To implement Section 366.96, FS, which was passed by the Florida Legislature in the 2019 session. Section 366.96, FS, requires public electric utilities to file storm protection plans with the Commission and allows a public electric utility to ...  

  •  

    PUBLIC SERVICE COMMISSION

    RULE NOS: RULE TITLES

    Rule 25-6.0143              Use of Accumulated Provision Accounts 228.1, 228.2, and 228.4

    Rule 25-6.030              Storm Protection Plan

    Rule 25-6.031              Storm Protection Plan Cost Recovery Clause

    Rule 25-6.034              Standard of Construction

    Rule 25-6.0341              Location of the Utility’s Electric Distribution Facilities

    Rule 25-6.0342              Electric Infrastructure Storm Hardening

    Rule 25-6.0343Municipal Electric Utility and Rural Electric Cooperative Reporting Requirements

    Rule 25-6.0345Safety Standards for Construction of New Transmission and Distribution Facilities

    Rule 25-6.044Continuity of Service

    Rule 25-6.0455Annual Distribution Service Reliability Report

    Rule 25-6.061Relocation of Poles

    Rule 25-6.064Contribution-in-Aid-of-Construction for Installation of New or Upgraded Facilities

    Rule 25-6.077Installation of Underground Distribution Systems within New Subdivisions

    Rule 25-6.078Schedule of Charges

    Rule 25-6.081Construction Practices

    Rule 25-6.115Facility Charges for Conversion of Existing Overhead Investor-owned Distribution Facilities

    PURPOSE AND EFFECT: To implement Section 366.96, FS, which was passed by the Florida Legislature in the 2019 session. Section 366.96, FS, requires public electric utilities to file storm protection plans with the Commission and allows a public electric utility to petition for cost recovery annually through a storm plan cost recovery clause. To adopt new rules and to determine whether existing rules should be amended or repealed to implement Section 366.96, FS.

    Undocketed

    SUBJECT AREA TO BE ADDRESSED: Public electric utility storm protection plans and storm protection cost recovery clause.

    RULEMAKING AUTHORITY: 350.127(2), 366.05(1), 366.96, FS.

    LAW IMPLEMENTED: 350.115, 366.03, 366.04(1), (2), (4)–(6), 366.041(1), (4), 366.05(1), (7), 366.06(1), 366.96, FS.

    A RULE DEVELOPMENT WORKSHOP WILL BE HELD AT THE DATE, TIME, AND PLACE SHOWN BELOW:

    DATE AND TIME: Tuesday, June 25, 2019, 9:30 a.m.

    PLACE:  Room 148, Betty Easley Conference Center, 4075 Esplanade Way, Tallahassee, Florida. 

    One or more Commissioners may be in attendance and participate in the workshop. In accordance with the Americans with Disabilities Act, persons needing a special accommodation to participate at this workshop should contact the Office of Commission Clerk no later than five days prior to the workshop at 2540 Shumard Oak Boulevard, Tallahassee, Florida 32399-0850 or (850)413-6770 (Florida Relay Service, 1(800)955-8770 Voice or 1-(800)955-8771 TDD).  Assisted Listening Devices are available upon request from the Office of Commission Clerk, Gerald L. Gunter Building, Room 152.

    THE PERSONS TO BE CONTACTED REGARDING THE PROPOSED RULE DEVELOPMENT AND A COPY OF THE PRELIMINARY DRAFT, IF AVAILABLE, ARE: Adria Harper, (850)413-6082, aharper@psc.state.fl.us or Andrew King, (850)413-6195, aking@psc.state.fl.us. A copy of the agenda and materials for the workshop will be posted on the Commission’s website, www.floridapsc.com, under the Rule Development tab on June 11, 2019.

    THE PRELIMINARY TEXT OF THE PROPOSED RULE DEVELOPMENT IS AVAILABLE AT NO CHARGE FROM THE CONTACT PERSONS LISTED ABOVE.

Document Information

Subject:
Public electric utility storm protection plans and storm protection cost recovery clause.
Purpose:
To implement Section 366.96, FS, which was passed by the Florida Legislature in the 2019 session. Section 366.96, FS, requires public electric utilities to file storm protection plans with the Commission and allows a public electric utility to petition for cost recovery annually through a storm plan cost recovery clause. To adopt new rules and to determine whether existing rules should be amended or repealed to implement Section 366.96, FS. Undocketed
Rulemaking Authority:
350.127(2), 366.05(1), 366.96, FS
Law:
350.115, 366.03, 366.04(1), (2), (4)–(6), 366.041(1), (4), 366.05(1), (7), 366.06(1), 366.96, FS
Related Rules: (15)
25-6.0143. Use of Accumulated Provision Accounts 228.1, 228.2, and 228.4
25-6.030. Storm Protection Plan
25-6.031. Storm Protection Plan Cost Recovery Clause
25-6.034. Standard of Construction
25-6.0341. Location of the Utility’s Electric Distribution Facilities