1(1) 2A State of Florida Well Completion Report, DEP Form 1162-532.900(2), 12(October 7, 2010), which is incorporated by reference in paragraph 40C-3.036(9)(b), 23F.A.C., 24is 25required for the construction, repair or abandonment of all wells regardless of whether a permit is required under Rule 4440C-3.041, 45F.A.C. Well completion reports shall be 51completed and 53filed 54at a 56District 57office identified in Rule 6140C-3.101, 62F.A.C., at the District’s website floridaswater.com, 68or with the entity to which the authority to issue a permit has been delegated, 83as identified in Rule 8740C-3.035, 88F.A.C89., 90by the contractor within 30 days of the completion of the work.
102(a) Well completion reports for sites controlled by Chapter 62-761, F.A.C., may include all monitoring wells for the same site on a single form.
126(b) Computer generated completion reports developed by the contractor may be used in place of District supplied forms if these reports have been approved by the District prior to use.
156(2) The water well contractor shall keep or cause to be kept by a person in his employ a field log. Such records shall be available for inspection by the District at the site during all times when actual work is in progress.
199(3) If no work is performed or if the well is not completed, a report shall be filed by the contractor within thirty days of the expiration of the permit stating that no well construction was performed or completed under the permit.
241Rulemaking Authority 243373.044, 244373.113 FS. 246Law Implemented 248373.308, 249373.309, 250373.313, 251373.326, 252373.342 FS. 254History–New 10-14-84, Formerly 25740C-3.411, 25840C-3.0411, Amended 9-17-89, 7-27-16.