 0-3 percent

3462The School Board encourages the use of

3469minority subcontractors in excess of the

3475minimum goal ranges established for this

3481project.

3482Section 00030, page 2.

348630. In addition, Section 1.13 requires that the following

3495M/WBE-related information be submitted with a proposal:

3502G. Document 00466 – Statement of Commitment

3509[containing the proposer's pledge to comply

3515with the M/WBE program]

3519H. Document 00470 – Letter of Intent: M/WBE

3527Subcontractor Participation [from each

3531certified minority business that has agreed

3537to participate in the Project, describing

3543the subject of the subcontract and the

3550dollar amount thereof]

35531. Separate Section with a sub tab: M/WBE

3561Participation

3562(a) Briefly discuss how the Proposer will

3569address the M/WBE participation goals.

3574Identify proposed M/WBE team members, their

3580role, and their anticipated percentage of

3586participation. Include past experience with

3591the team.

3593(b) Proposers shall submit evidence of

3599dollar ($) participation for the past two

3606(2) years, both internal and agency

3612documentation of its M/WBE utilization, and,

3618evidence of any M/WBE outreach, internship,

3624and apprenticeship programs it conducts.

3629(c) Proposers, if awarded a contract,

3635shall submit monthly M/WBE Utilization

3640reports on forms provided by The School

3647Board of Broward County, Florida, M/WBE

3653Compliance Office, with each request for

3659payment. Such reports shall also include

3665evidence of dollar participation for the

3671past 2 years, both internal and agency

3678documentation of its M/WBE utilization, and

3684evidence of any M/WBE outreach, internship,

3690and apprenticeship programs it conducts.

3695The foregoing language, which is contained in an addendum to the

3706RFP that was issued on June 16, 2004, supplanted provisions in

3717the first release of the RFP that would have required proposers

3728to submit even more information relating to the satisfaction of

3738M/WBE goals.

374031. Pirtle's proposal clearly complied with Sections

37471.13(G) and 1.13(H)(1)(a)-(c) of the RFP. Where Pirtle fell

3756short, according to MCM, was on the requirement to submit

3766letters of intent from minority subcontractors. Pirtle did, in

3775fact, attach a couple of letters of intent to its proposal——but

3786these showed minimal minority participation, far below the

3794prescribed range of 20-22 percent. MCM contends that proposers

3803were required to submit letters of intent documenting minority

3812participation meeting the M/WBE goals for the Project. Put

3821another way, it is MCM's position each proposer needed to line

3832up most or all of its minority subcontractors before submitting

3842a proposal.

384432. The School Board asserts that proposers were not

3853required to submit all of their letters of intent, but merely

3864some letters as the fruit of good faith efforts to reach the

3876mandated M/WBE goals. 12 The evidence supports the School Board's

3886contention that this was indeed the operative interpretation and

3895understanding of Sections 1.13(G) and 1.13(H). Under this

3903interpretation, a proposal such as Pirtle's that included some

3912letters of intent would be deemed responsive; a paucity or

3922plethora of letters of intent would then be a factor for the

3934evaluators to consider in scoring MBE Participation, a selection

3943criterion worth seven points.

394733. Whether the plain meaning of Section 1.13(H) supports

3956MCM's or the School Board's position, or alternatively whether

3965the School Board's interpretation is clearly erroneous, is a

3974legal question that will be addressed below.

3981CONCLUSIONS OF LAW

398434. DOAH has personal and subject matter jurisdiction in

3993this proceeding pursuant to Sections 120.569, 120.57(1), and

4001120.57(3), Florida Statutes, and the parties have standing.

400935. Pursuant to Section 120.57(3)(f), Florida Statutes,

4016the burden of proof rests with the party opposing the proposed

4027agency action, here MCM. See State Contracting and Engineering

4036Corp. v. Department of Transp. , 709 So. 2d 607, 609 (Fla. 1st

4048DCA 1998). MCM must sustain its burden of proof by a

4059preponderance of the evidence. Florida Dept. of Transp. v.

4068J.W.C. Co., Inc ., 396 So. 2d 778, 787 (Fla. 1st DCA 1981).

408136. Section 120.57(3)(f), Florida Statutes, spells out the

4089rules of decision applicable in bid protests. In pertinent

4098part, the statute provides:

4102In a competitive-procurement protest, other

4107than a rejection of all bids, the

4114administrative law judge shall conduct a de

4121novo proceeding to determine whether the

4127agency's proposed action is contrary to the

4134agency's governing statutes, the agency's

4139rules or policies, or the bid or proposal

4147specifications. The standard of proof for

4153such proceedings shall be whether the

4159proposed agency action was clearly

4164erroneous, contrary to competition,

4168arbitrary, or capricious.

417137. The First District Court of Appeal has construed the

4181term "de novo proceeding," as used in Section 120.57(3)(f),

4190Florida Statutes, to "describe a form of intra-agency review.[ 13 ]

4201The judge may receive evidence, as with any formal hearing under

4212section 120.57(1), but the object of the proceeding is to

4222evaluate the action taken by the agency." State Contracting ,

4231709 So. 2d at 609. In this, the court followed its earlier

4243Intercontinental Properties, Inc. v. State Dept. of Health and

4252Rehabilitative Services , 606 So. 2d 380, 386 (Fla. 1st DCA

42621992), a decision which predates the present version of the bid

4273protest statute, wherein the court had reasoned:

4280Although the hearing before the hearing

4286officer was a de novo proceeding, that

4293simply means that there was an evidentiary

4300hearing during which each party had a full

4308and fair opportunity to develop an

4314evidentiary record for administrative review

4319purposes. It does not mean, as the hearing

4327officer apparently thought, that the hearing

4333officer sits as a substitute for the

4340Department and makes a determination whether

4346to award the bid de novo. Instead, the

4354hearing officer sits in a review capacity,

4361and must determine whether the bid review

4368criteria set . . . have been satisfied.

437638. In framing the ultimate issue to be decided in this de

4388novo proceeding as being "whether the agency's proposed action

4397is contrary to the agency’s governing statutes, the agency's

4406rules or policies, or the bid or proposal specifications," the

4416statute effectively establishes a standard of conduct for the

4425agency, which is that, in soliciting and accepting bids or

4435proposals, the agency must obey its governing statutes, rules,

4444and the project specifications. If the agency breaches this

4453standard of conduct, its proposed action is subject to

4462(recommended) reversal by the administrative law judge in a

4471protest proceeding.

447339. Consequently, the party protesting the intended award

4481must identify and prove, by the greater weight of the evidence,

4492a specific instance or instances where the agency's conduct in

4502taking its proposed action was either: (a) contrary to the

4512agency's governing statutes; (b) contrary to the agency's rules

4521or policies; or (c) contrary to the bid or proposal

4531specifications.

453240. It is not sufficient, however, for the protester to

4542prove merely that the agency violated the general standard of

4552conduct. By virtue of the applicable standards of "proof,"

4561which are best understood as standards of review, 14 the protester

4572additionally must establish that the agency's misstep was: (a)

4581clearly erroneous; (b) contrary to competition; or (c) an abuse

4591of discretion.

459341. The three review standards mentioned in the preceding

4602paragraph are markedly different from one another. The abuse of

4612discretion standard, for example, is more deferential (or

4620narrower) than the clearly erroneous standard. The bid protest

4629review process thus necessarily entails a decision or decisions

4638regarding which of the several standards of review to use in

4649evaluating a particular action. To do this requires that the

4659meaning and applicability of each standard be carefully

4667considered.

466842. The clearly erroneous standard is generally applied in

4677reviewing a lower tribunal's findings of fact. In Anderson v.

4687City of Bessemer City, N.C. , 470 U.S. 564, 573-74 (1985), the

4698United States Supreme Court expounded on the meaning of the

4708phrase "clearly erroneous," explaining:

4712Although the meaning of the phrase "clearly

4719erroneous" is not immediately apparent,

4724certain general principles governing the

4729exercise of the appellate court's power to

4736overturn findings of a [trial] court may be

4744derived from our cases. The foremost of

4751these principles . . . is that "[a] finding

4760is 'clearly erroneous' when although there

4766is evidence to support it, the reviewing

4773court on the entire evidence is left with

4781the definite and firm conviction that a

4788mistake has been committed ." . . . . This

4798standard plainly does not entitle a

4804reviewing court to reverse the finding of

4811the trier of fact simply because it is

4819convinced that it would have decided the

4826case differently. The reviewing court

4831oversteps the bounds of its duty . . . if it

4842undertakes to duplicate the role of the

4849lower court. "In applying the clearly

4855erroneous standard to the findings of a

4862[trial] court sitting without a jury,

4868appellate courts must constantly have in

4874mind that their function is not to decide

4882factual issues de novo. " . . . . If the

4892[trial] court's account of the evidence is

4899plausible in light of the record viewed in

4907its entirety, the court of appeals may not

4915reverse it even though convinced that had it

4923been sitting as the trier of fact, it would

4932have weighed the evidence differently.

4937Where there are two permissible views of the

4945evidence, the factfinder's choice between

4950them cannot be clearly erroneous. . . . .

4959(Citations omitted)(emphasis added).

496243. The Florida Supreme Court has used somewhat different

4971language to give this standard essentially the same meaning:

4980A finding of fact by the trial court in a

4990non-jury case will not be set aside on

4998review unless there is no substantial

5004evidence to sustain it, unless it is clearly

5012against the weight of the evidence, or

5019unless it was induced by an erroneous view

5027of the law. A finding which rests on

5035conclusions drawn from undisputed evidence,

5040rather than on conflicts in the testimony,

5047does not carry with it the same

5054conclusiveness as a finding resting on

5060probative disputed facts, but is rather in

5067the nature of a legal conclusion. . . . .

5077When the appellate court is convinced that

5084an express or inferential finding of the

5091trial court is without support of any

5098substantial evidence, is clearly against the

5104weight of the evidence or that the trial

5112court has misapplied the law to the

5119established facts, then the decision is

5125'clearly erroneous' and the appellate court

5131will reverse because the trial court has

5138'failed to give legal effect to the

5145evidence' in its entirety.

5149Holland v. Gross , 89 So. 2d 255, 258 (Fla. 1956)(citation

5159omitted).

516044. Because administrative law judges are the triers of

5169fact charged with resolving disputed issues of material fact

5178based upon the evidence presented at hearing, and because bid

5188protests are fundamentally de novo proceedings, the undersigned

5196is not required to defer to the letting authority in regard to

5208any findings of objective historical fact that might have been

5218made in the run-up to preliminary agency action. It is

5228exclusively the administrative law judge's job, as the trier of

5238fact, to ascertain from the competent, substantial evidence in

5247the record what actually happened in the past or what reality

5258presently exists, as if no findings previously had been made.

526845. If, however, the challenged agency action involves an

5277ultimate factual determination——for example, an agency's

5283conclusion that a proposal's departure from the project

5291specifications was a minor irregularity as opposed to a material

5301deviation——then some deference is in order, according to the

5310clearly erroneous standard of review. 15 To prevail on an

5320objection to an ultimate finding, therefore, the protester must

5329substantially undermine the factual predicate for the agency’s

5337conclusion or convince the judge that a defect in the agency's

5348logic led it unequivocally to commit a mistake.

535646. There is another species of agency action that also is

5367entitled to review under the clearly erroneous standard:

5375interpretations of statutes for whose administration the agency

5383is responsible, and interpretations of the agency's own rules.

5392See State Contracting and Engineering Corp. v. Department of

5401Transp. , 709 So. 2d 607, 610 (Fla. 1st DCA 1998). In deference

5413to the agency's expertise, such interpretations will not be

5422overturned unless clearly erroneous. Id. 16

542847. This means that if the protester objects to the

5438proposed agency action on the ground that it violates either a

5449governing statute within the agency's substantive jurisdiction

5456or the agency's own rule, and if, further, the validity of the

5468objection turns on the meaning, which is in dispute, of the

5479subject statute or rule, then the agency's interpretation should

5488be accorded deference; the challenged action should stand unless

5497the agency's interpretation is clearly erroneous (assuming the

5505agency acted in accordance therewith). 17

551148. The statute requires that agency action (in violation

5520of the applicable standard of conduct) which is "arbitrary, or

5530capricious" be set aside. Earlier, the phrase "arbitrary, or

5539capricious" was equated with the abuse of discretion standard,

5548see endnote 14, supra , because the concepts are practically

5557indistinguishable——and because use of the term "discretion"

5564serves as a useful reminder regarding the kind of agency action

5575reviewable under this highly deferential standard.

558149. It has been observed that an arbitrary decision is one

5592that is not supported by facts or logic, or is despotic. Agrico

5604Chemical Co. v. State Dept. of Environmental Regulation , 365 So.

56142d 759, 763 (Fla. 1st DCA 1978), cert. denied , 376 So. 2d 74

5627(Fla. 1979). Thus, under the arbitrary or capricious standard,

"5636an agency is to be subjected only to the most rudimentary

5647command of rationality. The reviewing court is not authorized

5656to examine whether the agency's empirical conclusions have

5664support in substantial evidence." Adam Smith Enterprises, Inc.

5672v. State Dept. of Environmental Regulation , 553 So. 2d 1260,

56821273 (Fla. 1st DCA 1989). Nevertheless,

5688the reviewing court must consider whether

5694the agency: (1) has considered all relevant

5701factors; (2) has given actual, good faith

5708consideration to those factors; and (3) has

5715used reason rather than whim to progress

5722from consideration of each of these factors

5729to its final decision.

5733Id.

573450. The second district framed the "arbitrary or

5742capricious" review standard in these terms: "If an

5750administrative decision is justifiable under any analysis that a

5759reasonable person would use to reach a decision of similar

5769importance, it would seem that the decision is neither arbitrary

5779nor capricious." Dravo Basic Materials Co., Inc. v. State Dept.

5789of Transp. , 602 So. 2d 632, 634 n.3 (Fla. 2d DCA 1992). As the

5803court observed, this "is usually a fact-intensive

5810determination." Id. at 634.

581451. Compare the foregoing "arbitrary or capricious"

5821analysis with the test for reviewing discretionary decisions:

"5829Discretion, in this sense, is abused when

5836the judicial action is arbitrary, fanciful,

5842or unreasonable, which is another way of

5849saying that discretion is abused only where

5856no reasonable man would take the view

5863adopted by the trial court. If reasonable

5870men could differ as to the propriety of the

5879action taken by the trial court, then it

5887cannot be said that the trial court abused

5895its discretion."

5897Canakaris v. Canakaris , 382 So. 2d 1197, 1203 (Fla. 1980),

5907quoting Delno v. Market St. Ry. Co. , 124 F.2d 965, 967 (9th Cir.

59201942). Further,

5922[t]he trial court's discretionary power is

5928subject only to the test of reasonableness,

5935but that test requires a determination of

5942whether there is logic and justification for

5949the result. The trial courts' discretionary

5955power was never intended to be exercised in

5963accordance with whim or caprice of the judge

5971nor in an inconsistent manner. Judges

5977dealing with cases essentially alike should

5983reach the same result. Different results

5989reached from substantially the same facts

5995comport with neither logic nor

6000reasonableness.

6001Canakaris , 382 So. 2d at 1203

600752. Whether the standard is called "arbitrary or

6015capricious" or "abuse of discretion," the scope of review, which

6025demands maximum deference, is the same. Clearly, then, the

6034narrow "arbitrary or capricious" standard of review cannot

6042properly be applied in evaluating all agency actions that might

6052be challenged in a bid protest; rather, this highly deferential

6062standard appropriately applies only to those decisions which are

6071committed to the agency's discretion.

607653. Therefore, where the protester objects to agency

6084action that entails the exercise of discretion, but only in such

6095instances, the objection cannot be sustained unless the agency

6104abused its discretion, i.e. acted arbitrarily or capriciously.

611254. The third standard of review articulated in Section

6121120.57(3)(f) is unique to bid protests. The "contrary to

6130competition" test is a catch-all which applies to agency actions

6140that do not turn on the interpretation of a statue or rule, do

6153not involve the exercise of discretion, and do not depend upon

6164(or amount to) a determination of ultimate fact.

617255. Although the contrary to competition standard, being

6180unique to bid protests, is less well defined than the other

6191review standards, the undersigned concludes that the set of

6200proscribed actions should include, at a minimum, those which:

6209(a) create the appearance of and opportunity for favoritism; (b)

6219erode public confidence that contracts are awarded equitably and

6228economically; (c) cause the procurement process to be genuinely

6237unfair or unreasonably exclusive; or (d) are unethical,

6245dishonest, illegal, or fraudulent. See , e.g. , R. N. Expertise,

6254Inc. v. Miami-Dade County School Bd., et al. , Case No. 01-

62652663BID, 2002 WL 185217, *21-*22 (Fla.Div.Admin.Hrgs. Feb. 4,

62732002); see also E-Builder v. Miami-Dade County School Bd. et

6283al. , Case No. 03-1581BID, 2003 WL 22347989, *10

6291(Fla.Div.Admin.Hrgs. Oct. 10, 2003)

629556. Moving on to the merits of the case, as discussed in

6307the Findings of Fact, MCM has proved its charge that the School

6319Board scored the proposals using an undisclosed preference for

6328SBBC-experienced builders. Whether this violated the standard

6335of conduct depends on the meaning of certain provisions of the

6346RFP.

634757. The School Board takes the position that previous

6356experience with SBBC brings added value and hence was a factor

6367that could fairly be considered in scoring the proposals,

6376especially with respect to the Past Work Performance and

6385References criterion, and perhaps also in connection with

6393criterion, Profile & Qualifications of Proposer's Team.

640058. The School Board's position, however, conflates two

6408distinct evaluative processes: (a) evaluating past performance

6415qua past performance and (b) handicapping a proposal based

6424solely on the fact that the proposer had or had not previously

6436worked for SBBC. The former is a merit-based exercise, while

6446the latter is status-based. It is important to separate the two

6457analytically, because there is no dispute that the RFP

6466authorizes (and indeed requires) the evaluators to consider a

6475proposer's relevant past work for SBBC, if any, as part of the

6487proposer's experience. (Such experience, of course, might be

6495advantageous or disadvantageous to the proposer, depending on,

6503among other things, whether SBBC was impressed with its work.)

6513But relevant past work, whether for SBBC or not, can be

6524evaluated as experience without also adding or subtracting

6532points merely because SBBC was or wasn't the owner, which latter

6543is what happened here, and what MCM is complaining about.

655359. It is concluded that giving more points to former

6563SBBC-contract holders and fewer points to other proposers based

6572on their respective statuses in this regard, being a discrete

6582scoring phenomenon, cannot be justified as a function of

6591considering SBBC-specific experience, as experience, in scoring

6598the experience-related evaluation criteria. The question before

6605us, therefore, is not, Is experience building schools for SBBC a

6616relevant factor to consider in scoring past performance? That

6625query practically gives its own affirmative answer. Instead, we

6634must ask: Is it permissible independently to reward (or

6643penalize) a proposer for having (or not having) experience

6652building schools for SBBC, irrespective of the facts surrounding

6661the proposer's past school projects and how well (or how poorly)

6672it designed and built them.

667760. The School Board has conceded that the RFP does not

6688expressly authorize the use of a scoring preference for SBBC-

6698experienced builders; its defense of the preference, to the

6707extent grounded in the language of the RFP, seems to rest on the

6720premises that the RFP does not prohibit the practice, and the

6731broadly worded selection criteria provide a sufficient warrant

6739for the evaluators' actions.

674361. The School Board's argument fails to take account of

6753Section 1.1(E) of the RFP, which lists five specific

6762experiential preferences. See paragraphs 17-21, supra .

6769Repeating them here for convenience, the preferences, as

6777paraphrased, are that (1) in the past five years, the builder

6788should have (2) designed and built school projects (3) on three

6799occasions, (4) in the State of Florida, (5) each of which was a

6812proven success.

681462. These experience-related preferences concern the same

6821subjects as the evaluation criteria, Past Work Performance and

6830References, and Profile & Qualifications of Proposer's Team.

6838Being in pari materia in this regard, Section 1.1(E) and the

6849experience-related evaluation criteria must be construed jointly

6856so as to further the common goal of choosing a suitably

6867qualified and experienced builder. See , e.g. , Mehl v. State ,

6876632 So. 2d 593, 595 (Fla. 1993)(separate statutory provisions

6885that are in pari materia should be construed to express a

6896unified legislative purpose); Lincoln v. Florida Parole Com'n ,

6904643 So. 2d 668, 671 (Fla. 1st DCA 1994)(statutes on same subject

6916and having same general purpose should be construed in pari

6926materia ). That is to say, Section 1.1(E) must be read together

6938with the evaluative criteria, which latter it informs and

6947circumscribes.

694863. In practical terms, this means that in scoring

6957proposals, the evaluators must apply the stated experiential

6965preferences——a point that should not be controversial. Whether

6973evaluators can rely upon other experiential preferences not

6981mentioned depends on the wording of Section 1.1(E).

698964. As explained, the undersigned considers Section 1.1(E)

6997to be unambiguously exclusive, manifesting an intention to

7005identify all applicable experiential preferences. The list of

7013preferred qualities, further, is quite specific. Consequently,

7020the undersigned concludes that the exegetic maxim expressio

7028unius est exclusio alterius provides controlling guidance in

7036interpreting Section 1.1(E). This rule holds that if "one

7045subject is specifically named [in a contract], or if several

7055subjects of a large class are specifically enumerated, and there

7065are no general words to show that other subjects of that class

7077are included, it may reasonably be inferred that the subjects

7087not specifically named were intended to be excluded." Espinosa

7096v. State , 688 So. 2d 1016, 1017 (Fla. 3d DCA 1997)(internal

7107quotation marks omitted); see also , e.g. , Gay v. Singletary , 700

7117So. 2d 1220, 1221 (Fla. 1997)("[W]hen a law expressly describes

7128the particular situation in which something should apply, an

7137inference must be drawn that what is not included by specific

7148reference was intended to be omitted or excluded.")

715765. Here, Section 1.1(E) lists several specific subjects

7165within the larger class of experiential preferences, and there

7174are no general words to show that other specific preferences

7184within that class are included. It is therefore concluded that

7194the subjects (i.e. particular experiential preferences) not

7201specifically named were intended to be excluded. 18

720966. From the foregoing conclusion it follows that the

7218preference for SBBC-experienced builders was not merely

"7225unstated"; it was excluded or rejected. This is because the

7235specific and exclusive geographic-experiential preference was

7241for prior similar work done "in the State of Florida." Section

72521.1(E) clearly and unambiguously puts relevant work completed

7260anywhere in Florida on an equal footing with other such work

7271done elsewhere in the state, with all such in-state work

7281occupying a favored position vis-à-vis work done in other

7290states. And plainly, work done anywhere in Florida comprises

7299work done for every school district in the state——which means

7309that work done for one such district (e.g. Miami-Dade County

7319Public Schools) is no less preferred than work done for another

7330such district (e.g. SBBC).

733467. Accordingly, the undersigned concludes that the

7341evaluators' preference for builders having previous experience

7348with SBBC, which was expressed in the form of a scoring

7359handicap, was contrary to Section 1.1(E) of the RFP 19 and hence

7371violated the applicable standard of conduct. 20

737868. The next question is whether this violation

7386constitutes reversible error under the applicable standard of

7394review, which is, the undersigned concludes, the contrary to

7403competition standard. 21

740669. As an initial observation, a scoring preference for

7415former contract holders, pursuant to which evaluators reward

7423proposers with whom the agency has done business in the past and

7435penalize the other proposers, is suspect on its face. Such a

7446preference undeniably creates the appearance of favoritism and

7454may provide opportunities therefor; favoring those with whom

7462business has been done might also be, depending on the

7472circumstances, unreasonably anticompetitive. This is not to say

7480that a parochial preference can never be valid; but it should

7491usually raise eyebrows.

749470. With that in mind, the undersigned is convinced that

7504to ensure a fair competition, the letting authority should

7513always clearly disclose such a preference in the procurement

7522document. That way, would-be proposers who stand to suffer as a

7533result of the preference at least can attempt to level the

7544playing field before the contest begins by bringing a

7553specifications challenge. That said, however, the undersigned

7560need not conclude here that nondisclosure of a parochial

7569preference is necessarily contrary to competition.

757571. What happened in this case was worse than "mere"

7585nondisclosure, for the RFP informed potential proposers that

7593relevant work completed in one area of Florida would be afforded

7604the same preference as relevant work completed in another area

7614of the state. Thus, not only did potential proposers have no

7625reason to suspect that SBBC's former contract holders would have

7635an advantage; they reasonably should have concluded that SBBC's

7644former contract holders would have no advantage (simply on the

7654basis of having previously done work for SBBC) over proposers

7664who had built schools in Florida for other owners. It almost

7675goes without saying that proposers such as MCM had no reason to

7687bring a specifications protest to object to a preference that

7697the RFP excludes.

770072. In sum, it is concluded that a status-based scoring

7710preference for former contract holders, implemented via giving

7718additional points to favored proposers while taking points away

7727from disfavored proposers, is contrary to competition where, as

7736here, the RFP contains an unambiguous, exclusive list of other

7746specific experiential preferences, manifesting an intention to

7753exclude the very preference utilized.

775873. MCM's contention that Pirtle's proposal was

7765nonresponsive to the RFP turns on a disputed interpretation of

7775Section 1.13(H), raising the question whether that provision

7783required proposers to submit some letters of intent (as the

7793School Board maintains) or, alternatively, enough such letters

7801to document that the M/WBE goals for the Project would be met

7813(as MCM insists).

781674. The undersigned concludes that Section 1.13(H) is

7824ambiguous in this regard, for it is effectively silent on the

7835subject of how many letters of intent must be included with a

7847proposal. 22 MCM argues persuasively that the requirement of

7856including letters of intent makes little sense if a proposer can

7867comply by attaching documents showing de minimis minority

7875participation. On the other hand, Section 1.13(H)(1)(a)

7882requires a forward-looking statement describing how the M/WBE

7890participation goals will be met——a statement that arguably would

7899be superfluous if letters of intent coinciding with the minority

7909goals were also supposed to be attached to the proposal. As

7920well, the information required under Section 1.13(H)(1)(b),

7927which asks for evidence of the proposer's historical use of

7937minority subcontractors, would seem to be irrelevant, if

7945proposers were otherwise obligated to document sufficient

7952arrangements for minority participation in the instant Project

7960to meet the prescribed goals. Consequently, the School Board's

7969interpretation is reasonable, too.

797375. It is concluded, therefore, that the School Board's

7982interpretation of Section 1.13(H), while not necessarily the

7990best reading of the text, is at least a permissible one and thus

8003not clearly erroneous. That being the case, it cannot be said,

8014in this proceeding, that Pirtle's proposal deviated materially

8022from the RFP specifications.

802676. Finally, MCM has complained about other sundry

"8034scoring anomalies," which the undersigned has declined to

8042detail herein. Suffice it to say that MCM has pointed to

8053several discrete scoring decisions that reasonable people could

8061second-guess. However, given the wide latitude that evaluators

8069are afforded under the RFP to assign the points allotted to the

8081various evaluation criteria, the undersigned concludes that none

8089of these alleged "anomalies" constituted an abuse of discretion.

8098RECOMMENDATION

8099Based on the foregoing Findings of Fact and Conclusions of

8109Law, it is RECOMMENDED that a Final Order be entered that

8120rescinds the proposed award to Pirtle. In addition, while

8129recognizing that the choice of remedies for invalid procurement

8138actions is within the agency's discretion, it is nevertheless

8147recommended that a meeting be convened for the purposes of

8157reassigning points to each proposer using the published

8165selection criteria, re-ranking each proposer according to its

8173respective scores, and awarding the contract to the firm that

8183receives a majority of the first choice votes.

8191DONE AND ENTERED this 21st day of March, 2005, in

8201Tallahassee, Leon County, Florida.

8205___________________________________

8206JOHN G. VAN LANINGHAM

8210Administrative Law Judge

8213Division of Administrative Hearings

8217The DeSoto Building

82201230 Apalachee Parkway

8223Tallahassee, Florida 32399-3060

8226(850) 488-9675 SUNCOM 278-9675

8230Fax Filing (850) 921-6847

8234www.doah.state.fl.us

8235Filed with the Clerk of the

8241Division of Administrative Hearings

8245this 21st day of March, 2005.

8251ENDNOTES

82521 / With the exception of Messrs. Munilla and Cotilla,

8262Petitioner's witnesses were the board members who had evaluated

8271the proposals and voted to award the contract to Intervenor.

8281(At the time of the final hearing, Ms. Wexler and Ms. Budnick

8293were no longer board members.) Given the role that these

8303individuals played in the events giving rise to this protest,

8313the testimony of the board members was critical to the case;

8324indeed, the undersigned relied heavily on this testimony in

8333making the findings of fact herein. A nontrivial question

8342therefore arises as to whether a substitute agency head should

8352be appointed to review this Recommended Order and issue the

8362Final Order. See Ridgewood Properties, Inc. v. Department of

8371Community Affairs , 562 So. 2d 322, 324 (Fla. 1990)(when agency

8381head testifies to material fact in administrative hearing, due

8390process requires that review of the recommended order be

8399undertaken by neutral, disinterested third party); see also

8407§ 120.665, Fla. Stat. (disqualification of agency head for bias,

8417prejudice, or interest); but see Optiplan, Inc. v. School Bd. of

8428Broward County , 710 So. 2d 569, 572 (Fla. 4th DCA 1998)(fact

8439that two board members testified in bid protest hearing did not

8450require disqualification of entire board). To be sure, there

8459are grounds for arguing that Ridgewood , on the one hand, or

8470Optiplan on the other, is distinguishable from the instant case,

8480and the undersigned expresses no opinion herein on the merits of

8491the constitutional issue. It is recommended, however, that the

8500matter be addressed in the first instance at the agency level.

85112 / The term "School Board" will be used herein when reference to

8524the nine-member collegial body that governs the Broward County

8533district school system is intended. The term "SBBC" will be

8543used when referring generally to the district school system as

8553an institution or entity; hence, as used herein, "SBBC" is meant

8564to denote not only the members of the School Board, but also any

8577of the employees and agents of the Broward County School

8587District through whom the district acted.

85933 / This sentence echoes Section 1.1(B) of the RFP, which states:

"8605The School Board of Broward County, Florida intends to award a

8616design/build contract to the design/build firm receiving the

8624majority of School Board Members first choice votes based upon

8634point scores in the selection process . . . ."

86444 / School Board Member Carole Andrews was not present.

86545 / The RFP clearly and unambiguously provides that the contract

8665will be awarded, if at all, to the proposer receiving the

8676majority of the first choice votes. In the context of vote

8687counting, the term "majority" is commonly understood to mean

8696more than half. Pirtle received four votes out of eight, which

8707constitutes a plurality , not a majority. It is highly doubtful,

8717moreover, that the RFP contemplates awarding the contract to the

8727recipient of a mere plurality of first choice votes. Imagine,

8737for example, that all nine board members had voted, and the

8748result was three first choice votes for one proposer (say,

8758Pirtle), with two first choice votes apiece for three other

8768proposers. In that situation, Pirtle would have a plurality of

8778the first choice votes but would not be the first choice of a

8791majority of the members. To award the contract to Pirtle in

8802such a situation would defy the plain language of the RFP, which

8814was designed to prevent the School Board from awarding the

8824contract to a builder whom the majority had found less suitable

8835than other candidates. As in the hypothetical, Pirtle in fact

8845had a plurality of first choice votes but was not the first

8857choice of a majority of members and thus at least arguably

8868should not have been chosen for the award unless and until it

8880picked up another first choice vote——which could have proved

8889difficult, since none of the four members whose first choice was

8900not Pirtle had ranked that builder higher than third .

8910Fortunately for SBBC, MCM failed to object to the proposed award

8921on this ground and hence waived the issue. Still, the School

8932Board might want to take note of the problem for future

8943reference.

89446 / "M/WBE," which is sometimes also rendered "MBE," is an

8955acronym for Minority and Women Business Enterprises.

89627 / See generally Green v. State , 604 So. 2d 471, 473 (Fla.

89751992)("Under the doctrine of ejusdem generis, where an

8984enumeration of specific things is followed by some more general

8994word, the general word will usually be construed to refer to

9005things of the same kind or species as those specifically

9015enumerated."); see also Robbie v. Robbie , 788 So. 2d 290, 293

9027n.7 (Fla. 4th DCA 2000)(When, in implementing a non-exhaustive

9036statutory listing, the use of an unenumerated criterion is

9045indicated, "that ad hoc factor will have to bear a close

9056affinity with those enumerated in the statute——i.e., the factor

9065employed must be ejusdem generis with the enumerated ones.").

90758 / An evaluator's subjective judgments on preference nos. 2 or 5

9087could affect objective preference no. 3, if it were determined

9097that some particular past work of a proposer was not a "school

9109project" or was unsuccessful.

91139 / Board Member Darla Carter evidently saw no substantial

9123differences between the proposals, for she awarded the maximum

9132points in every category to all the proposers, except that she

9143awarded Seawood only six (out of seven) points on the criterion,

9154MBE Participation. This had the effect of making the S.I.T.

9164Award——which was determined mathematically by staff——decisive in

9171her ranking of the proposals. Because MCM and Cummings were

9181each awarded 15 points (the maximum) on the S.I.T. Award, Ms.

9192Carter had them tied at 100 points apiece. Breaking the tie,

9203Ms. Carter awarded her first choice vote to MCM.

921210 / Board Member Judie Budnick added a unique twist to the

9224preference for SBBC-experienced builders. She testified

9230candidly that a proposer could not get the maximum points from

9241her in connection with the experience-related evaluative

9248criteria unless the proposer had "paid its dues" by making

9258charitable contributions for the benefit of, or otherwise doing

9267good works for, the children of Broward County.

927511 / The use of a particular consideration to "double-dip" (or

"9286triple-dip") across the lines of evaluation criteria was not

9296limited to the parochial preference. A number of board members,

9306for example, cited the fact that MCM had not previously worked

9317as a team with its designated architectural firm as a reason for

9329deducting points from MCM's score in the Profile &

9338Qualifications of Proposer's Team category as well as from its

9348score on Past Work Performance and References. Such double-

9357dipping is problematic because it tends to subvert the relative

9367weight of the evaluation criteria as published in the RFP,

9377arbitrarily magnifying the importance of the cross-criterion

9384consideration. Because MCM did not object to the practice,

9393however, it will not be further addressed.

940012 / The School Board's position is consistent with, if not

9411directly supported by, Section 1.28(B) of the RFP, which

9420requires the successful proposer to submit to SBBC, within 10

9430consecutive calendar days after receiving notice of the contract

9439award, a list of all subcontractors for principal portions of

9449the Project, on a prescribed form known as Document 00433.

945913 / Because DOAH is always independent of the letting authority,

9470see § 120.65(1), Florida Statutes, it might be preferable to

9480label bid protests before DOAH a form of inter -agency review or,

9492alternatively, intra-branch review; however, because the letting

9499authority itself ultimately renders the final order, the first

9508district’s nomenclature is not incorrect.

951314 / The term "standard of proof" as used in § 120.57(3)(f)

9525reasonably may be interpreted to reference standards of review .

9535This is because, while the "standard of proof" sentence fails to

9546mention any common standards of proof, it does articulate two

9556accepted standards of review: (1) the "clearly erroneous"

9564standard and (2) the abuse of discretion (= "arbitrary, or

9574capricious") standard. (The "contrary to competition"

9581standard——whether it be a standard of proof or standard of

9591review——is unique to bid protests.)

959615 / An ultimate factual determination is a conclusion derived by

9607reasoning from objective facts; it frequently involves the

9615application of a legal principle or rule to historical facts:

9625e.g. the driver failed to use reasonable care under the

9635circumstances and therefore was negligent; and it may be infused

9645with policy considerations. Reaching an ultimate factual

9652finding requires that judgment calls be made which are unlike

9662those that attend the pure fact finding functions of weighing

9672evidence and choosing between conflicting but permissible views

9680of reality.

968216 / From the general principle of deference follows the more

9693specific rule that an agency's interpretation need not be the

9703sole possible interpretation or even the most desirable one; it

9713need only be within the range of permissible interpretations.

9722State Bd. of Optometry v. Florida Soc. of Ophthalmology , 538 So.

97332d 878, 885 (Fla. 1st DCA 1988); see also Suddath Van Lines,

9745Inc. v. State Dept. of Environmental Protection , 668 So. 2d 209,

9756212 (Fla. 1st DCA 1996). However, "[t]he deference granted an

9766agency's interpretation is not absolute." Department of Natural

9774Resources v. Wingfield Development Co. , 581 So. 2d 193, 197

9784(Fla. 1st DCA 1991). Obviously, an agency cannot implement any

9794conceivable construction of a statute or rule no matter how

9804strained, stilted, or fanciful it might be. Id. Rather, "only

9814a permissible construction" will be upheld by the courts.

9823Florida Soc. of Ophthalmology , 538 So. 2d at 885. Accordingly,

"9833[w]hen the agency's construction clearly contradicts the

9840unambiguous language of the rule, the construction is clearly

9849erroneous and cannot stand." Woodley v. Department of Health

9858and Rehabilitative Services , 505 So. 2d 676, 678 (Fla. 1st DCA

98691987); see also Legal Environmental Assistance Foundation v.

9877Board of County Com'rs of Brevard County , 642 So. 2d 1081, 1083-

988984 (Fla. 1994)("unreasonable interpretation" will not be

9897sustained).

989817 / The same standard of review also applies, in a protest

9910following the announcement of an intended award, with regard to

9920preliminary agency action taken upon the agency's interpretation

9928of the project specifications——but perhaps for a reason other

9937than deference to agency expertise. Section 120.57(3)(b),

9944Florida Statutes, provides a remedy for badly written or

9953ambiguous specifications: they may be protested within 72 hours

9962after the posting of the specifications. The failure to avail

9972oneself of this remedy effects a waiver of the right to complain

9984about the specifications per se. Consequently, if the dispute

9993in a protest challenging a proposed award turns on the

10003interpretation of an ambiguous, vague, or unreasonable

10010specification, which could have been corrected or clarified

10018prior to acceptance of the bids or proposals had a timely

10029specifications protest been brought, and if the agency has acted

10039thereafter in accordance with a permissible interpretation of

10047the specification (i.e. one that is not clearly erroneous), then

10057the agency's intended action should be upheld——not necessarily

10065out of deference to agency expertise, but as a result of the

10077protester's waiver of the right to seek relief based on a faulty

10089specification. If, however, the agency has acted contrary to

10098the plain language of a lawful specification, then its action

10108should probably be corrected, for in that event the preliminary

10118agency action likely would be clearly erroneous or contrary to

10128competition; in that situation, there should be no waiver,

10137because a reasonable person would not protest an unambiguous

10146specification that facially conforms to Florida procurement law.

1015418 / The School Board has not advanced a contrary interpretation

10165of Section 1.1(E), and there is no evidence that the evaluators

10176construed this section as authority for giving or withholding

10185points based on whether a proposer previously had done work for

10196SBBC. In any event, the undersigned concludes as a matter of

10207law that Section 1.1(E) is not ambiguous, and alternatively, if

10217it were, construing the pertinent provisions of the RFP to

10227authorize the parochial preference would be clearly erroneous.

1023519 / The preference, as applied, also ran afoul of Section

102461.20(B), which states that points will be awarded, "up to a

10257maximum, for evaluation criteria listed [in Section 1.20(A).]"

10265In fact, due to the preference, only builders who had previously

10276done work for SBBC could receive the maximum points on the

10287experience-related evaluative criteria, because builders without

10293such experience automatically had points taken away for that

10302reason.

1030320 / Board Member Budnick's singular preference for meritorious

10312works in favor of Broward's children finds no support in the

10323stated evaluation criteria and cannot be grounded in Section

103321.1(E) or any other provision of the RFP. Consequently,

10341awarding or withholding points based on a proposer's charitable

10350contributions, as Ms. Budnick admittedly did, was ultra vires

10359and contrary to the RFP.

1036421 / There are no ultimate factual determinations or agency

10374interpretations to review under the clearly erroneous standard,

10382and evaluators do not have discretion to apply scoring

10391preferences in contravention of the RFP.

1039722 / The provision refers only to a letter of intent (singular)

10409and hence, read literally, would require only one such letter.

10419Such a construction, however, while perhaps plausible, seems a

10428bit mechanical, and in any event is not the interpretation put

10439forward by the School Board.

10444COPIES FURNISHED :

10447J. Alfredo De Armas, Esquire

10452Alvarez, De Armas & Borron, P. A.

104593211 Ponce De Leon Boulevard, Suite 302

10466Coral Gables, Florida 33134

10470Robert Paul Vignola, Esquire

10474School Board of Broward County

10479K. C. Wright Administrative Building

10484600 Southeast Third Avenue, 11th Floor

10490Fort Lauderdale, Florida 33301

10494Kevin A. Fernander, Esquire

10498Tripp Scott, P. A.

10502AutoNation Tower, 15th Street

10506110 Southeast Sixth Street

10510Fort Lauderdale, Florida 33301

10514John Winn, Commissioner

10517Department of Education

10520Turlington Building, Suite 1514

10524325 West Gaines Street

10528Tallahassee, Florida 32399-0400

10531Dr. Franklin L. Till, Jr.

10536Superintendent

10537Broward County School Board

10541600 Southeast Third Avenue

10545Fort Lauderdale, Florida 33301-3125

10549Daniel J. Woodring, General Counsel

10554Department of Education

10557325 West Gaines Street

105611244 Turlington Building

10564Tallahassee, Florida 32399-0400

10567NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

10573All parties have the right to submit written exceptions within

1058310 days from the date of this Recommended Order. Any exceptions

10594to this Recommended Order should be filed with the agency that

10605will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 04/27/2005
Proceedings: Agency Final Order filed.
PDF:
Date: 04/22/2005
Proceedings: Agency Final Order
PDF:
Date: 04/12/2005
Proceedings: MCM`s Withdrawal of Motion for Attorney`s Fees and Suggestion of Mootness filed.
PDF:
Date: 03/30/2005
Proceedings: MCM`s Motion for Attorney`s Fees Pursuant to Recommended Order Entered March 21, 2005 filed.
PDF:
Date: 03/21/2005
Proceedings: Recommended Order
PDF:
Date: 03/21/2005
Proceedings: Recommended Order (hearing held January 19 and 20, 2005). CASE CLOSED.
PDF:
Date: 03/21/2005
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 03/01/2005
Proceedings: Respondent School Board`s Proposed Recommended Order filed.
PDF:
Date: 03/01/2005
Proceedings: Proposed Findings of Fact and Rulings of Law filed.
PDF:
Date: 03/01/2005
Proceedings: MCM`s Notice of Filing Proposed Findings and Rulings of Law filed.
PDF:
Date: 03/01/2005
Proceedings: Intervenor James B. Pirtle Construction`s Proposed Recommended Order.
PDF:
Date: 03/01/2005
Proceedings: Intervenor James B. Pirtle Construction`s Proposed Recommended Order.
PDF:
Date: 02/09/2005
Proceedings: Order Regarding Proposed Recommended Orders (proposed recommended orders shall be filed on or before March 1, 2005).
Date: 02/09/2005
Proceedings: Transcript (Volumes I-II) filed.
PDF:
Date: 02/09/2005
Proceedings: Respondent School Board`s Notice of Filing Transcripts filed.
PDF:
Date: 01/27/2005
Proceedings: Re-notice of Taking Deposition filed.
PDF:
Date: 01/26/2005
Proceedings: Letter to Judge Van Laningham from R. Vignola enclosing exhibits filed.
Date: 01/19/2005
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 01/18/2005
Proceedings: Motion to Appear Telephonically or in the Alternative by Video Conference filed.
PDF:
Date: 01/14/2005
Proceedings: Second Notice of Hearing (hearing set for January 19 and 20, 2005; 11:00 a.m.; Fort Lauderdale).
PDF:
Date: 01/14/2005
Proceedings: Joint Pre-hearing Stipulation filed.
PDF:
Date: 01/13/2005
Proceedings: Statement of Position (filed by K. Fernander).
PDF:
Date: 01/13/2005
Proceedings: Intervenor, James B. Pirtle Construction`s Witness and Exhibits List filed.
PDF:
Date: 01/13/2005
Proceedings: Notice of Taking Deposition filed.
PDF:
Date: 01/13/2005
Proceedings: Magnum Construction Management Corporation`s Witness and Exhibit List filed.
PDF:
Date: 01/12/2005
Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for January 19 and 20, 2005; 9:00 a.m.; Fort Lauderdale).
PDF:
Date: 01/11/2005
Proceedings: Re-Notice of Taking Depositions (filed via facsimile).
PDF:
Date: 01/10/2005
Proceedings: Notice of Taking Deposition filed.
PDF:
Date: 01/10/2005
Proceedings: Respondent School Board`s Second Request to Produce to Petitioner MCM Corp. filed.
PDF:
Date: 01/10/2005
Proceedings: Notice of Taking Depositions filed.
PDF:
Date: 01/07/2005
Proceedings: Joint Motion to Continue Hearing Date By One Day filed.
PDF:
Date: 01/07/2005
Proceedings: Notice of Taking Depositions filed.
PDF:
Date: 01/06/2005
Proceedings: Re-Notice of Taking Deposition filed.
PDF:
Date: 01/06/2005
Proceedings: Joint Motion to Continue Hearing Date by One Day filed.
PDF:
Date: 01/05/2005
Proceedings: Notice of Taking Deposition filed.
PDF:
Date: 01/05/2005
Proceedings: Magnum Construction Management Corporation`s Witness & Exhibits List filed.
PDF:
Date: 12/30/2004
Proceedings: Order Granting Petition to Intervene (James B. Pirtle Construction Company, Inc.) .
PDF:
Date: 12/30/2004
Proceedings: Order Granting Petition to Intervene (James B. Pirtle Construction Company, .
PDF:
Date: 12/27/2004
Proceedings: Notice of Taking Deposition (R. Parks and L. Wexler) filed.
PDF:
Date: 12/21/2004
Proceedings: Respondent School Board`s First Request to Produce to Petitioner MCM Corp filed.
PDF:
Date: 12/21/2004
Proceedings: Respondent School Board`s First Request to Produce to Petitioner MCM Corp filed.
PDF:
Date: 12/21/2004
Proceedings: Respondent School Board`s Set of Interrogatories to Petitioner MCM Corp. filed.
PDF:
Date: 12/20/2004
Proceedings: Respondent School Board`s Notice of Unavailability filed.
PDF:
Date: 12/08/2004
Proceedings: Respondent School Board`s Notice of Compliance filed.
PDF:
Date: 12/07/2004
Proceedings: James B Pirtle Construction Company, Inc.`s Petition for Leave to Intervene filed.
PDF:
Date: 12/01/2004
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 12/01/2004
Proceedings: Notice of Hearing (hearing set for January 18 and 19, 2005; 9:00 a.m.; Fort Lauderdale, FL).
PDF:
Date: 11/30/2004
Proceedings: Joint Stipulation for date and Location of Formal Hearing filed.
PDF:
Date: 11/22/2004
Proceedings: Bid Protest Bond (filed via facsimile).
PDF:
Date: 11/22/2004
Proceedings: Letter to Clerk of the Board from J. Armas pertaining to notice of bid protest (filed via facsimile).
PDF:
Date: 11/22/2004
Proceedings: Letter to Mr. Herrmann from P. Munilla requesting to refer Protest to Division of Administrative Hearings (filed via facsimile).
PDF:
Date: 11/19/2004
Proceedings: Agency referral (filed via facsimile).

Case Information

Judge:
JOHN G. VAN LANINGHAM
Date Filed:
11/19/2004
Date Assignment:
01/14/2005
Last Docket Entry:
04/27/2005
Location:
Coral Gables, Florida
District:
Southern
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Counsels

Related DOAH Cases(s) (2):

Related Florida Statute(s) (4):